36C24718B0121 00001 RFIs, Questions _ Answers - 36C24718B0121.xlsx

View the file

Other files

File Type Posted
36C24718B0121-00001000.docx DOCX document
36C24718B0121-011.docx DOCX document
36C24718B0121-009.docx DOCX document
36C24718B0121-010.txt TXT text file
36C24718B0121-012.pdf PDF
36C24718B0121-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

RFIs557-14-101, Solicitation Number 36C24718B0121
QuestionResponse
1Spec section 23 73 00/2.1/K calls for the chilled water coils to have galvanized supports. In the past it has been my experience that chilled water coils which will constantly be exposed to moisture due to condensate will have the casing deteriorate very quickly when it is galvanized steel. Should the casings be made from stainless steel?Specification shall remain as written, requiring hot dipped galvanized steel supports

2 Spec section 23 73 00/2.1/K calls for the chilled water coil to have copper fins if it is serving surgery suites. Please clarify which unit, if any, will be serving surgical suites. No units will serve surgical suites

3 The existing units have UV arrays. Should the replacement units be furnished with UV arrays? If so, is their purpose purely for coil cleaning or are they there for on the fly air decontamination? Do not provide the replacement units with UV arrays.

4Is it the intent to only replace the Hydronic piping and insulation from the isolation valves to the new equipment?Provide demolition and new work of chilled and hot water piping per H4 and H7. Intent is to replace and add piping and insulation only as necessary to properly tie in new units in the course of one weekend.
5Control System Architecture:Specification 23 09 23 shall remain as written, allowing only approved controls manufacturers and approved Tridium Integretion contractors.
Third Party Interfaces:
· The Controls Systems shall include necessary hardware, equipment and software to allow data communications between the Controls Systems and building systems supplied by other trades.
· The other manufacturers and contractors supplying other associated systems and equipment will provide their necessary hardware, software and start-up at their cost and will cooperate fully with the Controls Contractor in a timely manner and at their cost to ensure complete functional integration.
· The existing controllers are Honeywell and are to be upgraded.
· Is another Niagara/Triduim open protocol framework with BACnet comm. Acceptable? Local contractor will be hired to perform verification testing and intergrading to existing graphic package.

6 After the weekend AHU installed and before and ductwork is to be connected, the unit should be pressured tested before moving forward with the air distribution connection as per specification. Will there be a representative onsite to sign off on this testing? COR or approved VA representative will be available to sign off on pressure testing.

7 During the walk through there was insulation missing from some of the piping in the penthouse area. Is this to be repaired during this project? The only repairs included in this bid are those specifically listed in the bid documents.

8Is this project sales tax exempt? If the project is sales tax exempt can the government provide a sales tax exemption certificate?No.
9Where will the designated parking and laydown area be for workers accessing the construction site?Yes.
10Will the government accept the use of the industry leading Procore Project Management software as the primary submittal and data tracking tool for this project? The software is compatible with the VA’s networks and is currently in use at many VA locations.Yes.
11During construction in an area where the ceilings or fire suppression system will be disrupted, will NFPA 241 apply? Will the government require additional security measures beyond NFPA code such as fire watch, temporary fire alarms, adjustments to sprinkler heads, etc.Yes.
12Does the Government have a fire alarm servicer that they currently work with? What is the name and contact information of the person or persons that will need to be coordinated with for security and fire alarm and suppression systems work and/or disruptions?Fire Alarm system is Simplex Grinnell. POC at Simplex is John Sawyer, 678-896-4090. VA has in-house Fire Safety Officer who can assist with outages.
13Has the work area been checked for asbestos?It is not expected to encounter any asbestos-containing materials on this project.
14Does the VA have a lift plan for any heavy equipment required to position the new equipment on site?Crane operator shall provide lift plan for approval by VA Safety Office.
15Due to current potentially significant tariffs being placed on the importation of building materials such as wood or steel by the current Presidential Executive Branch, if a tariff is placed after bid time and before award will the government consider a price escalation on a contract value for products such as steel or wood should the executive branch levee tariffs effecting such materials? Most of these materials would still have been Buy American compliant as the tariffs would increase pricing on all steel or wood materials, regardless of origin.No, this is a firm fixed price contract.
16Do you have a current sprinkler company under contract for the facility?Simplex Grinnell is our Fire Sprinkler monitoring company, see previous POC information for John Sawyer.
17Who is your controls company for your Mechanical systems on site?See 23 09 23 for list of approved Tridium Controls integrators on site.
18It does not show that there will be temporary cooling but for phase - one in the Pharmacy. Phase 1. Is this correct? It also states under Phase 2-3 and 4 that the GC is to provide conditioned air on all phases. Please explain what you would like to have.Only unit 5.4 is required to run on the weekends. If the contractor can remove and replace the AHU over the course of a weekend (from 5:00 pm Friday evening to 5:00 am Monday morning), then no temporary cooling will be required. However, because the pharmacy is operation 24/7, it will require temporary cooling while 5.4 is replaced.
19The roof we went out on is a PVC roof. Is the roof above the units the same?Yes.
20Has there been an asbestos test report done on each mechanical roof? If so can they be supplied?No.
21Phase 4 penthouse is an alternate. If this is not taken is there a need to put in the roll up door for demo reasons? Does this need to be priced separately?No, the roll up door for demo will not be required in the Phase 4 bid deduct.
22Is there power for the temporary unit close by that can be used?Yes, however it will be contractor's responsibility to provide connection to this power.
23Where will the lay down area be for the contractor?This decision will be made during the Pre-Construction meeting, however, it is expected to be in close proximity to Building 5.
24What is the square footage for the Pharmacy that will need to be cooled so we can get the correct size unit.Pharmacy is approximately 10,000 SF
25Will there need to be any test and balance done on the Temporary Unit?No.
26What time on Friday will the area be given to the contractor to provide time for the switch over of the units?5:30 pm Friday afternoon through 5:00 am Monday morning.
27Will there be any time constraints on working hours when it comes to the switch overs?No, the contractor should plan to work as necessary to complete the change overs between 5:30 pm Friday and 5:00 am Monday morning.
28Will there be constraints as to when saw cutting can be done?Yes, after hours on weekdays or on a weekend.
29Can the test and balance be done after hours through the week?Yes, if TAB contractor can avoid distupting patients and staff, as the clinics will be operational.
30After the units are in place will they need to be commissioned again by a third party?No, 3rd party commissioning is not a part of this project.
31Can the electrical be done other than on weekends? Like changing out the boxesThe units must be running during the hours of 6:00 am - 5:30 pm M-F. Any electrical work which will require the units to be off will need to be done after hours or on weekends.
32Spec Section 10 00 00 Section 1.1 Paragraph F States: 1. Prior to commencing work, general contractor shall provide proof that a OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present. OSHA certified “competent person” cannot be the job site superintendent. Is the intent of the government for the General contractor to provide this additional manpower as this has generally been a collateral duty of the Site Superintendent in the past. Please advise.As long as the safety of the job is being properly maintained, the Site Superintendent may serve as the OSHA certified competent person. If the contractor received an excess of Safety write-ups or repeat offenses during the Weekly Construction Safety Committee (VA employees) site visit, the CO can direct the contractor to hire a separate Safety Officer to serve for the remainder of the project. The site superintendent may only serve as the OSHA competent person for specific tasks such as confined space entry, scaffold work, etc, if he has specific additional OSHA training allowing him to function as the competent person for such specific tasks.