About this file

This is an architectural drawing and construction specification document for renovation work at James A. Haley VA Hospital located at 13000 Bruce B. Downs Boulevard, Tampa, Florida 33612. The project, titled "AE Renovate Ground Floor Halls and Walls," is identified as Project Number 673-21-153 and Drawing Number AS.100, with a final submittal date of September 20, 2024.

The document outlines general construction requirements and phasing notes for ground floor renovation work. Key contractual requirements include: all changes must receive Contracting Officer Representative (COR) approval before proceeding; work must be performed during regular day shift hours (8:00 AM–4:30 PM) unless otherwise approved; contractor must coordinate staging areas and secure covered interior storage for weather-sensitive materials with the COR; and all work must comply with VHA Directive 2004-012 (Safety and Health During Construction Activities) and VHA Directive 7701 (Occupational Safety and Health). The contractor is responsible for verifying all details against existing site conditions prior to equipment purchase and construction, and must immediately report any discrepancies between plans and actual conditions to the COR. Work must follow VA Master Construction Specifications, with the more stringent requirement applied where discrepancies exist. The floor plan indicates multiple discrete areas of work throughout the ground floor, with temporary infection control barriers required based on project duration, ranging from plastic sheeting for single-day work to metal-stud construction with gypsum board for longer durations. All hospital access points and building exits must remain clear and accessible throughout construction phases, with temporary rated doors and frames required at construction area entry points.

View the file

Other files

File Type Posted
Pages from Bldg 1 Life Safety3.pdf PDF
Plumbing - Bldg 1 ground3.pdf PDF
Electrical - Bldg 1 Ground3.pdf PDF
Pages from Bldg 1 Life Safety 3-1.pdf PDF
05 673-21-153 BB SOW rev RFI update.docx DOCX document
site visit2.pdf PDF
1-S6.pdf PDF
1-S18.pdf PDF
1-S7.pdf PDF
1-S4B.pdf PDF
TUG MAP - TampaGroundFloor.png PNG image
1-S9.pdf PDF
1-S1.pdf PDF
1-S15.pdf PDF
1-S12.pdf PDF
1-S5.pdf PDF
673-21-153_HallsAndWalls_Drawings RFI Update.pdf PDF
1-S16.pdf PDF
1-S13.pdf PDF
1-S4A.pdf PDF
1-S14 1.pdf PDF
1-S21.pdf PDF
673-21-153_HallsAndWalls_Specs RFI update.pdf PDF
1-S8.pdf PDF
1-S22.pdf PDF
1-S19.pdf PDF
1-S17.pdf PDF
1-S3.pdf PDF
1-S2.pdf PDF
36C24826Q0451 0003.docx DOCX document
1-S11.pdf PDF
1-S20.pdf PDF
1-S4.pdf PDF
1-S10.pdf PDF
Mechanical - grdfloor-Floor - Arch E1.pdf PDF
WD-FL20260208 DATED 05-18-2026.pdf PDF
Pages from Building 01 - As Built_Drawings.pdf PDF
Mechanical - grdfloor-Chilled Water - Arch E1.pdf PDF
Plumbing - Bldg 1 ground.pdf PDF
673-21-153 RFI Combined.pdf PDF
Camera Locations drawing.pdf PDF
Camera Locations.pdf PDF
Electrical - Bldg 1 Ground.pdf PDF
Fire Protection - Bldg 1 ground.pdf PDF
mgas-grdfloor-Floor - Arch E1.pdf PDF
M001.pdf PDF
Pages from Bldg 1 Life Safety.pdf PDF
852.204-72.pdf PDF
36C24826Q0451 0002.docx DOCX document
Pages from Bldg 1 Life Safety 1.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

D

C

ROLL-UP DOOR

ROLL-UP DOOR

ROLL UP

DOOR

48"

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 222.4 3.2 4.1 4.9 5.8 7.1 14.9 16.2 20.1

A

B

C

D

E

F

G

H

J

K

L

M

N

P

Q

R

S

T

U

N.8

M.1

C.2

A. ANY CHANGES MUST BE APPROVED BY COR BEFORE DOING ANY

ADDITIONAL WORK. WORK SCHEDULE TO BE PERFORMED DURING

REGULAR DAY SHIFT HOURS (8AM-4:30PM) ANY WORK OUTSIDE OF

REGULAR SCHEDULE REQUIRES APPROVAL FROM COR.

