This is a comprehensive set of architectural and engineering design documents for a HVAC replacement project at the Salem VA Medical Center in Building 16. The project involves replacing the existing air handling unit serving the first floor, which is primarily office space, with a new 12-ton DX rooftop unit (RTU-1). Key scope elements include:
The design documents cover architectural, structural, mechanical, and electrical disciplines across 36 detailed sheets. The project will replace existing PTAC units, install new variable air volume (VAV) terminal units with individual room temperature control, provide two new exhaust fans for restrooms, and integrate new steam control valves for radiators into the existing Siemens building automation system. The work will enhance the HVAC systems while maintaining the building's existing business occupancy classification and will involve carefully coordinated demolition and new installation to minimize disruption to the medical center's operations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S07 Bid Abstract 1.20.2026.pdf | ||
| S07 Bid Abstract 1.20.2026.pdf | ||
| 36C24625B0029 0005.docx | DOCX document | |
| S05 RFI responses Replace Bldg 16 HVAC 658-24-106.pdf | ||
| 36C24625B0029 0004.docx | DOCX document | |
| 36C24625B0029 0003.docx | DOCX document | |
| 36C24625B0029 0002.docx | DOCX document | |
| Amendment A0002 (1).pdf | ||
| S04 Site Visit Roster _Bldg 16 HVAC System.pdf | ||
| S04_SIte Visit 12.2.2025 Attendance.pdf | ||
| 36C24625B0029_ Amendment A00002.pdf | ||
| Wage Determination 10 .03.pdf | ||
| Replace Bldg 16 HVAC - Specifications Final - 20250813.pdf | ||
| SOW 658-24-106.pdf | ||
| 36C24625B0029_1.docx | DOCX document | |
| Final SOW_DRWNG_SPEC.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARCHITECT
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
PHONE: (206) 590-2118
DESIGN TEAM
ELECTRICAL
MECHANICAL
DAVENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
PHONE: (619) 770-8552
DAVENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
PHONE: (619) 770-8552
STRUCTURAL
JUNKER GONZALEZ ENGINEERING
8285 LA MESA BLVD, SUITE C
LA MESA, CA 91942
PHONE: (858) 245-3660
PROJECT INFORMATION
STATE:
COUNTY:
JURISTICTION:
OWNER:
CONST TYPE:
OCCUPANCY:
CODE ANALYSIS PROJECT DESCRIPTION
PROJECT INVOLVES EVALUATION, SURVEY
AND DESIGN FOR REPLACEMENT OF AIR
HANDLING UNITS AT THE SALEM VA MEDICAL
CENTER BUILDING 16. THE INTENT IS TO
ENHANCE THE HVAC SYSTEMS OF THE
BUILDING AND REPLACE THE CURRENT HVAC
UNIT SERVING THE FIRST FLOOR. THE FIRST
FLOOR IS MAINLY OFFICE SPACE.
APPLICABLE BUILDING & LEVEL
BUILDING 16, LEVEL 1
APPLICABLE CLINIC
N/A
ICRA CLASS REQUIREMENTS
CLINIC RISK:
CLASS REQS:
APPROX SQUARE FEET IN SCOPE
8,509 SF
LOW
CLASS II
VIRGINIA
ROANOKE
SALEM
GOV, VETERANS AFFAIRS
EXISTING
BUSINESS
GENERAL NOTES
1. DO NOT SCALE DRAWINGS.
BLDG 16
SALEM VA MEDICAL CENTER
BUILDING WITHIN SCOPE OF THIS PROJECT
2A
15 13
29 2827
ENGINEERING DISCIPLINE: 16
SALEM VA MEDICAL CENTER
1970 ROANOKE BLVD, SALEM, VA 24153
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building No.
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
o n e e ig h th in c h o n e fo o t
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Office of Construction and Facilities Management
Department of Veteran Affairs
STAMP:
BID SET
REPLACE BUILDING 16 HVAC 658-24-106
Floor No.
Dwg.
DAV ENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
619-770-8552
WWW.DAVENERGY.COM
02/28/2025
COVER SHEET
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
MK AJ02/28/2025
G-001
REPLACE BUILDING 16 HVAC
SALEM VA MEDICAL CENTER, SALEM - VIRGINIA
PROJECT #: 658-24-106
DRAWING INDEX
PAGE # SHEET # SHEET NAME
GENERAL
1 OF 36 G-001 COVER SHEET
ARCHITECTURAL
2 OF 36 A-001 ARCH SYMBOLS, ABBREVIATIONS, & GENERAL NOTES
3 OF 36 AS101 ICRA
4 OF 36 AS111 FIRE LIFE SAFETY
5 OF 36 AD101 FIRST FLOOR DEMO PLAN
