COLUMBIA WT BOILER SD6MSOP 15_D High Steam Pressure Limits Boiler.docx
DOCX document 26 KB Posted
- Solicitation number
- 36C24726Q0127
About this file
This document is a standard operating procedure (SOP) checklist for testing boiler steam pressure limit switches at a VA medical facility. The checklist, created on January 1, 2023 and valid until January 1, 2028, outlines a semi-annual testing procedure for two critical boiler switches (HBSPLS and HHBSPLS) with specific requirements for pressure settings and manual reset conditions. The document provides a structured evaluation method to ensure boiler safety, requiring switches to be set at precise pressure differentials relative to normal steam pressure and safety valve set points, with explicit pass/fail criteria for each testing parameter.
The related federal contract opportunity (Solicitation Number 36C24726Q0127) is a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside solicitation for Boiler Preventative Maintenance Services issued by the Department of Veterans Affairs VISN 07 at the William Jennings Bryan Dorn VA Medical Center in Columbia, SC. The procurement falls under NAICS code 561210 with a small business size standard of $47.0 Million, and requires vendors to be registered in SAM and SBA verified as an SDVOSB, with quotes being requested for comprehensive boiler plant control systems preventative maintenance services.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| VHA Boiler and Associated Plant Safety Device Testing Manual 8th Edition 1.pdf | ||
| 36C24726Q0127 0001.docx | DOCX document | |
| COLUMBIA WT BOILER SD6MSOP 15_P High Steam Pressure Limits Boiler.docx | DOCX document | |
| S06-36C24726Q0127 0001_1.docx | DOCX document | |
| 36C24726Q0127.docx | DOCX document | |
| 36C24726Q0127 .docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REF: SOP 544-138-11-5 WT BOILER SD6MSOP 15_D
Checklist for Recycle and Non-Recycle Boiler Steam Pressure Limit Switches Boiler#_________ (HBSPLS & HHBSPLS)
| Date: ___________________ | Tested By: ___________________________ |
| Procedure Created: January 1, 2023 | Procedure Expires: January 1, 2028 |
| Testing Frequency: Semi-Annual | VHA Directive: 1810 |
Location and Plumbing *This test involves two switches. The switch with the highest set point must be a non-recycle switch.
Make & Range of HBSPLS psig
Setpoint of HBSPLS psig
Make & Range of HHBSPLS psig
Setpoint of HHBSPLS psig
Normal Steam Pressure psig
Lowest Boiler Steam Safety Valve Set Point psig
Pressure Gage Calibration Date
| Is the switch with the highest set point a non-recycle switch? |
| Yes |
| Fail |
| Are the ranges of the switches and gage satisfactory? |
| Yes |
| Fail |
Switch Setpoint & Mechanics *The VA requires that the HBSPLS set point should be 10 psig or more higher than the normal steam pressure and the HHBSPLS set point should be 5 psig or more above the HBSPLS set point & 5 psig or more below the lowest boiler steam safety valve set point
What pressure did the HBSPLS activate?
psig
What pressure did the HHBSPLS activate?
psig
| Did HBSPLS activate 10 psig or more above the normal steam pressure |
| Yes |
| Fail |
| Did HHBSPLS activate 5 psig or more above that of the HBSPLS |
| Yes |
| Fail |
| Did HHBSPLS activate 5 psig or more below the lowest boiler SSRV set point? |
| Yes |
| Fail |
Check the Logic
| Did HBSPLS require a manual reset? |
| Yes |
| Fail |
| Did HHBSPLS require a manual reset? |
| Yes |
| Fail |
| Were all questions answered as “YES” |
| Yes |
| Fail |
| If required - Were repairs made to all items marked fail? |
| Repaired |
| Not Repaired |
EXPLAIN: