36C24725Q0274.pdf

PDF 652 KB Posted

Attached to
RFQ for Project 534-23-513 Install Med Gas in B185
Solicitation number
36C24725Q0274
Issued by

About this file

This is a Request for Quotation (RFQ) issued by the Department of Veterans Affairs VISN 7 Network Contracting Office for Project 534-23-513 to install medical gas systems in Building 185 at the Ralph H. Johnson VA Medical Center in Charleston, SC. The scope includes providing supervision, labor, equipment and materials to remove existing fixtures/medical instruments/TV, install a new 4-panel trackless ICU glass door with 42" clear opening, and install a medical gas header panel containing duplex receptacles, medvac outlets, med air outlets, oxygen outlets and nurse call provisions.

The magnitude of construction is estimated between $25,000-$100,000 with NAICS code 236220 and a size standard of $45 million. This is a service-disabled veteran-owned small business (SDVOSB) set-aside. RFIs are due by February 20, 2025 at 3:00PM EST and quotes are due by February 28, 2025 at 3:00PM EST. The period of performance is 300 calendar days from Notice to Proceed. Normal working hours are 0700-1700 Monday through Friday, with some after-hours work potentially required. A site visit is available upon request. Contractors must provide ASSE certified technicians for medical gas installation and independent ASSE certified inspection.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES NO

a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________

(hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C24725Q0274

02-13-2025

534-25-2-5788-0011

534-23-513

36C247

Department of Veterans Affairs

VISN 7 Network Contracting Office

3 FL Directors Office

3700 Crestwood Parkway

Duluth GA 30096

Kenyon E. Dulaney

Contract Specialist kenyon.dulaney@va.gov

No physical Copies will be accepted.

Kenyon E. Dulaney (470)882-2776

Project No. 534-23-513 Install Med Gas in B185

The contractor shall provide all supervision, labor, equipment, and materials needed to complete work for project 534-23-513, O2, Med Gas Installation. This project includes the upgrade of B185. Work will need to be done on working hours are 0700 – 1700 Monday to Friday, except for Federal holidays. To reduce patient impact, some work may need to take place during after-hours (1700 – 0700) or during weekends.

A site visit is available as needed. Please reach out to kenyon.dulaney@va.gov to schedule.

The magnitude of construction for this project is estimated to be between $25,000 and $100,000.

NAICS Code No. 236220 with a size standard of $45.0 Million.

RFI's are due no later than February 20th, 2025 at 3:00PM EST.

Quotes are due no later than February 28th, 2025 at 3:00PM EST.

0 300

X X 52.211-10

X

3PM EST

02-28-2025

X

14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

PHONE: FAX:

28. NEGOTIATED AGREEMENT 29. AWARD Your

Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code)

(Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

(Type or print)

(4 copies unless otherwise specified)

(Type or print) (Type or print)

(Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror)

(To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

534-3650162-5788-854200-3220 23NRNR009

36C247

Department of Veterans Affairs

VISN 7 Network Contracting Office

3 FL Directors Office

3700 Crestwood Parkway

Duluth GA 30096

Austin Payment Center

Department of Veteran Affairs

PO Box 149971

Austin TX 78714-8971

(877) 353-9791 (512) 460-5545

Chantel Guest

Table of Contents

PART I - THE SCHEDULE

SECTION A - SOLICITATION/CONTRACT FORM

A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or

Repair)

A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,

ALTERATION, OR REPAIR)– BACK

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

A.4 DELIVERY SCHEDULE

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE

OF THE WORK (MAY 2014)

2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE

EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION

MATERIALS (MAY 2014)

2.5 52.228-1 BID GUARANTEE (SEP 1996)

2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE)

(FEB 2021)

2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

2.8 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)

2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB

1998)

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2025)

3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS

AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)

3.3 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—

REPRESENTATION AND DISCLOSURES (DEC 2023)

GENERAL CONDITIONS

4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR

INFORMATION SYSTEMS (NOV 2021)