6 OF 36 AD102 DEMO CEILING PLAN
7 OF 36 AE101 FIRST FLOOR PLAN
8 OF 36 AE102 ROOF PLAN
9 OF 36 AC101 FIRST FLOOR CEILING PLAN
10 OF 36 AE301 BUILDING SECTIONS
11 OF 36 A-501 DETAILS
STRUCTURAL
12 OF 36 S-001 STRUCTURAL COVER SHEET & STRUCTURAL NOTES
13 OF 36 S-002 STRUCTURAL NOTES, VERIFICATION & INSPECTION SCHEDULES
14 OF 36 S-101 STRUCTURAL NEW WORK ROOF PLAN
15 OF 36 S-501 TYPICAL DETAILS
MECHANICAL
16 OF 36 M-001 MECHANICAL COVER SHEET
17 OF 36 MD-101 MECHANICAL 1ST FLOOR DEMOLITION PLAN
18 OF 36 MH-101 MECHANICAL 1ST FLOOR HVAC SUPPLY PLAN
19 OF 36 MH-102 MECHANICAL 1ST FLOOR HVAC RETURN / EXHAUST PLAN
20 OF 36 MH-201 MECHANICAL ROOF HVAC PLAN
21 OF 36 M-401 MECHANICAL SCHEDULES
22 OF 36 M-402 MECHANICAL SCHEDULES
23 OF 36 M-501 MECHANICAL DETAILS
24 OF 36 M-502 MECHANICAL AHU CONTROL DIAGRAM
25 OF 36 M-503 MECHANICAL SEQUENCE OF OPERATION
26 OF 36 M-504 MECHANICAL POINTS LIST
ELECTRICAL
27 OF 36 E-001 ELECTRICAL COVER SHEET
28 OF 36 ED-101 FIRST FLOOR POWER PLAN-DEMO
29 OF 36 ED-102 FIRST FLOOR LIGHTING PLAN-DEMO
30 OF 36 EP-101 FIRST FLOOR POWER PLAN-NEW
31 OF 36 EP-102 ROOF POWER PLAN-NEW
32 OF 36 EL-101 FIRST FLOOR LIGHTING PLAN-NEW
33 OF 36 E-601 SINGLE LINE DIAGRAM-DEMO
34 OF 36 E-701 PANEL SCHEDULES
35 OF 36 E-801 ELECTRICAL DETAILS
36 OF 36 E-802 ELECTRICAL DETAILS
NOT TO SCALE
FACILITY SITE PLAN
TRUE
NORTH
101A
EXTERIOR ELEVATION
INTERIOR ELEVATION
BUILDING SECTION FLAG
WALL SECTION FLAG
CALLOUT FLAG
VERTICAL GRID LINE
HORIZONTAL GRID LINE
TRUE NORTH ARROW
PROJECT NORTH ARROW
(TRUE NORTH DASHED)
ELEVATION / LEVEL MARKER
KEY NOTE
ROOM TAG
(SF OPTIONAL)
CEILING HEIGHT TAG
WALL TAG
FLOOR TAG
ROOF TAG
DOOR TAG
WINDOW TAG
SPECIALTY EQUIPMENT TAG
SIGNAGE TAG
SIGNAGE KEY NOTE
(AW SHEETS ONLY)
SIGNAGE MATERIAL TAG
(AW SHEETS ONLY)
TOILET
150 SF
A
01A
TRUE
NORTH
W1
PROJECT
NORTH
TRUE NORTH
(DASHED)
A01
D88
A5175SOAP DISH
ACT 2x2
9' - 0" AFF
F-1
R-1
SYMBOLS
A-101
A-101
A-101
EXISTING TO REMAIN
NEW CONSTRUCTION
TO DEMOLISH
(DEMO SHEET(S) ONLY)
ABOVE
BELOW
EXISTING DOOR TO REMAIN
EXISTING DOOR TO DEMOLISH
(DEMO SHEET(S) ONLY)
NEW DOOR
AREA SHOWN ON SHEET
OUT OF SCOPE
INACCESSIBLE DURING PHASE
(ICRA SHEET(S) ONLY)
TEMPORARY ICRA BOUNDRY
(ICRA SHEET(S) ONLY)
TEMPORARY ICRA BARRIER
(ICRA SHEET(S) ONLY)
TEMPORARY ICRA DOOR
(ICRA SHEET(S) ONLY)
ADHESIVE WALK-OFF MATS
(ICRA SHEET(S) ONLY)
TEMPORARY ICRA AIR PRESSURE
(ICRA SHEET(S) ONLY)
CONTRACTOR PATH OF TRAVEL
(ICRA SHEET(S) ONLY)
SMOKE COMPARTMENT PERIMETER
(FIRE LIFE SAFETY SHEET(S) ONLY)
SMOKE RATED WALL
1 HR FIRE RATED WALL
2 HR FIRE RATED WALL
SMOKE & 1 HR FIRE RATED WALL
FIRE EXTINGUISHER CABINET
(FIRE LIFE SAFETY SHEET(S) ONLY)
EMERGENCY EGRESS ROUTE
(FIRE LIFE SAFETY SHEET(S) ONLY)
SPRINKLER PER FIRE PROTECTION
DIFFUSER PER MECHANICAL
(SIZE & PROPORTION MAY VARY)
LIGHT FIXTURE PER ELECTRICAL
(SIZE & PROPORTION MAY VARY)
MATERIALS
EARTH
SAND
BATT INSULATION
RIGID INSULATION
CONCRETE
STEEL
PLYWOOD, FIRE RATED
GYPSUM BOARD, TYPE 'X'
ACOUSTICAL CEILING TILE, 2' x 2'
A-101
A-101
FEC
IN-04.02-01
ABBREVIATIONS
SYMBOLS
& AND
∠ ANGLE
@ AT
℄ CENTERLINE
° DEGREES
# NUMBER
A
AB ANCHOR BOLT
ABA ARCHITECTURAL BARRIERS ACT
A(C)T ACOUSTICAL (CEILING) TILE
ACM ASBESTOS CONTAINING MATERIAL
ACW ACOUSTICAL WALL
ADA AMERICANS W/ DISABILITIES ACT
ADJ ADJACENT
A/E ARCHITECT/ENGINEER
AF ACCESS FLOOR
AFF ABOVE FINISH FLOOR
AGG AGGREGATE
ALT ALTERNATE
ALUM ALUMINUM
APPROX APPROXIMATELY
ARCH ARCHITECT(URAL)
ASPH ASPHALT
A/V AUDIO / VIDEO
B
BARR BARRIER
BATH BATHROOM
BB BACKER BOARD
BLD(G) BUILDING
BLK(G) BLOCK(ING)
BLW BELOW
BM BEAM
BMT(U) BONE MARROW TRANSPLANT (UNIT)
BO BOTTOM OF
BOC BOTTOM OF CURB
BOS BOTTOM OF SLAB
BRC BRACE, BRACING
BRKT BRACKET
BRNG BEARING
BTM BOTTOM
BTWN BETWEEN
C
CAB CABINET
CC CONTRACTOR FURN, CONTRACTOR INST
CD CONSTRUCTION / CONTRACT DOCUMENTS
CJ CONTROL JOINT
CLG CEILING
CLR CLEAR(ANCE)
CMU CONCRETE MASONRY UNIT
CO CONTRACTING OFFICER
COL COLUMN
COMP COMPOSITION
CONC CONCRETE
