36C24718B0121-011.docx
DOCX document 2 MB Posted
- Solicitation number
- 36C24718B0121
About this file
36C24718B0121 Specs - 55714101.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24718B0121-00001000.docx | DOCX document | |
| 36C24718B0121-00001001.xlsx | XLSX spreadsheet | |
| 36C24718B0121-009.docx | DOCX document | |
| 36C24718B0121-010.txt | TXT text file | |
| 36C24718B0121-012.pdf | ||
| 36C24718B0121-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Carl Vinson VA Medical Center, Dublin, Georgia
SPECIFICATIONS
PROJECT:
Implement Retro Commissioning Recommendations Veterans Administration Health Care System A/E Contract No. VA 247-14-D-0066 Station Project No. 557-14-101
June 27 2014 Construction Documents
Charleston Office | 1941 Savage Road, Suite 300 – E Charleston, SC 29407 | PH: 843-277-2023
DEPARTMENT OF VETERANS AFFAIRS VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
| DIVISION 00 - SPECIAL SECTIONS |
| DATE |
| 00 01 15 |
| List of Drawing Sheets |
| 09-11 |
DIVISION 01 - GENERAL REQUIREMENTS
| 01 00 00 |
| General Requirements |
| 10-13 |
| 01 33 23 |
| Shop Drawings, Product Data, and Samples |
| 11-08 |
| 01 45 29 |
| Testing Laboratory Services |
| 01 57 19 |
| Temporary Environmental Controls |
| 01-11 |
| 01 74 19 |
| Construction Waste Management |
DIVISION 02 – EXISTING CONDITIONS
| 02 41 00 |
| Demolition |
| 04-13 |
DIVISION 03 – CONCRETE
| 03 30 53 |
| (Short-Form) Cast-in-Place Concrete |
| 10-12 |
DIVISION 04 – MASONRY
| 04 05 16 |
| Masonry Grouting |
| 09-11 |
| 04 20 00 |
| Unit Masonry |
| 05-12 |
| 04 72 00 |
| Cast Stone Masonry |
| 06-13 |
DIVISION 05 – METALS
| 05 12 00 |
| Structural Steel Framing |
| 11-12 |
DIVISION 06 – WOOD,PLASTICS AND COMPOSITES
| 06 10 00 |
| Rough Carpentry |
| 09-11 |
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
| 07 60 00 |
| Flashing and Sheet Metal |
| 12-13 |
| 07 81 00 |
| Applied Fireproofing |
| 11-11 |
| 07 84 00 |
| Firestopping |
| 10-11 |
| 07 92 00 |
| Joint Sealants |
| 12-11 |
DIVISION 08 - OPENINGS
| 08 33 00 |
| Coiling Doors and Grilles |
| 10-11 |
| 08 90 00 |
| Louvers and Vents |
| 10-11 |
DIVISION 09 – FINISHES
| 09 22 16 |
| Non-Structural Metal Framing |
| 07-13 |
| 09 29 00 |
| Gypsum Board |
| 02-13 |
| 09 91 00 |
| Painting |
| 07-13 |
Implement Retro Commissioning Recommendations Carl Vinson VA Medical Center-Dublin, Ga
Construction Documents – June 27, 2014
00 01 10-1
DIVISION 21- FIRE SUPPRESSION
| 21 05 11 |
| Common Work Results for Fire Suppression |
| 11-09 |
| 21 13 13 |
| Wet-Pipe Sprinkler Systems |
| 05-08 |
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
| 23 05 11 |
| Common Work Results for HVAC |
| 11-10 |
| 23 05 12 |
| General Motor Requirements for HVAC and Steam |
Generation Equipment 11-10
| 23 05 41 |
| Noise and Vibration Control for HVAC Piping and |
Equipment 11-10
| 23 05 93 |
| Testing, Adjusting, and Balancing for HVAC |
| 05-11 |
| 23 07 11 |
| HVAC and Boiler Plant Insulation |
| 05-11 |
| 23 09 23 |
| Direct-Digital Control System for HVAC |
| 09-11 |
| 23 21 13 |
| Hydronic Piping |
| 09-12 |
| 23 22 13 |
| Steam and Condensate Heating Piping |
| 23 31 00 |
| HVAC Ducts and Casings |
| 03-13 |
| 23 34 00 |
| HVAC Fans |
| 23 37 00 |
| Air Outlets and Inlets |
| 11-09 |
| 23 40 00 |