4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(APR 1984) ALTERNATE I (APR 1984)

4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION

(FEB 2024)

4.4 52.223-20 AEROSOLS (MAY 2024)

4.5 52.223-21 FOAMS (MAY 2024)

4.6 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)

4.7 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)

4.8 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

4.9 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000)

4.10 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN

2020)

4.11 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED

SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023)

(DEVIATION)

4.12 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—

CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)

(DEVIATION)

4.13 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV

2018)

4.14 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION

(APR 2019)

4.15 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)

4.16 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)

4.17 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT

ADMINISTRATION (OCT 2020)

4.18 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) ..57

4.19 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT

(SEP 2019)

ATTACHMENTS

O2, Med Gas Installation

Project # 534-23-513

109 Bee Street Charleston, SC 29401-5799

Statement of Work

A. Scope

The contractor will provide all supervision, labor, equipment, and materials needed to complete work for project 534-23-513, O2, Med Gas Installation. This project includes the upgrade of

B185.

1. Remove all fixtures/medical instruments/TV from walls and store for later re-installation.

2. Remove existing door and provide and install a glass ICU type door in place. Work will include all finishes (drywall [level 5], paint [primer, 2 coats], caulk, etc.) around the door to create a complete and working finished product which matches the existing ED to greatest extent possible. Paint colors can be obtained from the COR. Door shall be 4 panel trackless ICU door with the clear open of 42” and package width of 60”. Contractor to field verify dimensions, package width can vary if required. Basis of design is Stanley

ICU/CCU 7200 ICU. Finish and room markings to match existing ED doors. Contractor to provide shop drawing of door construction for approval prior to purchase.

3. Provide and install a matching Med Gas header panel on west wall of room B185.

Header should contain: one normal duplex receptacle fed from 2L1CC or 2L2CC; one emergency duplex receptacle fed from 1LE1CC; 2 medvac outlets; 2 med air outlets; 2 oxygen outlets; and should make provision for nurse call installation. Installation should be similar to the below picture:

See attached drawings for the location of the electrical closet and the layout of room

B185.

4. Provide stamped shop drawings and calculation for med gas piping, capacity, layout.

Ensure that installation is completed by ASSE certified technician and inspected and excepted by an independent ASSE certified inspector. Tie-in point for Medical gasses is believed to be above ceiling of Room B164.

5. Contractor must test all impacted existing materials for asbestos and dispose of them according to state and federal regulations based on the testing. For purposed of bidding, contractor can assume that all demoed material will be disposed of as non-friable ACM.

If test results demonstrate a variance to that assumption, a credit form or an addition to the contract will be negotiated at that time.

6. Install a matching ED room curtain across the door way.

7. Reinstall all previously removed wall fixtures/medical instruments/TV as directed by VA.

8. Scheduling and coordination with the VAHCS will be critical and must be approved by

Contracting Officer’s Representative (COR) prior to work.

B. General Requirements

1. Employees of the contractor and sub-contractors shall always conduct themselves in a professional manner while on medical center property. The contractor shall ensure all personnel working on this contract are aware of Medical Center policies pertaining to employee behavior and conduct.

2. Physical or verbal misconduct may be grounds for removing employees from Medical

Center property, or grounds for arrest by the Veteran Affairs (VA) Police. Employees may be banned from VAHCS property as a result of inappropriate or illegal behavior.

The contractor shall not be entitled to any compensation from the Government for any costs resulting from employee misconduct (including, but not limited to, delays in contract completion) and may be held liable for costs incurred by the Government because of employee misconduct.

3. Refer to Specification Section 01 00 00.1.5.F. Smoking and vaping is strictly prohibited on the entire VAMC campus.

4. Contract shall furnish maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment. Refer to Specification Sections 01 22 23 and 01 00 00.1.19 General Requirements for details.