CONN CONNECTION
CONST CONSTRUCTION
CONT CONTINUOUS
COORD COORDINATE
COR CONTRACTING OFFICER REPRESENTATIVE
CORR CORRIDOR
CS CONCRETE SEALER
CT CERAMIC TILE
CTR CENTER
CV CONTRACTOR FURNISHED, VA INSTALLED
D
DB DESIGN BUILD
DBL DOUBLE
DC DIRECT CURRENT
DD DESIGN DEVELOPMENT
DEMO DEMOLISH(ION)
DEPT DEPARTMENT
DG DESIGN GUIDE
DIA DIAMETER
DIM DIMENSION
DM DESIGN MANUAL
DWN DOWN
DR DOOR
DTL DETAIL
DWG DRAWING(S)
E
E EAST
EA EACH
EJ EXPANSION JOINT
ELEC ELECTRIC(AL)
ELEV ELEVATION OR ELEVATOR
ENG ENGINEER(ING)
EOC EDGE OF CURB
EOP EDGE OF PAVEMENT
EPDM ETHYLENE PROPYLENE DIENE TERPOLYMER
EQ EQUAL
EQUIP EQUIPMENT
ES EACH SIDE
ETS EXPOSED TO STRUCTURE
EX(IST) EXISTING
EXP EXPANSION
EXT EXTERIOR
F
FA FIRE ALARM
FD FLOOR DRAIN
FE(C) FIRE EXTINGUISHER (CABINET)
FF FACTORY FINISH
FFB FINISH FLOOR BREAK
FIN FINISH(ED)
FLASH FLASHING
FLR FLOOR(ING)
FLRSNT FLORESCENT
FNDN FOUNDATION
FOC FACE OF CONCRETE
FOF FACE OF FINISH
FOS FACE OF STUDS
FP FIRE PROOF
FR FIRE RATED
FRM FRAME
FT FOOT, FEET
FTG FOOTING
FUR FURRING
FURN FURNISHED
G
GA GAGE, GAUGE
GALV GALVANIZED
GE GENERAL ELECTRIC
G(W)B GYPSUM (WALL) BOARD
GC GENERAL CONTRACTOR
GL GRID LINE
GLB GLUE LAMINATED BEAM
GMU GLASS MASONRY UNIT
GOV(T) GOVERNMENT
GYP GYPSUM BOARD
H
HAC HOUSEKEEPING AIDES CLOSET
HDR HEADER
H(D)W(E) HARDWARE
HM HOLLOW METAL
HORZ HORIZONTAL
HPDL HIGH PRESSURE DECORATIVE LAM
HR HOUR
HT HEIGHT
HVAC HEATING, VENTILATION & AIR CONDITIONING
I
ICRA INFECTIOUS CONTROL RISK ASSESSMENT
ID INSIDE DIAMETER OR DIM
ILSM INTERIM LIFE SAFETY MEASURES
INCL INCLUDE(D,ING)
INST INSTALL
INSUL INSULATION
INT INTERIOR
J
JT JOINT
K
KV KILOVOLT
L
LAM LAMINATE(D)
LAV LAVATORY
LCM LEAD CONTAINING MATERIAL(S)
LD LEAD
LT LIGHT
M
MAT MATERIAL(S)
MAX MAXIMUM
MDF MEDIUM-DENSITY FIBREBOARD
MECH MECHANIC(AL)
MEP MECHANICAL, ELECTRICAL, PLUMBING
MFR MANUFACTURE(R)
MIN MINIMUM
MISC MISCELLANEOUS
MOD MODIFIED
MTL METAL
N
N NORTH
N(/)A NOT APPLICABLE
NEG NEGATIVE
NO. NUMBER
NOM NOMINAL
NTS NOT TO SCALE
O
O.C. ON CENTER(S)
OPN(G) OPEN(ING)
OPP OPPOSITE
OPT OPTION(AL)
OVHD OVERHEAD
P
P PAINT
PCONC PRECAST CONCRETE
PCRA PRE-CONSTRUCTION RISK ASSESSMENT
PL PLATE
PLAM PLASTIC LAMINATE
PLY(WD) PLYWOOD
PNL PANEL
PR PAIR
PRFB PREFABRICATED
PS PLASTIC
PT PORCELAIN TILE
PTN(S) PARTITION(S)
PVMT PAVEMENT
Q
QTY QUANTITY
R
RAD RADIUS
RCP(S) REFLECTED CEILING PLAN(S)
REF REFERENCE
REINF REINFORCE(D,ING)
REP REPRESENTATIVE
REQ(S,(')D) REQUIRE(D,S,MENT(S))
RESIL RESILIENT
REV REVERSE
RF ROOF
RM ROOM
RMV REMOVE
RO ROUGH OPENING
S
S SOUTH
SCHED SCHEDULE
SCI(D) SPINAL CORD INJURY (& DISABILITY)
SD SCHEMATIC DESIGN
SDSF SOLID SURFACE
SECT SECTION
SF SQUARE FEET
SFRM SPRAY APPLIED FIRE-RESISTIVE MATERIAL
SHG SHINGLES
SHLD(G) SHEILD(ING)
SHT(G) SHEET (SHEATHING)
SIM SIMILAR
SM SEAM
SOW SCOPE OF WORK
SPEC SPECIFICATION
SQ SQUARE
SS STAINLESS STEEL
ST STAIN
STDG STANDING
STF STAFF
STL STEEL
STOR STORAGE
STRUCT STRUCTURAL
SURG SURGERY, SURGICAL
SUSP SUSPENDED
SV SHEET VINYL
SYS SYSTEM
T
TBD TO BE DETERMINED
TBL TABLE
TEMP TEMPORARY
T&G TONGUE AND GROOVE
THK THICK(NESS)
THRESH THRESHOLD
TOC TABLE OF CONTENTS
TOS TOP OF SLAB
TPH TOILET PAPER HOLDER
TRANS TRANSITION
TS TUBE STEEL
TYP TYPICAL
U
UNO UNLESS NOTED OTHERWISE
UON UNLESS OTHERWISE NOTED
V
VA VETERANS AFFAIRS
VAR VARIES
VB VAPOR BARRIER
VC VA FURNISHED, CONTRACTOR INSTALLED
VERT VERTICAL
VIF VERIFY IN FIELD
VV VA FURNISHED, VA INSTALLED
W
W WEST
W/ WITH
WD WOOD
WDW WINDOW
WGHT WEIGHT
W/O WITHOUT
WP WATERPROOF(ING)
WR WATER RESISTANT
WRK WORK
X
XRY X-RAY
ENGINEERING DISCIPLINE: 16
SALEM VA MEDICAL CENTER
1970 ROANOKE BLVD, SALEM, VA 24153
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building No.
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
o n e e ig h th in c h o n e fo o t
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Office of Construction and Facilities Management
Department of Veteran Affairs
STAMP:
BID SET
REPLACE BUILDING 16 HVAC 658-24-106
Floor No.
Dwg.