| HVAC Air Cleaning Devices |
| 02-12 |
| 23 73 00 |
| Indoor Central-Station Air-Handling Units |
| 04-11 |
DIVISION 26 – ELECTRICAL
| 26 05 11 |
| Requirements for Electrical Installations |
| 12-12 |
| 26 05 19 |
| Low-Voltage Electrical Power Conductors and Cables |
| 07-13 |
| 26 05 26 |
| Grounding and Bonding for Electrical Systems |
| 12-12 |
| 26 05 33 |
| Raceway and Boxes for Electrical Systems |
| 05-14 |
| 26 24 16 |
| Panelboards |
| 05-14 |
| 26 29 11 |
| Motor Controllers |
| 12-12 |
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
| 28 31 00 |
| Fire Detection and Alarm |
| 10-11 |
SECTION 00 01 15 LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
| 5-T1 | TITLE SHEET AND PROJECT INFORMATION |
| 5-T2 | SYMBOLS & LEGENDS |
| 5-T3 | PHASING PLAN & NOTES |
| 5-A1 | EXISTING ROOF PLAN |
| 5-A2 | ENLARGED MECHANICAL ROOM |
DEMOLITION FLOOR PLANS
| 5-A3 | EXISTING EXTERIOR BUILDING ELEVATIONS |
| 5-A4 | ENLARGED MECHANICAL ROOM FLOOR PLANS |
| 5-A5 | EXTERIOR BUILDING ELEVATIONS |
| 5-A6 | ARCHITECTURAL DETAILS |
STRUCTURAL
| 5-S1 | GENERAL STRUCTURAL NOTES |
| 5-S2 | FRAMING PLANS |
| 5-S3 | SECTIONS & DETAILS |
HEATING, VENTILATING, AIR CONDITIONING
| 5-H1 | LEGENDS AND ABBREVIATIONS |
| 5-H2 | HVAC – ROOF DEMOLITION |
| 5-H3 | HVAC – ENLARGED MECHANICAL ROOM DEMOLITION PLANS |
| 5-H4 | HVAC – ENLARGED MECHANICAL ROOM DEMOLITION PIPING PLANS |
| 5-H5 | HVAC – ROOF PLAN |
| 5-H6 | HVAC – ENLARGED MECHANICAL PLANS |
| 5-H7 | HVAC – ENLARGED MECHANICAL PIPING PLANS |
| 5-H8 | HVAC BUILDING SECTIONS |
| 5-H9 | HVAC – SCHEDULES AND DETAILS |
| 5-H10 | HVAC - CONTROL DIAGRAM AND POINTS LISTS |
00 01 15 - 1
ELECTRICAL
| 5-E1 | ELECTRICAL LEGENDS, GENERAL NOTES, ABBREVIATIONS AND AHU WIRING DIAGRAM |
| 5-E2 | ELECTRICAL ENLARGED MECHANICAL ROOM DEMOLITION PLAN AND NOTES |
| 5-E3 | ELECTRICAL ENLARGED MECHANICAL ROOM PROPOSED FLOOR PLANS, MECHANICAL EQUIPMENT SCHEDULE AND NOTES |
| 5-E4 | EXISTING SCHEDULE PANELBOARDS AND PANELBOARD SCHEDULE NOTES |
| 5-E5 | NEW SCHEDULE PANELBOARDS AND PANELBOARD SCHEDULE NOTES |
FIRE PROTECTION
| 5-FP1 | ROOF FIRE PROTECTION PLAN |
| 5-FP2 | ENLARGED MECHANICAL ROOM |
FIRE PROTECTION DEMO PLANS
5-FP3 ENLARGED MECHANICAL ROOM
FIRE PROTECTION PLANS
- - - END - - -
00 01 15 - 2
Implement Retro Commissioning Recommendations Project No. 557-14-101 Carl Vinson VA Medical Center-Dublin, GA Construction Documentation (CD) Submission – May 30, 2014
SECTION 01 00 00 GENERAL REQUIREMENTS
TABLE OF CONTENTS
| GENERAL INTENTION | 1 |
| STATEMENT OF BID ITEM(S) | 3 |
| SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR | 3 |
| CONSTRUCTION SECURITY REQUIREMENTS | 3 |
| FIRE SAFETY | 5 |
| OPERATIONS AND STORAGE AREAS | 7 |
| ALTERATIONS | 10 |
| INFECTION PREVENTION MEASURES | 12 |
| PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS | 14 |
| RESTORATION | 15 |
| AS-BUILT DRAWINGS | 16 |
| USE OF ROADWAYS | 16 |
| TEMPORARY USE OF EXISTING ELEVATORS | 16 |
| TEMPORARY TOILETS | 16 |
| AVAILABILITY AND USE OF UTILITY SERVICES | 16 |
| TESTS | 18 |
| INSTRUCTIONS | 18 |
| HISTORIC PRESERVATION | 19 |
| PROCORE CONSTRUCTION PROJECT MANAGEMENT SYSTEM (CPMS) | 20 |
i
SECTION 01 00 00 GENERAL REQUIREMENTS
1.1 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Dublin, Georgia VA for the Implement Retro Commissioning project as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the Medical Center COR.