B. COORDINATE STAGING AREA WITH COR, AND FIND INTERIOR

COVERED STORAGE ON SITE FOR MATERIALS THAT MUST BE

PROTECTED FROM ELEMENTS - COORDINATE WITH COR.

C. PERFORM WORK IN ACCORDANCE WITH VHA DIRECTIVE 2004-012

SAFETY AND HEALTH DURING CONSTRUCTION ACTIVITIES AND VHA

DIRECTIVE 7701 OCCUPATIONAL SAFETY AND HEALTH (OSH) .

D. WORK PERFORMED FOR THIS PROJECT MAY INTERRUPT SERVICE

TO ADJACENT AREAS AT TIMES BUT WILL NOT INTERRUPT OVERALL

FACILITY OPERATION. SEE ELECTRICAL FOR POWER INTERRUPTION

AND OUTAGE REQUIREMENTS.

E. CONTRACTOR TO VERIFY ALL DETAILS AGAINST EXISTING

CONDITIONS PRIOR TO PURCHASE OF EQUIPMENT AND PRIOR TO

CONSTRUCTION. CONTRACTOR IS RESPONSIBLE FOR BRINGING

ANY DISCREPANCIES IN PLANS AND EXISTING SITE CONDITIONS TO

IMMEDIATE ATTENTION OF CONTRACTING OFFICER

REPRESENTATIVE.

F. CONTRACTOR SHALL PERFORM ALL WORK AND PROVIDE ALL

MATERIALS IN ACCORDANCE WITH VA MASTER CONSTRUCTION

SPECIFICATIONS, WHICH CAN BE FOUND AT

HTTP://WWW.CFM.VA.GOV/TIL/. WHERE DISCREPANCIES ARE FOUND

THE MORE STRINGENT SHALL APPLY.

GENERAL NOTES

A. THE CONTRACTORS SHALL COORDINATE EQUIPMENT AND

MATERIAL TRAFFIC AND STORAGE WITH COR.

B. ALL UTILITY WORK SHALL BE COORDINATED WITH MECHANICAL,

PLUMBING ELECTRICAL, AND FIRE PROTECTION.

C. ALL ASPECTS OF CONTRACTOR STAGING AND CONSTRUCTION

PHASING SHALL BE APPROVED BY COR.

D. ALL HOSPITAL ACCESS POINTS, AND ALL BUILDING EXITS, MUST

REMAIN ACCESSIBLE, CLEAR AND UNOBSTRUCTED THROUGHOUT

ALL PHASES OF DEMOLITION AND CONSTRUCTION. SHORT-TERM

CLOSURE MAY BE ACCEPTABLE AS COORDINATED WITH COR.

E. THE CONTRACTOR SHALL COORDINATE ALL ROOF TOP WORK AND

ROOF REPAIRS WITH THE COR.

GENERAL PHASING NOTES

A. THE CONTRACTOR SHALL USE THE FOLLOWING AS A GUIDE FOR ALL

ICRA BARRIERS. TEMPORARY INFECTION CONTROL BARRIERS

SHALL BE CONSTRUCTED AS FOLLOWS DEPENDING UPON LENGTH

OF NEED:

A. 1 DAY MAXIMUM - PLASTIC

B. 1 WEEK MAXIMUM - FLAME-RETARDANT PLASTIC

C. GREATER THAN 1 WEEK - SEE NOTE B AND C.

B. TEMPORARY CONSTRUCTION BARRIERS SHALL BE 3 5/8" METAL

STUDS @ 16" O.C. WITH 5/8" TYPE "X" GYP. BD. EACH SIDE. BARRIERS

ARE TO EXTEND TO THE BOTTOM OF EXISTING CEILINGS. PROVIDE

NON-DAMAGING SEAL AT INTERSECTION WITH CEILING. PROVIDE

PLASTIC SHEET BARRIER SEAL BETWEEN TOP OF WALL AND

STRUCTURE ABOVE. TAPE ALL SEAMS AND PENETRATION

OPENINGS TO PREVENT CONTAMINATION FROM PASSING OVER THE

TOP OR UNDERNEATH THE WALL FROM CONSTRUCTION AREAS.