DAV ENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
619-770-8552
WWW.DAVENERGY.COM
02/28/2025
ARCH SYMBOLS, ABBREVIATIONS,
& GENERAL NOTES
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
MK AJ02/28/2025
A-001
- +-- TEMPORARY ICRA AIR PRESSURE
ADHESIVE WALK-OFF MATS
CONTRACTOR PATH OF TRAVEL
1 2 3 4 5 6 7
A
B
C
D
170 SF
OFFICE
85 SF
WOMEN
142 SF
OFFICE
183 SF
EEO / OFFICE
183 SF
PGM ASST OFFICE
192 SF
OFFICE
172 SF
CLINICAL CO -
ORDR OFFICE
257 SF
OFFICE
302 SF
OFFICE
239 SF
OFFICE
259 SF
EDUCATION
OFFICE
3A
275 SF
OFFICE
196 SF
OFFICE
275 SF
CONFERENCE RM
249 SF
OFFICE
261 SF
OFFICE
502 SF
CORRIDOR
25 SF
HOUSE KEEPING
74 SF
10A
62 SF
MEN
10B
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
BLDG 16
ENGINEERING DISCIPLINE: 16
SALEM VA MEDICAL CENTER
1970 ROANOKE BLVD, SALEM, VA 24153
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building No.
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
o n e e ig h th in c h o n e fo o t
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Office of Construction and Facilities Management
Department of Veteran Affairs
STAMP:
BID SET
REPLACE BUILDING 16 HVAC 658-24-106
Floor No.
Dwg.
DAV ENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
619-770-8552
WWW.DAVENERGY.COM
02/28/2025
ICRA
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
MK AJ02/28/2025
AS101
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1/4" = 1'-0"
ICRA PLAN - FIRST FLOOR
1. ICRA CLASS II REQUIREMENTS MUST BE MET
THROUGHOUT THE ENTIRE DURATION OF CONSTRUCTION.
2. COMPLY WITH ALL REQUIREMENTS IN SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
3. CONSTRUCTION ZONE ENTRANCES AND EXITS SHALL BE
LOCKED AT ALL TIMES UNLESS IN USE BY THE
CONTRACTOR. WHEN IN USE, ACCESS WILL BE
CONTROLLED AND MONITORED BY THE CONTRACTOR.
4. ADHESIVE WALK-OFF MATS TO BE USED AT ALL
CONSTRUCTION ENTRANCES AND EXITS, INCLUDING ANTE
ROOMS.
5. ENTIRE BUILDING UNOCCUPIED DURING CONSTRUCTION,
NO ICRA CONCERNS.
1 WORK AREA ACCESS POINT WITH STICKY WALK OFF MATS.
EMERGENCY EGRESS ROUTE
FIRE EXTINGUISHER CABINET
EXISTING FIRE SPRINKLERS
FEC
1 2 3 4 5 6 7
A
B
C
D
FEC
P R
O V
ID
E
D
M A
X A
L L
O W
A B
L E
P R
O V
ID
E
D
M A
X A
L L
O W
A B
L E
TO POINT OF TWO EGRESS OPTIONS
PROVIDED 61'-6"
EXISTING FEC
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
BLDG 16
ENGINEERING DISCIPLINE: 16
SALEM VA MEDICAL CENTER
1970 ROANOKE BLVD, SALEM, VA 24153
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building No.
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
o n e e ig h th in c h o n e fo o t
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Office of Construction and Facilities Management
Department of Veteran Affairs
STAMP:
BID SET
REPLACE BUILDING 16 HVAC 658-24-106
Floor No.
Dwg.
DAV ENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
619-770-8552
WWW.DAVENERGY.COM
02/28/2025
FIRE LIFE SAFETY
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
MK AJ02/28/2025
AS111
1/4" = 1'-0"
FIRE LIFE SAFETY PLAN - FIRST FLOOR
LEGEND
CODE ANALYSIS
KEY PLAN
1. PLEASE NOTE, AS AN AGENCY OF THE FEDERAL
GOVERNMENT, THE VA IS NOT SUBJECT TO LOCAL
IMPOSITIONS OF CODE ENFORCEMENT PROCEDURES
(DRAWING REVIEWS, BUILDING PERMITS, INSPECTIONS,
FEES, ETC). THE VA SHALL FUNCTION AS THE AUTHORITY
HAVING JURISDICTION (AHJ).
2. THE BELOW CODES HAVE BEEN USED FOR ANALYSIS:
A. NATIONAL FIRE PROTECTION AGENCY (NFPA) 101 LIFE
SAFETY CODE, 2024. NFPA 101 TAKES PRECEDENCE
OVER IBC.
B. INTERNATIONAL BUILDING CODE (IBC), 2021.
3. EXISTING BUILDING CONSTRUCTION TYPE SHALL NOT BE
ALTERED AS PART OF THIS PROJECT.
A. ASSUMED NFPA 220 FIRE RESISTIVE RATING: TYPE III
(332). (NFPA 220, 2024).
B. ASSUMED IBC FIRE RESISTIVE RATING: TYPE III. (IBC,
2021).
4. EXISTING BUILDING OCCUPANCY TYPE SHALL NOT BE
ALTERED AS PART OF THIS PROJECT.
A. ASSUMED NFPA 101 OCCUPANCY TYPE: BUSINESS
AND STORAGE USE. (NFPA 101, 2024 - CHAPTER 19).
5. OCCUPANT LOADS IN AREA OF WORK ARE EQUAL OR LESS
THAN EXISTING, AND THEREFORE, EXISTING EXIT WIDTHS
ARE NOT REQUIRED TO BE ALTERED AS PART OF THIS
PROJECT. (NFPA 101, 2024 - TABLE 7.3.1.2).
A. 8362 SF BUSINESS (GENERAL) AT 150 SF / OCCUPANT
= 56 OCCUPANTS
B. TOTAL NET OCCUPANT LOAD = 56 OCCUPANTS
6. MAX COMMON PATH OF TRAVEL BEFORE TWO PATHS ARE
PROVIDED SHALL NOT EXCEED 100' (EXISTING BUSINESS,
FULLY SPRINKLERED). (NFPA 101, 2021 - 39
7. MAX TRAVEL DISTANCE TO EXITS SHALL NOT EXCEED
300' - 0" (EXISTING BUSINESS, FULLY SPRINKLERED). (NFPA
101, 2021 - 39.2.6.2.2 & 3).
