36C24826Q0451 0003.docx
DOCX document 49 KB Posted
- Solicitation number
- 36C24826Q0451
About this file
This is a Standard Form 30 Amendment/Modification of Contract document issued by the Department of Veterans Affairs Network Contracting Office (NCO) 8 for Solicitation 36C24826Q0451. The amendment extends the quote due date to July 24, 2026 at 1:00 PM EDT and updates the Period of Performance to 730 calendar days after Notice to Proceed. The project involves renovation of the ground floor halls and walls at James A. Haley VA Hospital in Tampa, Florida, with a project magnitude between $5,000,000 and $10,000,000.
The amendment provides answers to 39 Requests for Information (RFIs) and supplies updated documents including the Statement of Work, drawings, specifications, structural sheets, site visit signing sheets, and building life safety maps. Key scope elements addressed include asbestos abatement requirements, decontamination procedures with specific load-out hours (1300-0400), maintenance of existing access-controlled systems and intercom devices on a like-for-like basis, fireproofing specifications (2-hour rating for applied fireproofing), and phasing plans allowing for modified schedules to accommodate operational and safety considerations. The amendment also adds FAR clauses 52.223-2 (Reporting of Biobased Products) and 52.223-23 (Sustainable Products) to the solicitation requirements. Contractors must submit quotes by July 24, 2026 at 1:00 PM EST to David.hernandez1@va.gov and maintain hospital operations and patient access throughout construction using containment systems, tunneling where necessary, and coordinated phasing to minimize disruption.
View the file
Other files
Show 40 more
Latest 50 of 63 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
) 36C24826Q0451 PROJECT 673-21-153
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority)
THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 06-15-2026 673-21-153 36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) Tampa FL 33637 36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) Tampa FL 33637 To all Offerors/Bidders
36C24826Q0451
X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 07-24-2026 1:00PM EDT PROJECT TITLE: BB Renovate Ground Floor Halls and Walls
PROJECT NUMBER: 673-21-153
THE PURPOSE OF THIS AMENDMENT IS TO PROVIDE THE FOLLOWING INFORMATION CHANGES: ANSWERS TO RFIs;
Updated SOW, updated Drawings, update Specs, second Site visit signing sheet, structural drawings, bdg1 life safety Tampa ground Floor Map, Plumbing and electrical Add Clauses FAR 52.223-2 and 52.223-23 to Solicitation POP is updated to 730-calendar days after NTP.
Quote due date is now: 07/24/2026 at 1:00PM EST email to David.hernandez1@va.gov
SEE ATTACHED
DAVID HERNANDEZ
CONTRACTING OFFICER
| No. |
| Question |
| Reference |
| Contractor |
| 1 |
| Please clarify if a heater will be required for the shower in the deacon? If so, please provide the available power locations. |
Midwestern
| VA Response |
| Hot water is required in accordance with OSHA 1926.1101(j)(1)(i)(b) and 1910.141(d)(3). The owner may supply hot water for the decon if available depending on location of the decon, otherwise, it is the responsibility of the contractor to provide a heater for hot water. The location of available power will depend on the location of the decon unit. |
| 2 |
| It appears the Deacon will have to be built out in the hallway and load out of asbestos will be done in the hallway as well. Will special considerations need to be made for this load out? |
Midwestern
| VA Response |
| Load out is to be performed between the hours of 1300-0400 to ensure minimum disturbance to normal operations of the hospital. A haul out route will be determined depending on the location of the containment. |
| 3 |
| Please provide the available locations for water for the deacon. |
Midwestern
| VA Response |
| This will be decided depending on the location of the decon. |
| 4 |
| Please provide a revised drawing identifying all existing card reader and keypad access-controlled openings within the project limits and indicate which openings are included in this contract. The door schedule does not match the existing field conditions observed during the site visit. |
Midwestern
| VA Response |
| General intent is to maintain existing operating conditions (like-for-like) unless otherwise noted on the drawings, to include PIV. If door currently has access control, it shall be reinstalled and reconnected to new door unless otherwise noted. |
| 5 |
| Multiple intercom stations were observed during the site visit that are not identified in the contract documents. Please provide a revised drawing identifying all existing intercom devices within the project limits and indicate which devices are to be removed and reinstalled as part of this project. |
Midwestern
| VA Response |
| All devices shall be removed and re-installed as part of this scope of work. If particular devices are determined to be abandoned by the VA prior to/during demolition, the VA will notify the contractor that they do not need to be reinstalled. |
| 6 | |