5. Refer to Specification Section 01 00 00.1.6 for details on Operations and Storage Areas.

6. It is the contractor’s responsibility to properly assess the working conditions and include in the bid any specialty equipment, training, additional time, personnel, or safety equipment to perform the work safely and in compliance with all applicable VAHCS, local, state, and federal regulations.

C. Hours of Work

1. Normal working hours are 0700 – 1700 Monday to Friday, except for Federal holidays.

To reduce patient impact, some work may need to take place during after-hours (1700 –

0700) or during weekends.

2. All schedules and work hours shall be requested, coordinated, and approved through the

COR.

D. Phasing

1. N/A

E. Infection Control

1. Infection Control Requirements shall be followed in accordance with an Infection Control

Risk Assessment (ICRA) Permit. It is expected that work inside the facility will require a

Class IV permit. Dust, dirt, and debris shall be contained. Additional infection control requirements are in included in Specification Section 01 35 26 Safety Requirements.

2. Low/No Volatile Organic Compounds (VOC) materials are to be utilized. Refer to

Specification Section 01 81 13, Sustainable Construction Requirements.

3. All ICRA barriers and/or plan of execution shall be in-place and approved by VAHCS

Infection Control representative and COR prior to start of work.

4. Refer to Specification Section 01 35 26.1.11 for Personal Protective Equipment

Requirements.

F. Security

VA Directive 0710: VA policy requires all personnel be subject to an appropriate background investigation (Special Agreement Check (SAC)) Check (SAC)) prior to permitting access to VA information system. Badging must be secured prior to any contractor beginning work on the premises. The Contractor will determine the type of badge required for their contractor(s) based on the following criteria:

1. If contractor requires escorted access to RHJVAMC for less than 15 days per year, they will require a Visitor Badge.

2. If contractor requires any other access other than 15 days per calendar year, they will require a PIV-I Badge.

Prior to receiving sponsorship for any badge, all contractors must complete Contractor Safety

Training through the Safety Service as coordinated through the COR. Training occurs every other Wednesday at 9:00 am in the Engineering Conference Room (G206k). Procedures for acquiring the appropriate identification badge for a contractor are identified below.

1. Fill out fingerprint forms and have fingerprints done at the PIV Office. Contractors can walk-in to PIV Office Monday- Friday from 8:00 a.m. – 3:30 p.m. for fingerprints.

2. Complete background Investigation form.

3. Complete Contractor Safety Training.

G. Safety

Prior to commencing work, general contractor shall provide proof that an OSHA certified

“competent person” (CP) in compliance with (29 CFR 1926.20(b)(2) will supervise all work under this contract and maintain a continual presence at the work site whenever the general or subcontractors are present. At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the CO and has authority to act for the Contractor. Assigned CP shall have completed the OSHA 30-hour construction safety training within the past five (5) years and all other construction workers shall have at least a 10-hour OSHA course. Refer to Specification Section 01 35 26 Safety Requirements for details.

H. Schedules

The VA requires a schedule be submitted no later than 45 calendar days of Notice to Proceed

(NTP). The schedule shall be submitted in electronic PDF format using Microsoft Project or equivalent software. Work could be after normal business hours between 1700 and 0700. Any work that is to be performed outside those hours are to be clearly identified on the schedule and approved by the COR prior to commencement of work. Refer to Specifications Section 01 32

16.1.5 for Project Schedule Submittal Process.

The schedule will be updated weekly by the contractor. A summary of progress and comments on any deviations from the schedule will be included in the weekly contractor report. Weekly schedule updates will be uploaded into the document sharing program.

I. Parking/Laydown Area

The Contractor shall make arrangements for parking. At no time shall vehicles be parked on roadways, patient parking areas, the loading dock, etc. Coordinate use of the loading dock for loading/unloading material with the COR. Materials shall not be deposited on the loading dock for any length of time.

