This amendment to a combined solicitation provides details for maintenance services for chillers and cooling towers at the Gainesville VA Medical Center. The Department of Veterans Affairs seeks proposals for preventative maintenance, including annual inspections and cleaning for five chillers and two cooling towers. Proposals are due by January 30, 2023. Preventative maintenance is required quarterly for chillers and semi-annually for cooling towers. The schedule aims to perform annual chiller services between January and October 2023. The amendment revises the statement of work, provides a site visit sign-in sheet, and answers questions about the scope, clarifying that corrective maintenance is out of scope. Licensing and certification requirements, site procedures, and the performance period from December 2022 to December 2023 are also outlined.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24823Q0277 0002_5.docx | DOCX document | |
| Chiller Plant Sign-In Sheet.pdf | ||
| Revised- SOW Plant Chillers.docx | DOCX document | |
| 36C24823Q0277 0002_3.docx | DOCX document | |
| 36C24823Q0277 0002_2.docx | DOCX document | |
| 36C24823Q0277 0002_1.docx | DOCX document | |
| 36C24823Q0277 0002.docx | DOCX document | |
| 36C24823Q0277 0001.docx | DOCX document | |
| Chiller Plant Description.docx | DOCX document | |
| Past Performance Survey.pdf | ||
| VHA Seasonal Influenza Vaccination Program.pdf | ||
| 36C24823Q0277.docx | DOCX document | |
| 852.219-77 VA Notice of Limitations on Subcontracting.docx | DOCX document | |
| 36C24823Q0277_1.docx | DOCX document | |
| VHA ICARE Standards.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment to a Previous Combined Solicitation
Amendment to a Previous Combined Solicitation
| SUBJECT* |
| FY23: Gainesville Chiller Plant Maintenance Base plus Four |
GENERAL INFORMATION
| CONTRACTING OFFICE’S ZIP CODE* |
| 32601-3460 |
| SOLICITATION NUMBER* |
| 36C24823Q0277 |
| RESPONSE DATE/TIME/ZONE |
| 01-30-2023 15:00 EASTERN TIME, NEW YORK, USA |
| ARCHIVE |
| 60 DAYS AFTER THE RESPONSE DATE |
| RECOVERY ACT FUNDS |
| N |
| SET-ASIDE |
| SDVOSBC |
| PRODUCT SERVICE CODE* |
| J041 |
| NAICS CODE* |
| 238220 |
| CONTRACTING OFFICE ADDRESS |
| Department of Veterans Affairs |
Network Contracting Office 8 (NCO 8) Commerce Building 300 E. University Ave. Ste. 180 Gainesville FL 32601-3460
POINT OF CONTACT*
Contract Specialist Jermaine Wilson Jermaine.Wilson@va.gov 352-381-5706
PLACE OF PERFORMANCE
| ADDRESS |
| Malcom Randall VAMC |
1601 SW Archer Rd
Gainesville FL
| POSTAL CODE |
| 32608 |
| COUNTRY |
| USA |
ADDITIONAL INFORMATION
AGENCY’S URL
URL DESCRIPTION
AGENCY CONTACT’S EMAIL ADDRESS
EMAIL DESCRIPTION
DESCRIPTION
The purpose of this amendment is to provide a revised Statement of Work, provide the sign in sheet from the site visit, and provide answers to the questions received. The date for quotes to be submitted remains at 01/30/2023 3:00pm ET.
Attached is a revised Statement of Work.
Attached is the sign in sheet from the site visit.
Questions submitted:
1. What is the incumbent contract #?
2. What licenses and/or certifications are required at the time of quote submission?
3. Can the 12/28/22 site visit sign in sheet be made available to offerors?
4. What is expected for eddy current testing for the condenser and evaporator sides of chillers?
5. What is expected for evaporative tube cleaning of the chillers?
6. What is expected for vibration analysis of all equipment?
7. What is expected for oil analysis of the chillers?
8. Will there be another questions period following the site visit?
9. Please confirm whether disinfection of the towers is required during the annual cleaning.
10. What is the frequency of the requested services?
11. When does the facility expect the annuals and quarterlies to be completed?
12. Are there any known pre-existing conditions that will require immediate attention if we are the successful offeror?
13. Should the cost of labor for corrective action discovered during PM be included in the proposal?
14. Should the costs of materials and/or equipment for corrective action discovered during PM be included in the proposal?
15. Should the cost for labor for emergency responses be included in the proposal?
16. Should the cost for labor for corrective actions identified during an emergency response be included in the proposal?
17. Should the cost for materials and/or equipment for corrective actions identified during an emergency response be included in the proposal?
18. Will there be a threshold to cap the expenditure by the successful offeror for work performed outside of the PM requirements?
19. What are the site access procedures?
Response to questions submitted:
1. There is no longer a Chiller Plant Contract in place.
2. A current Trane Certification needs to be provided at time of quote.
3. The sign-in sheet will be posted with the answers to these questions.
4. Eddy currents are not part of the contract.
5. The tubes in the Evaporator are not cleaned. Only the Condenser.
6. Vibration Analysis is not part of the contract.
7. To be sent off to a lab for analysis.
8. All questions are answered in this amendment.
9. Disinfection is not required in the contract.
10. Chiller Annuals are done once a year. Cooling Towers are cleaned twice a year. Quarterly inspections are done every quarter.
11. We will attempt to follow the schedule at the bottom of this document.
12. None at this time.
13. No, corrective maintenance is not part of this contract.
14. No, corrective maintenance is not part of this contract.
15. No, corrective maintenance is not part of this contract.
16. No, corrective maintenance is not part of this contract.
17. No, corrective maintenance is not part of this contract.
18. No, corrective maintenance is not part of this contract.
19. Check-in at the Plant, ask for the COR.
Service Contract Plant Chillers
| Equipment |
| New Contract |
| 12-20-21 to 12-19-22 |
| 12-20-20 to 12-19-21 |
| Comments |
| Chiller 1 |
| Spring |
| 4/14/2022 |
| 4/5/2021 |
| Chiller 2 |
| Winter |
| 1/25/2022 |
| 1/25/2022 |
| Chiller 3 |
| Spring |
| 3/31/2022 |
| 1/12/2021 |
| Chiller 4 |
| Fall |
| 10/22/2022 |
| 10/4/2021 |
| Chiller 5 |
| Spring |
| 3/15/2022 |
| 4/27/2020 |
| BAC Tower |
| Winter |
| 12/20/2021 |
| 11/18/2020 |
| Evapco North |
| Spring |
| Fall |
| 1/11/2022 |
| 2/18/2021 |
| Evapco South |
| Spring |
| Fall |
| 10/22/2022 |
| 11/3/2021 |
See attached document: Revised- SOW Plant Chillers.
See attached document: Chiller Plant Sign-In Sheet.
| *= Required Field |
| Amendment to a Previous Combined Solicitation |
Page 1 of
Amendment to a Previous Combined Solicitation
File details come from the government source that posted it. Updated .