| Existing CCTV cameras observed during the site visit are not identified as active or abandoned in the contract documents. Please provide a revised drawing or device list identifying all existing CCTV cameras within the project limits and indicate which cameras are to be: | |
| a. | removed permanently, |
| b. | temporarily removed and reinstalled, or |
| c. | excluded from this contract. |
Midwestern
| VA Response |
| All devices shall be removed and re-installed as part of this scope of work. If particular devices are determined to be abandoned by the VA prior to/during demolition, the VA will notify the contractor that they do not need to be reinstalled. |
| 7 |
| Answer#50 The hallway must be accessible at all time. After building the scaffold start building the containment above the scaffold and establish negative pressure in the containment prior to start removing the ceiling tiles and grid. Make sure there are sufficient negative air machines to compensate for the loss of negative pressure once the ceiling tiles are removed. |
We are unclear how this is to be achieved with the existing ceilings only being ~8’. Once the scaffold is erected to allow proper overhead clearances below (sprinkler heads, lighting, alarm devices, speakers all below the scaffold), the remaining space will be ~12”. This will not leave enough room to safely perform the work. Another solution must be provided as this could also be considered a confined space by safety department which would add additional cost to the project if it was even feasible. The hallways in each phase will need to be shut down for several days to realistically make this happen.
Midwestern
| VA Response |
| The VA will not provide means and methods for constructing the containment. The contractor will submit means and methods in their abatement plan for approval by the owner. |
| 8. |
| Answer #16 Yes, the intent is to recess the surface mounted items. Situationally, if furred wall can be constructed in front of block wall without interfering with required corridor widths (with VA’s approval), this will be permitted. Note – if a wall is fire or smoke rated, the furred wall must be constructed with the same rating. |
Why would this be necessary if the wall behind carries the rating already. The furred wall would simply be cosmetic at this point. This appears to simply add redundancy and unneeded cost. Please clarify.
Midwestern
| VA Response |
| This can be revised. This only needs to occur if furred wall goes to deck. If furred wall ends 4-6” above ceiling (so there is visibility of the fire wall to check for integrity), then it does not need to meet the fire rating. |
| 9. |
| Answer #9 Site walk to be scheduled to allow contractors to go above ceiling (following VA above-ceiling requirements, including PPE and containment both- see attached).Because of this opportunity, this would not be considered unforeseen. |
We respectfully request that this statement be removed. Due to the limited time allotted for the site visit, it was not feasible to visually inspect every inch of space above the ceiling. As a result, additional unforeseen conditions may present themselves in other areas.
Midwestern
| VA Response |
| Multiple site visits were given and no requests for more time that day were received. If bidders choose not to take advantage of multiple time frames, this is not the VA’s issue. Because the opportunity was offered, this will not be considered unforeseen. |
| 10. |
| Does the VA has a preferred material for fireproofing |
Blue Cord
| VA Response |
| The GC shall bid per spec section 07 81 00. |
| 11. |
| Please confirm what fire rating is needed for the above ceiling fireproofing. |
Blue Cord
| VA Response |
| 2-hr (full flooring system with concrete, etc. must be 4-hr. 2-hr is for the new applied fireproofing) |
| 12. |
| Can the VA provide as built, structural sheets to show existing floor deck |
Blue Cord
| VA Response |
| Attached |
| 13. |
| It was stated at the 6-24-26, 5:30 AM site visit that the VA would be willing to give up entire sections of hallways for a phase. Can the VA please identify these areas on a drawing so that bidders can include this in our phasing and schedule that is submitted for the solicitation. |
Blue Cord
| VA Response |
| There are not entire hallways. The hallway that will be able to close the most is shown as phases 8 and 9. Access to ROI and electrical/mechanical/IT closets will need to remain so tunneling would only be required in those areas. |
| 14. |
| On drawing ASB-1 under Asbestos Abatement Legend/Key Notes, Note 3 under sequencing for abatement, it states to abate the ductwork insulation first. If this is the case it wall cause the ductwork to sweat until new insulation can be installed. New insulation cannot be installed until after air clearance without the risk of the new duct being cross-contaminated. Will the AHU’s associated with this ductwork be shutdown during the abatement phases to prevent the ductwork from sweating? |
Blue Cord
| VA Response |
| No. The sequence of work can be modified to remove the ductwork last to minimize condensation. Based on abatement requirements, work area shall already be contained to prevent water intrusion into non-work areas during abatement. |
| 15. |