There is no guarantee for laydown of material. The VAHCS shall not provide an extensive area for storage of materials and laydown. Scheduling and coordination with the VAHCS will be critical. Materials may be staged provided that the materials are secured and inaccessible by

VAHCS patients. Interim Life Safety Measure (ILSM) Permit may be required for staged materials due to increased combustible loading. It is the responsibility of the Contractor to ensure their materials remain secure.

J. Utility Shutdowns

If necessary, to interrupt utility services, the Contractor must coordinate and request a shutdown with the VAHCS prior to shutting down or interrupting any utility system. The Contractor shall provide a minimum of 14 calendar days of notice for a utility shutdown. The Contractor shall make every effort possible to reduce the amount and duration of impacts of utility shutdowns.

Requests to shutdown utilities are dependent upon the VAHCS’s ability to maintain normal operations. Should a request be denied due to clinical needs, the COR shall inform the contractor of alternate dates and times that meet the VAHCS’s needs. The Contractor shall submit to the COR a plan that identifies all utilities required to be shut down, a coordination/ work plan (including subcontractors), and provide documentation of all necessary pretests along with the submission of a shutdown request.

K. Site Investigation

All interested contractors will be invited to a pre-bid meeting. While not required, the contractor is strongly encouraged to attend the on-site pre-bid meeting. Access to the work areas and specific explanation of Statement of Work requirements will be discussed.

However, no questions will be answered during the pre-bid meeting. All questions must be officially submitted through the Vendor Portal. No comments, actions, or discussion (verbal or otherwise) are to be considered direction or answers to any questions, nor will they be considered accurate or binding unless submitted and answered in writing through the CO as an official request for information (RFI). Contractor site investigation outside of the pre-bid meeting shall not be allowed.

L. Submittals

1. Shop Drawing/Product Data: Submit in accordance with Specification Section 01 33 23

Shop Drawings, Product Data, and Samples. Submit materials to be used in the project to the COR for approval prior to purchasing. VA review period is 15 working days for submittals and ten (10) working days for RFI’s.

2. Sustainability Action Plan, Low Pollutant-Emitting Materials Tracking Spreadsheet, Construction Indoor Air Quality (IAQ) Management Plan: Within 30 days after the

Preconstruction Meeting provide documentation complying with Specification Section 01

81 13 Sustainable Construction Requirements.

M. Construction Drawings and Specifications

The contractor shall provide the VA with two (2) approved, completed sets of as built/record drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR. Any deviation from the original plan must be approved prior to change and must be included in the as built/record drawings. See Specification Section 01 00 00 General Requirements for details.

N. Recycling Requirement

The VA requires all recyclable material be removed and recycled. The contractor is responsible for minimizing landfill waste. The contractor will provide a list to include weight of each type of material that is recycled. Removal of all recyclables and landfill waste is the responsibility of the contractor, refer to Specification Section 01 74 19 Construction Waste Management.

O. Period of Performance

Period of Performance is 300 calendar days from Notice to Proceed, to include material lead time. The Contractor will be required to attend a preconstruction meeting. An ILSM and ICRA will be discussed at the preconstruction meeting and the approved plans to be posted at the job site.

Contractor shall have an accepted schedule, accident prevention plan (APP), and contractor quality control (CQC) plan prior to start of work. Refer to Specification Section 01 45 00 Quality

Control, Specification Section 01 35 25 Safety Requirements, and Specification Section 01 32

16.15 Project Schedules for details.

With respect to project schedule, the hospital operations shall take priority. Contractor may have to shift areas of work around to accommodate hospital operations. In the event the schedule is to be changed for any reason the contractor is responsible for notifying the COR within two (2) working days.

Records Management Obligations

A. Applicability

This clause applies to all Contractors whose employees create, work with, or otherwise handle

Federal records, as defined in Section B, regardless of the medium in which the record exists.

