This is a Request for Information (RFI) Tracking Log for Solicitation #36C24826R0057, a Design-Build (DB) contract for connecting reclaim water at the Lake Baldwin Campus. The document contains three related RFIs and VA responses regarding site plans and utility connection points for integrating the City of Orlando's incoming reuse utility feed with the VA's Lake Baldwin facility irrigation system.
All three RFIs request VA-issued site plans showing specific information about the connection location and path of the City of Orlando's reclaim water utility feed. The VA's uniform response to all three inquiries indicates that the final connection location will be determined by the Design-Build team's engineer rather than being specified by the VA in advance. The VA provided a reference PDF Site Layout but clarified it is for reference only and does not establish final connection points. The response directs the D/B team to confirm the layout and connection of the existing irrigation line, which is currently supplied by a well water connection believed to be located in the existing gravel lot. The connection shall be transitioned from well water to the city's reclaim water line. The VA notes that the engineer may contact the Orlando Utility Commission (OUC) to obtain GIS data of existing utilities in the right-of-way (ROW).
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information (RFI) Tracking Log
Solicitation#36C24826R0057 Design-Build (DB) Connect Reclaim Water at Lake Baldwin Campus
RFI Tracking Log
RFI
NBR. QUESTIONS & ANSWERS
1. Can the VA issue a site plan with the piping size & path locations of the City of Orlando’s incoming reuse utility feed on the VA Lake Baldwin facility ?
VA Response Final connection location is to be determined by the D/B’s engineer. A PDF of the Site Layout has been provided for reference. This plan is for reference only. D/B team to confirm layout and connection of existing irrigation line. The Irrigation is currently supplied from a well water connection that is believed to be in the existing gravel lot. Connection shall be made from well water to the cities reclaim water line. Engineer may reach out to Orlando Utility Commission (OUC) for GIS of existing utilities in their ROW.
2. Can the VA issue on this site plan of the VA proposed possible connection point location to the City of Orlando’s incoming reuse utility feed?
VA Response Final connection location is to be determined by the D/B’s engineer. A PDF of the Site Layout has been provided for reference. This plan is for reference only. D/B team to confirm layout and connection of existing irrigation line. The Irrigation is currently supplied from a well water connection that is believed to be in the existing gravel lot. Connection shall be made from well water
3. Can the VA issue a site plan with the VA proposed possible location of the connection of the City of Orlando’s incoming reuse utility feed to the VA site irrigation system?
VA Response Final connection location is to be determined by the D/B’s engineer. A PDF of the Site Layout has been provided for reference. This plan is for reference only. D/B team to confirm layout and connection of existing irrigation line. The Irrigation is currently supplied from a well water connection that is believed to be in the existing gravel lot. Connection shall be made from well water