| During the site visit on 6-24-26 it was observed in several areas that the ductwork is directly underneath the deck with less than 1’ in-between the top of the ductwork and bottom of the deck. In order to complete the abatement of the fireproofing on the deck the ductwork will need to be removed. Please advise if this is the intent in order to complete the abatement of the fireproofing. If the fireproofing is inaccessible is utilizing a penetrating encapsulant a viable option? |
Blue Cord
| VA Response |
| How to access area to abate is means and methods. If contractor determines duct removal is necessary to abate the fireproofing, this shall be done. The intent is to remove all ACM fireproofing and not encapsulate. |
| 16. |
| In the solicitation drawings it lists the room GD-038 as construction laydown. Is this room designated as the construction laydown during the entire duration of the project? |
Blue Cord
| VA Response |
| No that room is not part of the project area or designated as construction laydown and is an old room title. That space is now active. VA is working to provide space near each phase for decon, etc. where possible. Potential locations for connex and dumpster outside facility are provided. |
| 17. |
| Please provide the available as-built drawings for Electrical and Plumbing disciplines for areas affected by this project |
Blue Cord
| VA Response |
| Reattached. |
| 18. |
| On the demolition drawings there are various notes for removing existing devises on walls and recess conduit and boxes and in wall. Several of these locations in all wings are block walls. Are these block walls structural or poured solid? Please provide a structural detail for recessing the boxes and installing the conduits in the block walls without disturbing the structural integrity of the wall. |
Blue Cord
| VA Response |
| The VA have provided existing structural drawings for review. Otherwise, the GC shall bid the project as if the walls are non-structural. |
| 19. |
| Drawing AE.430 shows replacing the freezer pair of doors (Room GD-007) to a single door. Is this correct? If, so does a new frame need to be installed? |
Blue Cord
| VA Response |
| This is not correct. See revised drawings and door schedule. |
| 20. |
| Under the general demolition notes it states turn sprinkler heads up during construction. Does that mean that areas that portions of the corridors will remain active of during construction to staff and patients will not have fire sprinkler coverage? If the corridors do need to remain active during construction can the existing fire sprinkler pipe support having double the sprinkler coverage (sprinklers turned up and sprinklers turned down in the active corridor)? |
Blue Cord
| VA Response |
| Sprinklers shall be turned up in work area. Work area must have fire rated barriers; The accessible areas/tunnels shall have fire alarm notification, not sprinkler protection. Interconnected smoke detectors could satisfy this requirement so long as when one smoke detector goes into alarm all within the tunnel go into alarm. This will get the attention of anyone in the area after normal working hours, and they can make notification to the Operator of the code red situation. |
| 21. |
| It was identified in multiple locations on the 6-24-26 above ceiling site investigation that several active utilities (HVAC ductwork, electrical conduit, low voltage free wire data and fiber cables, cable trays and plumbing lines sit directly on top on the ceiling grid in multiple areas (in several areas in A wing and D Wing the ceiling grid bows down due to this). Are these utilities to demoed in order to safely access the fireproofing for asbestos abatement? If they are to remain active can the existing supports support workers on top of them to reach the deck? If not please provide support details to support the above ceiling utilities to allow for workers to safely work on top of them to perform the asbestos abatement. |
Blue Cord
| VA Response |
| Shoring and / or supporting elements for “workers to safely work on top of them is a means and methods that should be figured out by the GC. |
| 22. |
| Are there any above ceiling MEP utilities that the VA knows is abandoned or no longer in use that can be permanently demolished within the affected areas? |
Blue Cord
| VA Response |
| Not at this time. Any potentially abandoned utilities found during construction shall be brought to the attention of the CORs for confirmation of removal. |
| 23. |
| Will the VA consider extending the period of performance of the project? Based on the phasing plan provided by the VA it does not appear the current period of performance can be achieved unless multiple phases are given to the successful contractor at once. |
Blue Cord
| VA Response |
| Yes. See revised SOW for extended PoP (730 days) |
| 24. |
| It was stated in RFI Response 114 and 115 that negative air should be exhausted outside of the building. Please confirm if the VA’s intent is to penetrate the exterior to provide an acceptable exhaust area. |
Blue Cord
| VA Response |
| It is not the intent of the VA to penetrate the exterior to provide exhaust area. The exhaust location shall be determined for each containment separately depending on the location of the containment. How this is exhausted is means and methods. |