C. Offices of an Architect-Engineer service may render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
F. Safety:
1. Prior to commencing work, general contractor shall provide proof that a OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present. OSHA certified “competent person” cannot be the job site superintendent.
2. Contractor shall provide proof that a safety representative will maintain a presence at the work site whenever the general or subcontractors are present. The safety representative may be the OSHA certified “competent person,” if workplace hazards do not warrant additional safety oversight.
3. Contractor shall document daily safety meetings on the daily logs turned into the COR. Safety meetings shall highlight any safety issues Implement Retro Commissioning Recommendations Carl Vinson VA Medical Center-Dublin, Ga
Construction Documents – June 27, 2014
01 00 00 - 15 that will be encountered during the work day and shall list all hazardous conditions and the associated competent person that will be inspecting the preventative measures and overseeing the hazardous condition. The OSHA Required Competent Person inspections that must be documented on daily safety reports include, but are not limited to, asbestos work, assured equipment grounding, concrete slab lift operations, cranes and derricks, demolition, material chutes, fall protection, hot work, ladders, lead work, lockout, means of egress, penetrations, personnel hoists, power transmission lines, rigging equipment, scaffolding, and trenching/excavations. The required Competent Person inspections are the contractor’s responsibility with VA providing oversight.
4. Contractor must comply with VA Lock-out/Tag-out policy. Written permits must be approved for confined space entry, excavations deeper than 15”, hot work, live electrical work, and creating any hole or penetration in floors, walls, or ceilings. Except for hot work operations or actual emergencies, these tasks require a 24-hour advanced notice to allow for proper planning and adequate task review.
5. Contractors are expected to independently provide properly trained personnel and all safety equipment necessary for the contracted work including, but not limited to, personal protective equipment (i.e., safety glasses, face shields, ear plugs, hard hats, steel-toed footwear, flame-retardant clothing, gloves, etc.), atmospheric testing devices (such as “four-gas” monitors), confined space retrieval or extraction gear (harnesses, tripods, etc.), fall prevention/protection devices, lockout locks/tags/devices, excavation shoring or “trench boxes,” etc. Please note that lockout locks and tags used by the contractor must comply with Dublin VAMC requirements; COR can provide specific details. Contractor is also responsible for having all MSDS’s on their job site location.
6. Dublin VAMC reserves the right to temporarily terminate contractor operations, without financial penalty or other negative contract implications, if instances of non-compliance with safety regulations or generally accepted safe work practices are observed. Operations will not resume until all safety issues have been resolved to the satisfaction of Dublin VAMC management.