B. Definitions

“Federal Record” as defined in 44 U.S.C. § 3301, includes all recorded information, regardless of form or characteristics, made or received by a Federal agency under Federal law or in connection with the transaction of public business and preserved or appropriate for preservation by that agency or its legitimate successor as evidence of the organization, functions, policies, decisions, procedures, operations, or other activities of the United States Government or because of the informational value of data in them.

The term Federal record:

1. includes Department of Veterans Affairs records.

2. does not include personal materials.

3. applies to records created, received, or maintained by Contractors pursuant to their

Department of Veterans Affairs contract.

4. may include deliverables and documentation associated with deliverables.

C. Requirements

1. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at

36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.

2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA)

(5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.

3. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for

Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with

Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.

4. RHJ HCS and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of RHJ VAHCS or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the

Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of

Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to RHJ VAHCS. The agency must report promptly to NARA in accordance with 36 CFR 1230.

5. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in this SOW. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to RHJ VAHCS control or the

Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting

Officer or address prescribed in the contract. Destruction of records is EXPRESSLY

PROHIBITED unless in accordance with Paragraph (4).

6. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government and RHJ VAHCS guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.

7. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with RHJ VAHCS policy.

8. The Contractor shall not create or maintain any records containing any non-public RHJ

VAHCS information that are not specifically tied to or authorized by the contract.

9. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.

10. The RHJ VAHCS owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which RHJ VAHCS shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-

20.

11. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take RHJ VAHCS-provided records management training. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.

D. Flowdown of requirements to Subcontractors

1. The Contractor shall incorporate the substance of this clause, its terms and requirements including this paragraph, in all subcontracts under this contract, and require written subcontractor acknowledgment of same.

2. Violation by a subcontractor of any provision set forth in this clause will be attributed to the

Contractor.

IMPORTANT INFORMATION

QUOTE SUBMISSION: Send your quotation to kenyon.dulaney@va.gov.

mailto:kenyon.dulaney@va.gov

Physical bids shall not be accepted.

The following documents are to be included in the bid submission:

(1) An original, fully completed and signed SF 1442 Offer page.

(2) Acknowledgment of any amendments issued either by completing block 19 of the SF1442 or completing blocks 15a, b, and c of the Amendment and attaching to the SF 1442 Offer page.

(3) An original, fully completed bid schedule. The Base Bid amount for the entire project is entered in block 17 of the SF 1442 Offer page.

(4) A completed and signed copy of FAR 52.219-28 - POST-AWARD SMALL BUSINESS

PROGRAM REREPRESENTATION (FEB 2024), if the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the

NAICS code applicable to this contract.

PROJECT INFORMATION

PROJECT NUMBER: 534-23-513

PROJECT LOCATION:

Ralph H. Johnson VA Medical Center

109 Bee Street

Charleston, SC 29401-5799

MAGNITUDE OF CONSTRUCTION: Between $25,000 to $100,000.

NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM CODE: (NAICS): 236220

TYPE CONSTRUCTION: Commercial and Institutional Building Construction

SMALL BUSINESS SIZE STANDARD: $45.0 Million

PERIOD OF PERFORMANCE: 300 calendar days from receipt of Notice to Proceed (NTP)

WAGE DETERMINATION: Department of Labor General Decision Number SC20250023 is included as an attachment this solicitation and is applicable to any resultant contract. If necessary, subsequent revisions will be posted to the solicitation via amendment prior to bid opening. Revision may also be applicable prior to any contract award. Wage determinations are available at: https://wdolhome.sam.gov

SYSTEM FOR AWARD MANAGEMENT REGISTRATION: The System for Award

Management (SAM) is the Official U.S. Government system that consolidated the capabilities of the Central Contractor Registration (CCR including FedReg), Online Representations and

Certifications Application (ORCA), and the Excluded Parties List System (EPLS). Federal

Acquisition Registrations require that federal contractors register in SAM at www.sam.gov and enter all mandatory information into the system. Warning: FAR 4.1102(a) requires be registered in SAM at the time an offer or quotation is submitted in order to comply with the annual representations and certifications requirements. If a bid is received and bidder is not registered as required, the bid will be considered non-responsive and therefore not eligible for award.