C. TEMPORARY CONSTRUCTION BARRIERS SHALL BE EITHER TYPE I

OR TYPE II. TYPE I BARRIERS SHALL BE ANCHORED TO THE

FLOORING SURFACE (WHICH IS INTENDED TO BE REPLACED) WITH

POWER ACTUATED FASTENERS. TYPE II BARRIERS SHALL BE

ANCHORED TO THE FLOORING SURFACE (WHICH IS INTENDED TO

REMAIN) BY TAPING BOTTOM STUD TRACK TO FLOOR SURFACE OR

BY OTHER METHODS WHICH WILL NOT HARM FLOOR SURFACE.

D. TEMPORARY PARTITIONS SHALL NOT CONSTRICT WALKWAYS TO

LESS THAN 42" CLEAR. ANY EXITS CHANGED OR BLOCKED SIGNAGE

NEEDS TO BE POSTED FOR THE MODIFICATIONS.

E. PROVIDE TEMPORARY RATED DOOR AND FRAME IN CONSTRUCTION

BARRIER AT ENTRY POINTS TO THE CONSTRUCTION AREAS.

DOORS ARE TO REMAIN LOCKED AT ALL TIMES. CONSTRUCTION

CORES WILL BE PROVIDED BY THE VA.

F. RENOVATION CONSTRUCTION SHOULD BE COORDINATED WITH

EXISTING STRUCTURAL CONDITION WHERE IT OCCOURS AND

SHOULD BE CHECKED BY VA.

TEMPORARY CONSTRUCTION

FLOOR PLAN LEGEND

INCLUDED IN SCOPE OF WORK

3/64" = 1'-0"1 LEVEL 01 FLOOR PLAN SCOPE

AREA OF WORK

AREA OF WORK

AREA OF WORK

1050 E. Southern Ave, Suite #D, Tempe, Arizona 85282, (480) 751-9542designgroup

Architecture, Engineering, and Sustainable Design

AESUS

KEY PLAN NTS NORTH

Drawing Title: Project Title:

Date

Location

Checked

Building Number:

Project Number:

Drawing Number:

Drawn

CONSULTANTS: ARCHITECT/ENGINEERS: Office of Construction and Facilities Management

AE RENOVATE GROUND FLOOR

HALLS AND WALLS

Location:

Sept 20, 2024 o n e e ig h th in c h o n e fo o t

B

A

C

D

E

F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t

VA FORM

08-6231

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

673-21-153

JAMES A. HALEY VA HOSPITAL

13000 BRUCE B. DOWNS BLVD. TAMPA, FL, 33612

AESUS

B45

A D

B C

E

VA FORM

08-6231

Final Submittal

AESUS

AS.100

OVERALL FLOOR PLAN

Revision DATE

09.20.2024

VHATAMChapuK Cloud+

VHATAMChapuK Cloud+

ADO

VHATAMChapuK Cloud+

VHATAMChapuK Cloud+ ADO disabled and can be removed. Mag hold back for FA to be reused

VHATAMChapuK Cloud+

VHATAMChapuK Cloud+

ADO

VHATAMChapuK Cloud+

VHATAMChapuK Cloud+ both ADOs w PIV, bypass key switch

VHATAMChapuK Cloud+

VHATAMChapuK Cloud+ ADO w PIV/keypad

VHATAMChapuK Cloud+

VHATAMChapuK Cloud+ ADO w PIV, Mag lock, key bypass, and delayed egress controller mounted to wall

VHATAMChapuK Cloud+

VHATAMChapuK Cloud+ ADO w PIV, Mag lock, key bypass, and delayed egress controller mounted to wall

File details come from the government source that posted it. Updated .