PROJECT
NORTH
TRUE NORTH
(DASHED)
EXISTING DOOR TO REMAIN
TO DEMOLISH
EXISTING TO REMAIN
1 2 3 4 5 6 7
A
B
C
D
OFFICE
WOMEN
MEN
10B
OFFICE
EEO / OFFICE
PGM ASST OFFICE
CORRIDOR
OFFICE
CLINICAL CO -
ORDR OFFICE
OFFICE
OFFICE
OFFICE
EDUCATION
OFFICE
3A
OFFICE
OFFICE
CONFERENCE RM
OFFICE
OFFICE
10A
10C
FEC
EXISTING FEC
1. ENSURE CONSTRUCTION ZONE IS FULLY ENCLOSED,
PRIOR TO BEGINNING ANY WORK. NO WORK SHALL BE
DONE WITHOUT PROPERLY MEETING ALL ICRA
REQUIREMENTS, SEE ICRA PLAN(S) FOR SPECIFIC ICRA
CLASS LOCATIONS & REQUIREMENTS.
2. REMOVE WALL MOUNTED ACCESSORIES REQUIRED TO
COMPLETE A CONSTRUCTION TASK. VERIFY WITH COR
BEFORE DISPOSAL.
3. COORDINATE WITH VA COR PRIOR TO THE DEMOLITION OF
ANY EXISTING EQUIPMENT.
4. CONTRACTOR TO PATCH AND REPAIR ANY DAMAGE TO
THE FLOOR AND WALLS TO MATCH EXISTING FINISHES.
5. EXISTING WINDOWS AND BLINDS IN OFFICES 18, 19, AND 20
ARE EXISTING TO REMAIN. IF NEED TO REMOVE,
CONTRACTOR TO REMOVE, STORE AND REINSTALL.
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
ENGINEERING DISCIPLINE: 16
SALEM VA MEDICAL CENTER
1970 ROANOKE BLVD, SALEM, VA 24153
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building No.
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
o n e e ig h th in c h o n e fo o t
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Office of Construction and Facilities Management
Department of Veteran Affairs
STAMP:
BID SET
REPLACE BUILDING 16 HVAC 658-24-106
Floor No.
Dwg.
DAV ENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
619-770-8552
WWW.DAVENERGY.COM
02/28/2025
FIRST FLOOR DEMO PLAN
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
MK AJ02/28/2025
AD101
1/4" = 1'-0"
FIRST FLOOR - DEMO PLAN
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1 DEMO EXISTING PTAC
2 EXISTING AHU TO BE DEMOLISHED
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1 2 3 4 5 6 7
A
B
C
D
OFFICE
WOMEN
10C
10A
MEN
10B
OFFICE
HOUSE KEEPING
EEO / OFFICE
PGM ASST OFFICE
CORRIDOR
OFFICE
CLINICAL CO -
ORDR OFFICE
OFFICE
OFFICE
OFFICE
EDUCATION
OFFICE
3A
OFFICE
OFFICE
CONFERENCE RM
OFFICE
OFFICE
/1
6 3/8"
TO DEMOLISH
TO DEMOLISH
2x2 ACOUSTICAL CEILING TILE
GYPSUM BOARD ON METAL STUDS
EXISTING FIRE EXTINGUISHERS
ENGINEERING DISCIPLINE: 16
SALEM VA MEDICAL CENTER
1970 ROANOKE BLVD, SALEM, VA 24153
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building No.
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
o n e e ig h th in c h o n e fo o t
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Office of Construction and Facilities Management
Department of Veteran Affairs
STAMP:
BID SET
REPLACE BUILDING 16 HVAC 658-24-106
Floor No.
Dwg.
DAV ENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
619-770-8552
WWW.DAVENERGY.COM
02/28/2025
DEMO CEILING PLAN
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
MK AJ02/28/2025
AD102
1/4" = 1'-0"
FIRST FLOOR - DEMO CEILING PLAN
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
1. REMOVE AND STORE ANY CEILING TILES AND/OR ACT
SUSPENSION GRID SYSTEM COMPONENTS WHERE
REQUIRED TO COMPLETE ABOVE CEILING MECHANICAL
AND ELECTRICAL WORK.
2. REMOVE ANY CEILING OR WALL MOUNTED EQUIPMENT, AS
REQUIRED TO COMPLETE OTHER WORK. STORE UNTIL
READY FOR REINSTALLATION.
3. TEMPORARILY PROVIDE FIRE PROTECTION WHERE
CEILING IS DOWN BY ADJUSTING THE EXISTING FIRE
SPRINKLERS HEADS AS REQUIRED TO MEET VA AND NFPA
REQUIREMENTS.
INVERTED SPRINKLER HEADS PROCEDURE:
1. INITIAL INSTALLATION & PROTECTION:
A. SPRINKLER HEADS SHALL BE INSTALLED IN AN
UPRIGHT POSITION DURING ROUGH-IN TO PREVENT
ACCIDENTAL DAMAGE FROM CONSTRUCTION
ACTIVITIES.
B. FIRE PROTECTION PIPING SHALL BE PROPERLY
SUPPORTED AND SECURED TO AVOID
DISPLACEMENT.
C. TEMPORARY PROTECTIVE COVERS SHALL BE USED
ON SPRINKLER HEADS TO PREVENT DUST AND
DEBRIS ACCUMULATION, IN ACCORDANCE WITH
INFECTION CONTROL POLICIES.
2. INVERSION FOR CONSTRUCTION PHASE:
A. PRIOR TO CEILING INSTALLATION OR FINISHING
WORK, SPRINKLER HEADS SHALL BE INVERTED
(TURNED UPWARD) WITHIN ALLOWABLE PIPE
FITTING CONFIGURATIONS.
B. TEMPORARY PROTECTIVE MEASURES, SUCH AS
DUST-TIGHT COVERS, SHALL BE INSTALLED IN
COMPLIANCE INFECTION CONTROL PROTOCOLS
(ICRA – INFECTION CONTROL RISK ASSESSMENT).
C. COORDINATION WITH INFECTION CONTROL AND
FACILITY MANAGEMENT TEAMS IS REQUIRED TO
ENSURE COMPLIANCE WITH JOINT COMMISSION
STANDARDS.
3. FINAL POSITIONING, TESTING & CERTIFICATION:
A. AFTER THE CEILING OR FINAL FINISHES ARE
INSTALLED, SPRINKLER HEADS SHALL BE
CORRECTLY ORIENTED (TYPICALLY PENDANT OR
SIDEWALL) PER THE APPROVED FIRE PROTECTION
DESIGN.
B. ALL PROTECTIVE COVERINGS SHALL BE REMOVED
BEFORE SYSTEM TESTING.
C. SYSTEM FLUSHING, HYDROSTATIC TESTING, AND
FINAL ACCEPTANCE TESTING SHALL BE PERFORMED
PER NFPA 13, AND LOCAL FIRE CODES.