THE EXCLUDED PARTIES LIST SYSTEM (EPLS): To ensure that the individuals or businesses providing services under the contract have not engaged in fraud or abuse regarding

Sections 1128 and 1128A of the Social Security Act regarding federal health care programs, the contractor is required to check the Excluded Parties List System (EPLS) located at https://wdolhome.sam.gov/ http://www.sam.gov/ www.sam.gov for each person or business providing services under this contract. During the performance of this contract the Contractor is prohibited from using any individual or business listed on the List of Excluded Individuals/Entities.

SECURITY

BACKGROUND INVESTIGATIONS: All contractor employees are subject to the same level of investigation as VA employees who have access to VA Sensitive Information. The level of background investigation is commensurate with the level of access needed to perform the statement of work. This requirement is also applicable to all subcontractor personnel requiring the same level of access.

Levels and associated types of Background Investigations:

• If the project requires that workers have only limited physical access to the VA facility for a period of one year or less, a local flash badge with fingerprint check is issued.

• If the project requires that workers require un-supervised, logical and/or physical access for 180 consecutive or aggregate days in a 365-day period, over a 3-year period, a background investigation is required (Special Agency Check (SAC)) which must be completed prior to being allowed access.

• If the project requires that workers have un-supervised, full-time, logical, and/or physical access for more than 6 months or more than 180 aggregate days in a one-year period, a background investigation is required (Special Agency Check and National Agency Check with Written Inquiries (NACI)) and access is not allowed until a favorable SAC completion.

All costs for SAC and NACI checks are borne by the contractor. The VA may at its discretion make deductions against the contract in order to recoup the investigation costs. Current cost for a SAC is $25.00 per employee and the current cost for a NACI check is $177.00 per employee

(subject to change at any time).

MEDICAL CENTER ACCESS: Anyone participating in the site visit, or for any other reason that involves visiting the medical center related to this solicitation, must have a valid ID on your person and your vehicle must be properly registered and insured. Visitors are prohibited from possessing weapons while on a federal installation (See 18 USC 930 – Possession of Firearms and Dangerous Weapons in Federal Facilities). Handheld cellphone use or texting while driving is also prohibited. All VA Medical Centers and associated properties are Federal Property.

PRIVACY TRAINING: All workers regardless of project length must take VA Privacy Training which will be coordinated after project award with the Contracting Officer’s Representative.

E-VERIFY SYSTEM: Companies awarded a contract with the federal government shall enroll in

E-Verify within 30 days of the contract award date. They shall also begin using the E-Verify system to confirm that all of their new hires and their employees directly working on federal contracts are authorized to legally work in the United States. E-Verify is an Internet-based system that allows an employer, using information reported on an employee's Form I-9, to determine the eligibility of that employee to work in the United States. There is no charge to employers to use E-Verify. (FAR 52.222-54).

http://www.sam.gov/

VHA DIRECTIVE 1192.01: The Construction Contractors’ representatives performing construction activities on the Cincinnati VA Medical Center-Fort Thomas validate that the following additional requirements are in place before starting construction activities on campus:

Annual influenza shot is required for all staff performing work on campus. Contractor badge must be obtained and worn by the contractor or representative at all times while on campus.

The contractor will validate in writing via a signed memo to the Contracting Officer that the above items are being done as part of the bid package. No Personally Identifiable Information

(PII) will be collected. Seasonal influenza with Vaccines (VHA Directive 1192.01)

CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEMS: The Contractor shall perform work under this contract consistent with the relevant policy and objectives identified in the agency, organizational, or facility Green Environmental Management System (GEMS) applicable for your contract. The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the agency, organizational, or facility GEMS, and provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the Contractor shall respond and take corrective action immediately. In the case of a nonconformance, the Contractor shall respond and take corrective action based on the time schedule established by the facility GEMS Coordinator. In addition, the Contractor shall ensure that their employees are aware of the roles and responsibilities identified by the environmental management system and how these requirements affect their work performed under this contract.

