Z2DA--Replace Auxiliary Chiller Federal contract opportunity
Solicitation number
36C24626B0004
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6

About this file

This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by the Department of Veterans Affairs Network Contracting Office in Richmond, Virginia on January 20, 2026, for solicitation 36C24626B0004 regarding the replacement of an auxiliary chiller at Building 3 in Fayetteville, North Carolina (Project No. 565-24-113). The amendment provides government responses to vendor questions submitted during the pre-bid phase and includes a sign-in sheet from the pre-bid site visit. The bid due date and time remain unchanged from the original solicitation.

The amendment clarifies key project requirements through thirty questions and answers covering personnel qualifications, site logistics, equipment specifications, and installation scope. Notable clarifications include: the Superintendent and Site Safety Health Officer (SSHO) must be authorized to act for the prime contractor and remain on-site during work, though they may be dual-hatted if qualified; no asbestos or lead concerns are anticipated; the 120-ton auxiliary chiller must meet Buy American requirements with no specific manufacturer mandated; contractors must utilize the existing concrete pad and seek VA approval if exceeding its footprint; parking is available at the facility with laydown areas directed by the Contracting Officer; two existing electrical circuits should be reused if adequate amperage is available, otherwise the second circuit must be abandoned; welded steel piping (not fusion) is required; submittals on all products require approval; controls integration must be performed by a certified contractor qualified on Tridium DDC systems; and testing and balancing is not required. Specification sections 23 07 11 (HVAC Insulation), 23 21 23 (Hydronic Pumps), 23 21 13 (Hydronic Piping), and 23 64 00 (Packaged Water Chillers) are referenced for detailed technical requirements.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--Replace Auxiliary Chiller, newest first.
File Type Posted
36C24626B0004 0002.docx DOCX document
Aux Chiller Abstract.pdf PDF
Sign In Sheet.pdf PDF
23 21 13 HydronicPiping.pdf PDF
23 21 23 Hydronic Pumps.pdf PDF
23 07 11 HVAC Insulation.pdf PDF
Sign In Sheet 2.pdf PDF
236400 Packaged Water Chillers.pdf PDF
Photo 2- Data Plate west Airstack.pdf PDF
Photo 1 - Existing Airstack Chiller at Bldg. 3.pdf PDF
Specs AuxChillBldg3.pdf PDF
36C24626B0004_2.docx DOCX document
Attachment 1 - M103 AHU Bldg. 3 Mech Room 20 Chilled Water 2014.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 01-20-2026 565-24-113 Department of Veterans Affairs Network Contracting Office 6 1201 Broad Rock Blvd Richmond

VA

23249 Department of Veterans Affairs Network Contracting Office 6 1201 Broad Rock Blvd Richmond

VA

23249 To all Offerors/Bidders

36C24626B0004 12-09-2025

X X X x The purpose of this Amendment is to provide Government responses to all received Questions from Vendors and post the sign-in sheet from the pre-bid site visit.

1. See the following pages for all Government responses.

2. See the attached files for additional supporting information for Government responses.

3. Please acknowledge this and any other Amendments to this solicitation by completing Block 18 of the SF 1442 on your submitted offer.

The bid due date and time remain unchanged.

Michael Proctor Contracting Officer Replace Auxiliary Chiller Building 3 Project no: 565-24-113 Pre-Bid Questions

1. Does the Superintendent need to be directly employed by the Prime Contractor? Superintendent must be authorized to act in the name of the prime contractor.

2. Must the Superintendent be on site at all times while work is commencing? Yes

3. Does the SSHO (Site Safety Health Officer) need to be directly employed by the Prime Contractor? SSHO must be authorized to act in the name of the prime contractor.

4. Must the SSHO be on site at all times while work is commencing? Yes

5. Can the Superintendent & SSHO be a dual-hatted individual assuming that individual is qualified for both roles? Yes, see Spec 01 35 26.1.9 section heading: “The Site Superintendent may also serve as SSHO if considered qualified by VA Engineering.”

6. Are there any other mandatory on-site roles required in this contract? No

7. When does the VA expect the project to start following the award? The VA generally expects the project to start shortly after the award has been granted. The exact start date will be determined based on the completion of any necessary preparatory steps.

8. Are there any concerns for Asbestos Containing Material or Lead in the areas being worked in? There is no known ACM or lead as part of this project.