D. A FINAL INSPECTION SHALL BE COORDINATED WITH
THE AUTHORITY HAVING JURISDICTION (AHJ) AND
FACILITY REPRESENTATIVES BEFORE OCCUPANCY.
PROJECT
NORTH
TRUE NORTH
(DASHED)
1 DEMO EXISTING CEILING, SALVAGE EXISTING LIGHTS
FOR REINSTALLATION.
2 CUT EXISTING GYP CEILING FOR NEW LADDER ROOF
ACCESS.
1 2 3 4 5 6 7
A
B
C
D
OFFICE
WOMEN
10C 10A
MEN
10B
OFFICE
EEO /
OFFICE
PGM
ASST
OFFICE
OFFICE
CLINICAL CO -
ORDR OFFICE
OFFICE
OFFICE
OFFICE
EDUCATION
OFFICE
3A
OFFICE
OFFICE
CONFERENCE RM
OFFICE
OFFICE
CORRIDOR
HOUSE
KEEPING
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
EXISTING DOOR TO REMAIN
EXISTING TO REMAIN
NEW
ENGINEERING DISCIPLINE: 16
SALEM VA MEDICAL CENTER
1970 ROANOKE BLVD, SALEM, VA 24153
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building No.
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
o n e e ig h th in c h o n e fo o t
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Office of Construction and Facilities Management
Department of Veteran Affairs
STAMP:
BID SET
REPLACE BUILDING 16 HVAC 658-24-106
Floor No.
Dwg.
DAV ENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
619-770-8552
WWW.DAVENERGY.COM
02/28/2025
FIRST FLOOR PLAN
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
MK AJ02/28/2025
AE101
PROJECT
NORTH
TRUE NORTH
(DASHED)
1/4" = 1'-0"
FLOOR PLAN
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
1 INFILL WALL, PATCH AND REPAIR TO MATCH EXISTING
WHERE PTAC WAS DEMOLISHED
2 INSTALL NEW LADDER FOR ROOF ACCESS
1. DIMENSIONS SHOWN ARE FROM GRID LINES TO FACE OF
STUD, CENTERLINE OF STRUCTURAL COLUMNS,
CENTERLINE OF OPENINGS, UNO.
2. ANY DOORS NOT DIMENSIONED SHALL BE INSTALLED 6"
FROM THE INTERSECTING WALL OR CENTERED ON THE
WALL, UNO.
3. ALL DIMENSIONS NOTED AS CLEAR SHALL MAINTAIN THE
FULL SPACE INDICATED WITHOUT ENCROACHMENTS.
4. ENSURE THAT ALL REQUIRED BACKING IS INSTALLED IN
WALLS PRIOR TO INSTALLING GYPSUM BOARD.
5. CONTRACTOR TO PATCH AND REPAIR ANY DAMAGE TO
THE FLOOR, WALLS, AND CEILING TO MATCH EXISTING
FINISHES.
6. EXISTING WINDOWS AND BLINDS IN OFFICES 18, 19, AND 20
ARE EXISTING TO REMAIN. IF NEED TO REMOVE,
CONTRACTOR TO REMOVE, STORE AND REINSTALL.
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1. DIMENSIONS SHOWN ARE FROM GRID LINES TO FACE OF
STUD, CENTERLINE OF STRUCTURAL COLUMNS,
CENTERLINE OF OPENINGS, UNO.
2. ANY DOORS NOT DIMENSIONED SHALL BE INSTALLED 6"
FROM THE INTERSECTING WALL OR CENTERED ON THE
WALL, UNO.
3. ALL DIMENSIONS NOTED AS CLEAR SHALL MAINTAIN THE
FULL SPACE INDICATED WITHOUT ENCROACHMENTS.
4. ENSURE THAT ALL REQUIRED BACKING IS INSTALLED IN
WALLS PRIOR TO INSTALLING GYPSUM BOARD.
5. CONTRACTOR TO PATCH AND REPAIR ANY DAMAGE TO
THE FLOOR, WALLS, AND CEILING TO MATCH EXISTING
FINISHES.
6. EXISTING WINDOWS AND BLINDS IN OFFICES 18, 19, AND 20
ARE EXISTING TO REMAIN. IF NEED TO REMOVE,
CONTRACTOR TO REMOVE, STORE AND REINSTALL.
7. IN LIUE OF DESTRUCTIVE SITE INVESTIGATION, AE HAS
MADE ASSUMPTIONS SURROUNDING THE EXISTING
ROOFING SYSTEM AT TIME OF CONSTRUCTION BASED ON
VA PROVIDED DOCUMENTATION. COORDINATE WITH VA
COR AND ALERT THEM OF ANY DISCREPANCIES BETWEEN
THE EXISTING CONDITIONS AND THE CONTRACT
DOCUMENTS. THE DESIGN INTENT IS TO MATCH AND
INTEGRATE INTO THE EXISTING CONDITIONS AT THE TIME
OF CONSTRUCTION.
1 2 3 4 5 6 7
A
B
C
D
RTU-11 EXISTING ROOF VENT
EXISTING ROOF VENT
NEW ROOF HATCH AND LADDER WITH
SAFETY RAILING AND LADDER ASSIST POST.
13' - 1 3/4"
22"X42" ROOF OPENING, PER MECH8"X42" ROOF OPENING, PER MECH
NEW WALKWAY PAD
ENGINEERING DISCIPLINE: 16
SALEM VA MEDICAL CENTER
1970 ROANOKE BLVD, SALEM, VA 24153
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building No.
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
o n e e ig h th in c h o n e fo o t
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Office of Construction and Facilities Management
Department of Veteran Affairs
STAMP:
BID SET
REPLACE BUILDING 16 HVAC 658-24-106
Floor No.
Dwg.
DAV ENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
619-770-8552
WWW.DAVENERGY.COM
02/28/2025
ROOF PLAN
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
MK AJ02/28/2025
AE102
PROJECT
NORTH
TRUE NORTH
(DASHED)
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
1 NEW ROOFTOP AIR HANDLING UNIT
1/4" = 1'-0"
ROOF PLAN
2x2 ACOUSTICAL CEILING TILE
GYPSUM BOARD ON METAL STUDS
DIFFUSER PER MECHANICAL
(SIZE & PROPORTION MAY VARY)
LIGHT FIXTURE PER ELECTRICAL
(SIZE & PROPORTION MAY VARY)
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1. REMOVE AND STORE ANY CEILING TILES AND/OR ACT
SUSPENSION GRID SYSTEM COMPONENTS WHERE
REQUIRED TO COMPLETE ABOVE CEILING MECHANICAL
AND ELECTRICAL WORK. REINSTALL AFTER DISCIPLINE
WORK IS COMPLETE. REPLACE ANY DAMAGED TILES OR
SUSPENSION GRID SYSTEM COMPONENTS TO MATCH
EXISTING.