REFERENCES TO VA ENGINEER, RESIDENT ENGINEER, SENIOR RESIDENT ENGINEER,

OR PROJECT MANAGER: Any reference contained within contract specifications and/or drawings to the “VA Engineer”, “Resident Engineer”, “Senior Resident Engineer”, “Project

Manager”, or their abbreviations are to be replaced with “Contracting Officer’s Representative

(COR)”.

PAYMENT FOR MATERIALS STORED OFF-SITE: Payment in advance of installation for materials stored off-site is not authorized under this contract.

REVIEW REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE

ASSESSMENT SYSTEM (CPARS)

(a) As prescribed in Federal Acquisition Regulation (FAR) Part 42.15, the Department of

Veterans Affairs (VA) evaluates contractor past performance on all construction contracts that exceed $750,000 and shares those evaluations with other Federal

Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, CPARS, which is maintained by the Naval Seal Logistics Center in Portsmouth, Virginia. CPARS has connectivity with the Past Performance Information Retrieval System (PPIRS) database, which is available to all Federal agencies. PPIRS is the system used to collect and retrieve performance assessment reports used in source selection determinations and completed CPARS report cards transferred to PPIRS. CPARS also includes access to the federal awardee performance and integrity information system (FAPIIS). FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.

(b) Each contractor whose contract award is estimated to exceed $250,000 is required to register with CPARS database at the following web address:

www.cpars.csd.disa.mil. Help in registering can be obtained by contacting Customer

Support Desk at DSN: 684-1690 or COMM: 207-438-1690. Registration should occur no later than thirty days after contract award and must be kept current should there be any change to the contractor's registered representative.

(c) For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor's performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor's designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.

Failure to have a current registration in the CPARS database, or to re-assign the report to the

VA contracting officer within those thirty days, will result in the Government's evaluation being placed on file in the database with a statement that the contractor failed to respond.”

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM

NUMBE

R

DESCRIPTION OF

SUPPLIES/SERVI

CES

QUANTI

TY

UNI

T UNIT PRICE AMOUNT

1.00 JB _______________

Project replaces existing metal door with sliding glass door and installs a headwall on west wall in room B185 in the Emergency Wall.

Contract Period: Base POP Begin:

POP End:

PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z1DA - Maintenance of Hospitals and Infirmaries

GRAND TOTAL _______________

A.4 DELIVERY SCHEDULE

ITEM

NUMBER SHIPPING INFORMATION QUANTITY

DELIVERY

DATE

0001 SHIP TO: 109 Bee Street Charleston, SC 29401

USA

1.00

MARK FOR: Robert Darley

(843) 577-5011 ext 205549 robert.darley@va.gov

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)

(a) All actual and potential offerors are encouraged to provide feedback on the preaward and debriefing processes, as applicable. Feedback may be provided to agencies up to 45 days after award. The feedback is anonymous, unless the participant self-identifies in the survey. Actual and potential offerors can participate in the survey by selecting the following link: https:// www.acquisition.gov/360.

(b) The Contracting Officer will not review the information provided until after contract award and will not consider it in the award decision. The survey is voluntary and does not convey any protections, rights, or grounds for protest. It creates a way for actual and potential offerors to provide the Government constructive feedback about the preaward and debriefing processes, as applicable, used for a specific acquisition.

(End of Clause)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF

THE WORK (MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE

EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action

Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the

Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

31.7 % 6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance

Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action

Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order

11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for

Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

(End of Provision)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION

MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material,"

"domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials"

(Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the

Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the

Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR

52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

2.5 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury

Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20% percent of the bid price or $3,000,000.00, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB

2021)

(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—

(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and

(2) Standard Form 28, Affidavit of Individual Surety.

(b) The Offeror shall include with its offer the…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .