COLUMBIA WT BOILER SD6MSOP 15_P High Steam Pressure Limits Boiler.docx
DOCX document 329 KB Posted
- Solicitation number
- 36C24726Q0127
About this file
The document is a Standard Operating Procedure (SOP) for testing high steam pressure limit switches on a boiler, specifically referencing SOP 544-138-11-5 for the WT Boiler SD6MSOP 15_P. The procedure provides detailed step-by-step instructions for safely testing boiler pressure limit switches, including securing power, verifying pressure setpoints, and methodically checking high and high-high boiler steam pressure limit switches. The document includes safety warnings about using proper Personal Protective Equipment (PPE) and requires careful monitoring of boiler pressure during the testing process.
This technical procedure is directly related to a VA medical center solicitation (36C24726Q0127) for Boiler Plant Control Systems Preventative Maintenance Services, which is set aside for Service-Disabled Veteran-Owned Small Businesses. The solicitation is for the Department of Veterans Affairs, Veterans Integrated Service Network 7 (VISN 07) located in Columbia, SC, with a NAICS code of 561210 and a small business size standard of $47.0 Million. The procurement seeks comprehensive boiler maintenance services, and prospective vendors must be registered in SAM and verified as an SDVOSB to be eligible for award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| VHA Boiler and Associated Plant Safety Device Testing Manual 8th Edition 1.pdf | ||
| COLUMBIA WT BOILER SD6MSOP 15_D High Steam Pressure Limits Boiler.docx | DOCX document | |
| 36C24726Q0127 0001.docx | DOCX document | |
| S06-36C24726Q0127 0001_1.docx | DOCX document | |
| 36C24726Q0127.docx | DOCX document | |
| 36C24726Q0127 .docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REF: SOP 544-138-11-5 WT BOILER SD6MSOP 15_P
Checklist for High Boiler Steam Pressure Limit Switch and High-High Boiler Steam Pressure Limit Switches ( H
BSPLS &
HH
BSPLS)
Danger: Proper PPE Required
(NFPA 70E)
Close the steam stop valve and/or the steam header valve on the b oiler you are about to test On the boiler panel , place the boiler firing rate in manual . On the Control screen, verify that the Cut-In and Cut-Out Pressure Set points above the maximum safety valve setpoint.
If they are not, contact the Supervisor to obtain Password Access.
Start the boiler.
Observe and Record the pressure at which the boiler trips offline on the data sheet.
HBSPLS
Secure Power to the Boiler. (Prove the circuit dead with multimeter) Locate the High Boiler Steam Pressure Limit Switch and remove cover (See Picture.)
Install an electrical jumper across common and normally closed t erminals.
(See Picture).
Restore Boiler Power.
Start the Boiler.
Observe and Record the pressure at which the boiler trips offline.
HHBSPLS
Secure power to the boiler. (Prove Circuit Dead with multimeter) Remove electrical jumper on High Boiler Steam Pressure Limit Switch.
Slowly open Steam Stop and/or Header valves to bleed excess pressure.
Restore Boiler Power R eturn boiler to normal.
1,13
High-High
High
7,12 image3.jpeg image4.jpeg image5.jpeg image1.jpeg image2.jpeg