G. Training:
1. All employees of general contractor and subcontractors shall have the 10-hour OSHA certified Construction Safety course and /or other relevant competency training, as determined by VA CP with input from the ICRA team. In addition, the on-site superintendent, OSHA certified “competent person,” and safety manager shall have the 30- hour OSHA certified Construction Safety course and /or other relevant competency training, as determined by VA CP with input from the ICRA team.
2. Submit training records of all such employees for approval to COR before employees show up to the jobsite. No VA badges will be issued if OSHA certificates are not received by COR.
H. VHA Directive 2011-36, Safety and Health during Construction, dated 9/22/2011 in its entirety is made a part of this section.
I. The contractor must provide written certification that all contract employees assigned to the work site have had a pre-placement tuberculin screening within 90 days prior to assignment to the worksite and been found to have negative TB screening reactions. Contractors will be required to show documentation of negative TB screening reactions for any additional workers who are added after the 90-day requirement before they will be allowed to work on the work site. Contract employees manifesting positive screening reactions to the tuberculin must be examined according to current CDC guidelines prior to working on Veterans Health Administration (VHA) property. Subsequently, if the employee is found without evidence of active (infectious) pulmonary TB, a statement documenting examination by a physician must be on file with the employer (construction contractor), noting that the employee with a positive tuberculin screening test is without evidence of active (infectious) pulmonary TB. If the employee is found with evidence of active (infectious) pulmonary TB, the employee would require treatment with a subsequent statement to the fact on file with the employer before being allowed to return to work on VHA property.
1.2 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, mechanical and electrical work, necessary removal of existing construction and certain other items. Time to completion is 365 days.
B. BID DEDUCTIVE ALTERNATE NO. 1- Remove the coiling door to be installed in Room 5.2 and all related work related to installation of coiling door in a new masonry opening. Time to completion is 365 days.
D BID DEDUCTIVE ALTERNATE NO. 2: Remove humidifier and steam hook-up from humidifier section in AHU 5.4. Humidifier section shall remain for future humidifier addition. Remove also work associated with DEDUCTIVE ALTERNATE NO. 1. Time to completion is 365 days.
C. BID DEDUCTIVE ALTERNATE NO.3- Remove AHU 5.3 from the project and all related work associated with this AHU. Remove also work associated with DEDUCTIVE ALTERNATE NO. 1 and 2. Time to completion is 300 days.
D. Note that deductive alternates are cumulative.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. AFTER AWARD OF CONTRACT, one set of specifications and drawings will be furnished. These drawings and specifications may consist of those returned by prospective bidders.
B. Additional sets of drawings may be made by the Contractor, at Contractor's expense.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub- contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate flash badge, issued by the VA Police and Security department. They may also be subject to inspection of their personal effects when entering or leaving the project site. Paperwork for requesting a flash badge will be provided by the COR. Each employee requesting flash badge will be required to have fingerprints taken by VA Police and Security and a background check run. Employees with a negative adjudication will not be allowed to work on site.
2. For working outside the “regular hours” as defined in the contract, The General Contractor shall give three days notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
4. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
5. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
D. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. Separate permits shall be issued for General Contractor and its employees for parking in designated areas only.
1.5 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
E84-2009.............Surface Burning Characteristics of Building Materials
2. National Fire Protection Association (NFPA):
10-2010..............Standard for Portable Fire Extinguishers 30-2008..............Flammable and Combustible Liquids Code 51B-2009.............Standard for Fire Prevention During Welding, Cutting and Other Hot Work 70-2011..............National Electrical Code 101-2012.............Life Safety Code 241-2009.............Standard for Safeguarding Construction, Alteration, and Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926..........Safety and Health Regulations for Construction
4. VHA Directive 2005-007 B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to COR for review for compliance with VHA Directive 2005-007, NFPA 101 and NFPA 241. Prior to beginning work, all employees of the contractor and/or any subcontractors shall undergo a safety briefing provided by the general contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, etc. Provide documentation to the COR that all construction workers have undergone contractor’s safety briefing.
C. Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).