| 25. |
| For exhausting negative air will the VA allow the contractor to run negative air tubing/ductwork below ceiling, or will the tubing/ductwork be required to be ran above ceiling? |
Blue Cord
| VA Response |
| Exhaust ductwork will be located above the drop ceiling as much as possible. If that is not possible then the VA will consider running the ductwork below the drop ceiling as long as it is not too noisy and interferes with patient comfort or safety. If below ceiling, contractor must ensure it is adequately supported and maintains integrity at all time to prevent any cross-contamination to areas outside the work area. |
| 26. |
| Please confirm all ductwork and piping insulation that is demoed/abated during construction must be reinstalled. |
Blue Cord
| VA Response |
| All ductwork and piping insulation that is demoed/abated during construction must be replaced with new, compliant insulation. See insulation specifications. |
| 27 |
| Please confirm that phasing plans can be modified/changed to accommodate specific access safety or operational considerations? |
LC3 Solutions
| VA Response |
| Yes |
| 28. |
| Can elevators and phase 5 be taken out of service while work is being done or will tunnel/access need to be made available? |
LC3 Solutions
| VA Response |
| Access will need to be made to either Elevators 4 and 5 or elevators 10 and 11 (two of the four must remain accessible at all times as they are the only elevators in the area that can fit patient beds). Alternately, contractor can propose a change in phasing to separate the two banks into separate phases |
| 29 |
| Please advise on location and size of staging areas and locations we can place dumpsters? |
LC3 Solutions
| VA Response |
| VA will provide a location for one dumpster and one connex (approx. 10’x30’ each). Potential laydown area for dumpster is outside Building 39 (nearest 131st Ave). Potential area for connex is either same location or in Freedom lot. The exact locations will be confirmed by the VA upon award. |
| 30 |
| Please clarify work hours. |
LC3 Solutions
| VA Response |
| See revised SOW. |
| 31 |
| Please clarify whether the contractor will be permitted to perform work in multiple phases concurrently or if work will be limited to one active phase/work area at a time. |
LC3 Solutions
| VA Response |
| Contractor may submit an alternate phasing plan for the VA to review that decreases the number of phases or includes multiple phases at once. However, impact to hospital operations shall be minimized at all times so several phases cannot be combined due to heightened impact/longer duration (ie phase 7 provides alternate access for areas impacted in phase 8, so they cannot be combined, etc.) |
| 32 |
| Will fire detection systems be shut down/the energized and work areas? |
LC3 Solutions
| VA Response |
| The fire detection system shall remain energized unless other means of protection is proposed and approved by the VA. |
| 33. |
| Will all building systems within containment area areas be the energize and locked/tagged out while work is being performed |
LC3 Solutions
| VA Response |
| Building systems cannot be deenergized during construction since they supply multiple areas outside the work areas. |
| 34. |
| Well, relocation of hospital operations be acceptable in areas where maintaining access is not possible? |
LC3 Solutions
| VA Response |
| VA will vacate as many areas as possible. However, this mostly only applies to offices. Multiple areas have operations that cannot be relocated which is why tunnel system is needed. VA plans to reroute as much patient traffic as possible to first floor but key support areas on ground floor must remain (including but not limited to SPS, morgue, linen, etc.) |
| 35 |
| Does the VA contain technical data sheets of Terrazo tile for what’s already in place? |
LC3 Solutions
| VA Response |
| Current tile is not terrazzo, it is VCT. Data sheets are not available for existing. |
| 36 |
| Manufacturer listed for terrazzo tile does not produce product given. Please provide an alternate. |
| VA Response |
| Products are just for basis of design. Requirement is to meet specification. |
New Basis of Design: Surfaces 9 Floorazzo Marble Collection - Glacier
VA Response
VA Response
VA Response
VA Response
A.1 52.223-2 REPORTING OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACTS (NOV 2025) (DEVIATION)
(a) Definitions. As used in this clause— BioBased product means a product determined by the U.S. Department of Agriculture (USDA) to be a commercial product or industrial product (other than food or feed) that is composed, in whole or in significant part, of biological products, including renewable domestic agricultural materials and forestry materials, or that is in an intermediate ingredient or feedstock. The term includes, with respect to forestry materials, forest products that meet biobased content requirements, notwithstanding the market share the product holds, the age of the product, or whether the market for the product is new or emerging. (7 U.S.C. 8101) (7 CFR 4270.2).