2. REMOVE ANY CEILING OR WALL MOUNTED EQUIPMENT, AS
REQUIRED TO COMPLETE OTHER WORK. STORE UNTIL
READY FOR REINSTALLATION.
1 2 3 4 5 6 7
A
B
C
D
OFFICE
10C
WOMEN
10A
MEN
10B
OFFICE
HOUSE KEEPING
EEO / OFFICE
PGM ASST OFFICE
CORRIDOR
OFFICE
CLINICAL CO -
ORDR OFFICE
OFFICE
OFFICE
OFFICE
EDUCATION
OFFICE
3A
OFFICE
OFFICE
CONFERENCE RM
OFFICE
OFFICE
AE301
AE301
ACT 2x2
8' - 1 1/2" AFF
ACT 2x2
8' - 1 1/2" AFF
ACT 2x2
8' - 1 1/2" AFF
36"
A-501
Sim
GYP
9' - 7 1/2" AFF
GYP
9' - 7 1/2" AFF
GYP
9' - 7 1/2" AFF
GYP
9' - 7 1/2" AFF
GYP
9' - 7 1/2" AFF
GYP
9' - 7 1/2" AFF
GYP
9' - 7 1/2" AFF
GYP
9' - 7 1/2" AFF
ENGINEERING DISCIPLINE: 16
SALEM VA MEDICAL CENTER
1970 ROANOKE BLVD, SALEM, VA 24153
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building No.
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
o n e e ig h th in c h o n e fo o t
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Office of Construction and Facilities Management
Department of Veteran Affairs
STAMP:
BID SET
REPLACE BUILDING 16 HVAC 658-24-106
Floor No.
Dwg.
DAV ENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
619-770-8552
WWW.DAVENERGY.COM
02/28/2025
FIRST FLOOR CEILING PLAN
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
MK AJ02/28/2025
AC101
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1 INSTALL NEW ACT CEILING.
2 PATCH EXISTING GYP CEILING AS NEEDED WHERE
NEW OPENING OCCURS.
1/4" = 1'-0"
CEILING PLAN
3. TEMPORARILY PROVIDE FIRE PROTECTION WHERE
CEILING IS DOWN BY ADJUSTING THE EXISTING FIRE
SPRINKLERS HEADS AS REQUIRED TO MEET VA AND NFPA
REQUIREMENTS.
LEVEL 1
0' - 0"
LEVEL 1
0' - 0"
ROOF PLAN
12' - 7"
LEVEL 4
14' - 7 1/2"
10A
AE301
LEVEL 1
0' - 0"
ROOF PLAN
12' - 7"
LEVEL 4
14' - 7 1/2"
AE301
10A
SECURITY DOOR
ENGINEERING DISCIPLINE: 16
SALEM VA MEDICAL CENTER
1970 ROANOKE BLVD, SALEM, VA 24153
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building No.
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
o n e e ig h th in c h o n e fo o t
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Office of Construction and Facilities Management
Department of Veteran Affairs
STAMP:
BID SET
REPLACE BUILDING 16 HVAC 658-24-106
Floor No.
Dwg.
DAV ENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
619-770-8552
WWW.DAVENERGY.COM
02/28/2025
BUILDING SECTIONS
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
MK AJ02/28/2025
AE301
GENERAL NOTES
1. GENERAL NOTES HERE.
1/2" = 1'-0"
ROOM 10A - LADDER AND ROOF HATCH - EAST-WEST
1/2" = 1'-0"
ROOM 10A - LADDER AND ROOF HATCH - NORTH-SOUTH
FASTEN AT BOTH
ENDS WITH MIN 4
TAPPING SCREWS
GENERAL NOTES:
1. CONTRACTOR SHALL COORDINATE LOCATIONS OF
HORIZONTAL FASTENERS
2. ALL WALL MOUNTED EQUIPMENT SHALL HAVE METAL
BLOCKING IN WALL BEHIND. ENSURE ALL REQUIRED
BACKING IS INSTALLED PRIOR TO INSTALLING GYP.
PLAN VIEW
ISOMETRIC VIEW
WALL FINISH
VERTICAL WALL STUDS
@ 16" OR 24" OC
CUT HORIZONTAL
FASTENER FROM STUD
GENERAL NOTES:
1. WOOD NAILERS MUST BE INSTALLED WITH SUITABLE
FASTENERS TO MEET APPLICABLE BUILDING CODES.
2. GRANULES MUST BE EMBEDDED WHEN THERMALLY
FUSING GRANULE SUFACED CAP SHEET.
3. FLASHING LAPS MUST BE OFFSET FROM FIELD LAPS
BY A MINIMUM OF 12".
4. NOT TO BE SET UNTIL THE ROOF MEMBRANE AND
FLASHING HAVE BEEN INSTALLED.
SUBSTRATE
FOUR PLY BUILT-UP ROOF
MODIFIED BITUMEN GRANULE SURFACED CAP SHEET
INTERPLY REQUIRED FOR 15 - 20 YEAR SYSTEMS
FLASHING FROM ROOF HATCH
FASTENER 12" O.C. MAX
WITH SEALANT
ROOF HATCH METAL CURB
INSULATION
COVER BOARD (AS REQUIRED)
TRANSITION CLIP
BRACING AS REQUIRED
GRID SYSTEM
EXISTING WALL
EXISTING WINDOW
ACOUSTICAL PANEL
CHANNEL
12"
A-501
4 Sim
APPLY AT JOINT BRAND PAPER JOINT TAPE
APPLY ACOUSTICAL SEALANT AT
PERIMETER JOINTS, TYPICAL.
MOLDING ANGLE, SECURE TO
WALL WITH APPROPRIATE
FASTENER, TYPICAL.
SCREW GYPSUM BOARD TO ANGLE
MOLDING
J-BEAD
HANGER WIRE
SUSPENSION MAIN TEE
SUSPENSION CROSS TEE
5/8" GWB
EXISTING CONCRETE DECK
MODIFIED BITUMEN GRANULE SURFACED CAP SHEET
INTERPLY REQUIRED FOR 15 - 20 YEAR SYSTEMS
INSULATION
COVER BOARD (AS REQUIRED)
FOUR PLY BUILT-UP ROOF
3/4"
MTL COUNTER-FLASHING 3" MIN FACE
1X4 WOOD NAILER, BY OTHERS
FASTEN
GASKETED FASTENER
3" MIN 3" MIN
INSULATION
MTL CURB, BY OTHERS
GENERAL NOTES:
1. WOOD NAILERS MUST BE INSTALLED WITH SUITABLE
FASTENERS TO MEET APPLICABLE BUILDING CODES.