E. Temporary Construction Partitions:
1. Close openings in smoke barriers and fire-rated construction to maintain fire ratings. Seal penetrations with listed through- penetration fire stop materials in accordance with Section 07 84 00, FIRESTOPPING.
F. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.
G. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with COR.
H. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to COR.
I. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA 241 and NFPA 10.
J. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.
K. Sprinklers: Install, test and activate new automatic sprinklers prior to removing existing sprinklers.
L. Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections. Provide fire watch for impairments more than four hours in a 24-hour period. Request interruptions in accordance with Article, OPERATIONS AND STORAGE AREAS, and coordinate with COR. All existing or temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with the medical center. Parameters for the testing and results of any tests performed shall be recorded by the medical center and copies provided to the COR.
M. Smoke Detectors: Prevent accidental operation. Remove temporary covers at end of work operations each day. Coordinate with COR.
N. Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B. Coordinate with COR at least TWO (2) hours in advance. Designate contractor's responsible project-site fire prevention program manager to permit hot work. Hot work permits must be obtained from COR and posted at location of hot work.
P. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with, and report findings and corrective actions weekly to COR.
Q. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and additions under construction. In separate and detached buildings under construction, smoking is prohibited except in designated smoking rest areas.
R. Dispose of waste and debris in accordance with NFPA 241. Remove from buildings daily.
S. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than four work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
F. Phasing: To ensure such executions, Contractor shall furnish the COR with a schedule of phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR six (6) weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to insure accomplishment of this work in successive phases mutually agreeable to COR and Contractor.
G. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.
H. When a building is turned over to Contractor, Contractor shall accept entire responsibility therefore.
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
I. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services as noted on drawings. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No outage shall last more than FOUR (4) hours unless preapproved by COR. No utility service such as water, gas, steam, sewers or electricity, HVAC, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de- energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS for additional requirements. If work during outage cannot be completed in four-hour time frame, it is the contractor’s responsibility to provide temporary utility services to the areas affected. Contractor shall plan on portable cooling/heating
2. Contractor shall submit a request to interrupt any such services to COR, in writing, ONE (1) week in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
J. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
K. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
L. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 INFECTION PREVENTION MEASURES
A. Implement the requirements of VAMC’s Infection Control Risk Assessment (ICRA) team. ICRA Group may monitor dust in the vicinity of the construction work and require the Contractor to take corrective action immediately if the safe levels are exceeded.
B. Establish and maintain a dust control program as part of the contractor’s infection preventive measures in accordance with the guidelines provided by ICRA Group. Prior to start of work, prepare a plan detailing project-specific dust protection measures, including periodic status reports, and submit to and Facility ICRA team for review for compliance with contract requirements in accordance with Section 01
33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES.
1. All personnel involved in the construction or renovation activity shall be educated and trained in infection prevention measures established by the medical center.
C. Medical center Infection Control personnel shall monitor for airborne disease (e.g. aspergillosis) as appropriate during construction. A baseline of conditions may be established by the medical center prior to the start of work and periodically during the construction stage to determine impact of construction activities on indoor air quality. In addition:
1. The COR and VAMC Infection Control personnel shall review pressure differential monitoring documentation to verify that pressure differentials in the construction zone and in the patient-care rooms are appropriate for their settings. The requirement for negative air pressure in the construction zone shall depend on the location and type of activity. Upon notification, the contractor shall implement corrective measures to restore proper pressure differentials as needed.
2. In case of any problem, the medical center, along with assistance from the contractor, shall conduct an environmental assessment to find and eliminate the source.
D. In general, following preventive measures shall be adopted during construction to keep down dust and prevent mold.
1. Dampen debris to keep down dust and provide temporary construction partitions in existing structures where directed by COR. Blank off ducts and diffusers to prevent circulation of dust into occupied areas during construction.