9. Are there any ICRA requirements for this project? Work will be completed inside a mechanical room and outside Building 3. Dust generation must be kept to a minimum. It is not anticipated that negative air, sticky mats, plastic barriers, or similar would be required.

10. Who is the current Controls provider at the VA? There is not one controls contractor. This is an open BACNET system as per the SOW.

· Does the awarded contractor have to use this company's quote in our bid for controls integration? Not applicable

· If yes, can the VA please provide contact info? Not applicable

11. Site Visit sign in sheet posted? See Attached Sign-In sheet

12. What manufacturer chiller is required to be replaced? None specified. Must meet Buy American and SOW requirements.

13. What is the physical size of the new chiller? If bigger than existing, does the VA want to increase the size of the concrete pad or provide steel framing? Contractor to utilize the current concrete pad. If contractor’s proposed chiller exceeds the size and capacity of the current concrete pad, contractor will be responsible for any demolition and construction at no additional cost to the government. Contractor would have to first seek VA approval to exceed the current footprint as space is a premium.

14. Please confirm laydown and parking areas to be provided to contractor. Contractor may park in any available parking space at the facility. Laydown, if necessary, would be as directed by the COR. Assume the laydown area would be at the southeastern end of the facility, near the back gate.

15. Please confirm the VA will coordinate with awardee to only need 1 mobilization. Generally this job should only require 1 mobilization, assuming the VA will allow it. If the contractor mobilizes on site and the VA reschedules, this would be added cost. This question is unclear as to why multiple mobilizations are required. Contractor will provide the VA a proposed schedule and both parties will work towards those dates. Contractor will be responsible for submitting utility outage requests weeks before the desired date.

16. Scope states that the pumps be programed into the BAS – Pumps can not be programed that have existing ( Old ) drives. Should drives be replaced. If so, are there specs? If pumps are independently controlled, then they should have new drives. Otherwise, new pumps to be controlled by the new chiller.

17. Chiller Specs ( equivalent vender ) design requirements ( Screw, Recep, modular ) ? Screw or scroll chiller is what should be submitted for approval. See Spec Section 23 64 00 Packaged Water Chillers

18. Chiller power scope is not clear; there are two existing circuits which to be used and what to be done on the second. Correct, there are two electrical circuits for the existing chiller. The VA expects the two circuits to be reused with the replacement chiller unless only one circuit is required. Contractor to ensure adequate amperage is available for their proposed chiller. If second circuit isn’t required for new chiller, contractor to properly abandon circuit in place.

19. Will submittals be required on all products and approved? Yes.

20. Types of materials – can fusion piping be used? No. Welded steel is appropriate. See specification section 23 21 13 Hydronic Piping.

21. No specs on Insulation or heat tape requirements. See specification section 23 07 11 attached.

22. Is there a road closure permit required for the site for purpose of the crane to be set up? See Spec Section 01 00 00.1.6.L&M. Contractor must minimize impact to the facility. Any potential, temporary road closures and crane lift plans would have to be approved by the VA engineering and safety.

23. Please provide provisions if existing isolation valves do not hold VA will assist contractor by providing information and assistance with coordination so to avoid or address this potential problem.

24. Controls – scope states integration into BACNET card and into the BAS. Please clarify who has to be used for the integration and has access to program in system. Any certified controls contractor who is qualified to work on a Tridium DDC.

25. Existing Expansion tank – Has it been verified to work and / or leave off scope? This is an expansion tank; estimated at 44 gallons. Contractor to verify this current tank volume is adequate for proposed new chiller.

26. Air separator to be vented external of building per A2L code requirements Not applicable.

27. No defined scope on pumps ( manufacture, base mounted as existing, how should they be built out { Tripple Duty valves, gauges and temps} Alignment? Lots to know on theses. See spec Section 23 21 23 Hydronic Pumps.

28. How many on site Pre Con meetings required? There will be one Pre Con meeting.

29. Scope doesn’t state any required pre or post T&B - Please confirm if required. T&B not required. Contractor to verify flow is adequate across the primary chiller loop.

30. Is the intent for the new chiller to match the exciting modulating heat pump chiller? No.

See attached document: Sign In Sheet.

See attached document: Sign In Sheet 2.

See attached document: 23 07 11 HVAC Insulation.

See attached document: 23 21 23 Hydronic Pumps.

See attached document: 23 21 13 HydronicPiping.

See attached document: 236400 Packaged Water Chillers.