USDA-designated product category means a generic grouping of biobased products that are listed by USDA in a procurement guideline (7 CFR part 4270) and for which USDA has provided minimum biobased content standards (see https://www.biopreferred.gov/resources/categories.html).
(b) Requirement. The Contractor shall—
(1) Report to https://www.sam.gov, with a copy to the Contracting Officer, on the product types and dollar value of any biobased products in USDA designated product categories purchased by the Contractor during the previous Government fiscal year, between October 1 and September 30; and
(2) Submit this report no later than—
(i) October 31 of each year during contract performance; and
(ii) At the end of contract performance.
(End of Clause)
A.2 52.223-23 SUSTAINABLE PRODUCTS (NOV 2025) (DEVIATION)
(a) Definitions. As used in this clause— Sustainable products means—
(1) A product that contains recovered material designated by the EPA under the Comprehensive Procurement Guidelines (42 U.S.C. 6962) (40 CFR part 247) (https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program#products).
(2) An energy-efficient product or low standby power device (42 U.S.C. 8259b) (10 CFR part 436, subpart C) (https://www.energy.gov/femp/search-energy-efficient-products, https://www.energystar.gov/products?s=mega, and https://www.energy.gov/femp/low-standby-power-product-list).
(3) A biobased product that meets the content requirements of the USDA under the BioPreferred® program (7 U.S.C. 8102) (7 CFR Part 4270) (https://www.biopreferred.gov/)
(4) A substance identified in the EPA’s Significant New Alternatives Policy (SNAP) program as a safe alternative to an ozone-depleting substance (42 U.S.C. 7671l) (40 CFR part 82, subpart G) (https://www.epa.gov/snap/unacceptable-and-acceptable-substitutes-tables).
(b) Requirements. The Government has identified in the statement of work or elsewhere in the contract the sustainable products that are required during the performance of this contract. The Contractor shall ensure that it provides sustainable products as required by this contract, when the products are—
(1) Delivered to the Government;
(2)Furnished for use by the Government;
(3) Incorporated into the construction of a public building or public work; or
(c) Furnished for use in performing services under this contract, where the cost of the products is a direct cost to this contract.
(End of Clause) See attached document: site visit2.
See attached document: 1-S1.
See attached document: 1-S2.
See attached document: 1-S3.
See attached document: 1-S4.
See attached document: 1-S4A.
See attached document: 1-S4B.
See attached document: 1-S5.
See attached document: 1-S6.
See attached document: 1-S7.
See attached document: 1-S8.
See attached document: 1-S9.
See attached document: 1-S10.
See attached document: 1-S11.
See attached document: 1-S12.
See attached document: 1-S13.
See attached document: 1-S14 1.
See attached document: 1-S15.
See attached document: 1-S16.
See attached document: 1-S17.
See attached document: 1-S18.
See attached document: 1-S19.
See attached document: 1-S20.
See attached document: 1-S21.
See attached document: 1-S22.
See attached document: TUG MAP - TampaGroundFloor.
See attached document: 673-21-153_HallsAndWalls_Drawings RFI Update.
See attached document: Electrical - Bldg 1 Ground.
See attached document: Pages from Bldg 1 Life Safety.
See attached document: 05 673-21-153 BB SOW rev RFI update.
See attached document: 673-21-153_HallsAndWalls_Specs RFI update.
See attached document: Pages from Bldg 1 Life Safety 1.
See attached document: Plumbing - Bldg 1 ground.
image1.png