2. Do not perform dust producing tasks within occupied areas without the approval of the COR. For construction in any areas that will remain jointly occupied by the medical Center and Contractor’s workers, the Contractor shall:
a. Provide dust proof temporary drywall construction barriers to completely separate construction from the operational areas of the hospital in order to contain dirt debris and dust. Barriers shall be sealed and made presentable on hospital occupied side. Install a self-closing rated door in a metal frame, commensurate with the partition, to allow worker access. Maintain negative air at all times. A fire retardant polystyrene, 6-mil thick or greater plastic barrier meeting local fire codes may be used where dust control is the only hazard, and an agreement is reached with the COR and Medical Center.
b. HEPA filtration is required where the exhaust dust may reenter the breathing zone. Contractor shall verify that construction exhaust to exterior is not reintroduced to the medical center through intake vents, or building openings. Install HEPA (High Efficiency Particulate Accumulator) filter vacuum system rated at 95% capture of 0.3 microns including pollen, mold spores and dust particles. Insure continuous negative air pressures occurring within the work area. HEPA filters should have ASHRAE 85 or other prefilter to extend the useful life of the HEPA. Provide both primary and secondary filtrations units. Exhaust hoses shall be heavy duty, flexible steel reinforced and exhausted so that dust is not reintroduced to the medical center.
c. Adhesive Walk-off/Carpet Walk-off Mats, minimum 600mm x 900mm (24” x 36”), shall be used at all interior transitions from the construction area to occupied medical center area. These mats shall be changed as often as required to maintain clean work areas directly outside construction area at all times.
d. Vacuum and wet mop all transition areas from construction to the occupied medical center at the end of each workday. Vacuum shall utilize HEPA filtration. Maintain surrounding area frequently. Remove debris as they are created. Transport these outside the construction area in containers with tightly fitting lids.
e. The contractor shall not haul debris through patient-care areas.
f. Using a HEPA vacuum, clean inside the barrier and vacuum ceiling tile prior to replacement. Any ceiling access panels opened for investigation beyond sealed areas shall be sealed immediately when unattended.
g. There shall be no standing water during construction. This includes water in equipment drip pans and open containers within the construction areas. All accidental spills must be cleaned up and dried within 12 hours. Remove and dispose of porous materials that remain damp for more than 72 hours.
h. At completion, remove construction barriers and ceiling protection carefully, outside of normal work hours. Vacuum and clean all surfaces free of dust after the removal.
E. Final Cleanup:
1. Upon completion of project, or as work progresses, remove all construction debris from above ceiling, vertical shafts and utility chases that have been part of the construction.
2. Perform HEPA vacuum cleaning of all surfaces in the construction area. This includes walls, ceilings, cabinets, furniture (built-in or free standing), partitions, flooring, etc.
3. All new air ducts shall be cleaned prior to final inspection.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are indicated on drawings and which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR's review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
E. COR shall perform an as-built red-line review prior to all progress payment approvals.
1.12 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.13 TEMPORARY USE OF EXISTING ELEVATORS
A. Contractor will not be allowed the use of existing elevators. Outside type hoist shall be used by Contractor for transporting materials and equipment.
1.14 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workmen) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.15 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain heat by connecting to Medical Center heating distribution system.
a. Steam is available at no cost to the Contractor, however, it is the contractor’s responsibility to provide for all connection labor and materials.
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor, however, it is the contractor’s responsibility to provide for all connection labor and materials.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection. Water is available at no cost to the Contractor, however, it is the contractor’s responsibility to provide for all connection labor and materials.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR's discretion) of use of water from Medical Center's system.
G. Steam: Furnish steam system for testing required in various sections of specifications.
1. Obtain steam for testing by connecting to the Medical Center steam distribution system. Steam is available at no cost to the Contractor, however, it is the contractor’s responsibility to provide for all connection labor and materials.
2. Maintain connections, pipe, fittings and fixtures and conserve steam-use so none is wasted. Failure to stop leakage or other waste will be cause for revocation (at COR's discretion), of use of steam from the Medical Center's system.
1.16 TESTS
A. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
B. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
C. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire complex which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc.
D. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably short period of time during which operating and environmental conditions remain reasonably constant.
E. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.17 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (two hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed instructions to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
D. Submittals: Submit a compact disk containing .pdf files of all approved submittals containing VA COR approval stamp. Each specification section shall be its own .pdf file.