2. GRANULES MUST BE EMBEDDED WHEN THERMALLY
FUSING GRANULE SUFACED CAP SHEET.
3. FLASHING LAPS MUST BE OFFSET FROM FIELD LAPS
BY A MINIMUM OF 12".
4. NOT TO BE SET UNTIL THE ROOF MEMBRANE AND
FLASHING HAVE BEEN INSTALLED.
ENGINEERING DISCIPLINE: 16
SALEM VA MEDICAL CENTER
1970 ROANOKE BLVD, SALEM, VA 24153
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building No.
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
o n e e ig h th in c h o n e fo o t
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Office of Construction and Facilities Management
Department of Veteran Affairs
STAMP:
BID SET
REPLACE BUILDING 16 HVAC 658-24-106
Floor No.
Dwg.
DAV ENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
619-770-8552
WWW.DAVENERGY.COM
02/28/2025
DETAILS
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
MK AJ02/28/2025
A-501
NOT TO SCALE
TYPICAL BLOCKING DETAIL
6" = 1'-0"
FLASHING @ ROOF HATCH
1 1/2" = 1'-0"
TYP SOFFIT WINDOW DETAIL
6" = 1'-0"
TYP SOFFIT CONNECTION TO WALL
3" = 1'-0"
FLASHING @ MTL CURB
GENERAL NOTES
1. IN LIUE OF DESTRUCTIVE SITE INVESTIGATION, AE HAS
MADE ASSUMPTIONS SURROUNDING THE EXISTING
ROOFING SYSTEM AT TIME OF CONSTRUCTION BASED ON
VA PROVIDED DOCUMENTATION. COORDINATE WITH VA
COR AND ALERT THEM OF ANY DISCREPANCIES BETWEEN
THE EXISTING CONDITIONS AND THE CONTRACT
DOCUMENTS. THE DESIGN INTENT IS TO MATCH AND
INTEGRATE INTO THE EXISTING CONDITIONS AT THE TIME
OF CONSTRUCTION.
FP = 0.4SDSIPWP Hf Rμ
DESIGN BASIS
GRID ID
S#.#
GRID ID
SECTION NO.
SHEET NO. WHERE
SECTION IS SHOWN
S0.1
ELEVATION NO.
SHEET NO. WHERE
ELEVATION IS SHOWN
S#.#
DETAIL NO.
SHEET NO. WHERE
DETAIL IS SHOWN
GRID LINES - CENTER
GRID LINES - FACE
DETAIL INDICATOR
ELEVATION INDICATOR
SECTION INDICATOR
B. GRAVITY LOADS
1. AIR HANDLING UNIT
2. ROOF DEAD LOAD
3. ROOF LIVE LOAD
(REDUCIBLE)
C. SNOW LOAD
GROUND SNOW LOAD, pg
WINTER WIND PARAMETER
D. ICE LOAD
ICE THICKNESS: 1.04 in.
CONCURRENT TEMPERATURE:15°F
E. LATERAL LOADS
DEAD LOAD
2,473 LBS
UNIFORM LOAD
49 psf 0.35
1. WIND LOAD (ROOF TOP UNIT ONLY)
METHOD OF ANALYSIS DIRECTIONAL PROCEDURE
BASIC WIND SPEED 108 mph
EXPOSURE CATEGORY C
RISK CATEGORY II
FORCE COEFFICIENT GCr = 1.90 (AHU: HORIZANTAL)
GCr = 1.50 (AHU: UPLIFT)
SYMBOLS
2. EARTHQUAKE LOADS - NON-STRUCTURAL COMPONENTS
SEISMIC DESIGN FORCE
FACTOR FOR FORCE AMPLIFICATION Hf = 3.5 STRUCTURE DUCTILITY REDUCTION FACTOR Rμ = 1.3
COMPONENT RESONANCE DUCTILITY FACTOR CAR = 1.4
COMPONENT STRENGTH FACTOR Rpo = 2.0
RISK CATEGORY SEISMIC II
IMPORTANCE FACTOR IP=1.0
SITE CLASS D
SEISMIC DESIGN CATEGORY B
SITE COORDINATES
LATITUDE 32.274284
LONGITUDE -80.018752
SEISMIC PARAMETERS
SS = 0.23g S1 = 0.07g SDS = 0.18g SD1 = 0.098g
WP = EQUIPMENT WEIGHT
SHEET INDEX
SHEET NO. SHEET TITLE
S-001 STRUCTURAL COVER SHEET & STRUCTURAL NOTES
S-002 STRUCTURAL NOTES, VERIFICATION & INSPECTION SCHEDULES
S-101 STRUCTURAL ROOF PLAN
S-501 TYPICAL DETAILS
SUMMARY OF WORK
NEW AIR HANDLING UNIT (AHU) INSTALLATION AND ROOF PENETRATIONS. THE PROJECT IS LOCATED AT
1970 ROANOKE BLVD. SALEM, VA, 24153.
ABBREVIATIONS
STRUCTURAL NOTES
A. APPLICABLE CODES:
# NUMBER
& AND
= EQUAL, EQUALS
@ AT
A/C AIR CONDITIONING
AB ANCHOR BOLT
ABV ABOVE
ACI AMERICAN CONCRETE INSTITUTE
ADDL ADDITIONAL
ADJ ADJACENT
AFF ABOVE FINISHED FLOOR
AHU AIR HANDLING UNIT
AHJ AUTHORITY HAVING JURISDICTION
AISC AMERICAN INSTITUTE OF STEEL CONSTRUCTION
ALT ALTERNATE
APA AMERICAN PLYWOOD ASSOCIATION
APPROX APPROXIMATELY
ARCH ARCHITECTURAL
ASTM AMERICAN SOCIETY FOR TESTING AND MATERIALS
AT/FP ANTI-TERRORISM/ FORCE PROTECTION
AWS AMERICAN WELDING SOCIETY
BTWN BETWEEN
BLW BELOW
BM BEAM
BLKG BLOCKING
BN BOUNDARY NAIL
BOF BOTTOM OF FOOTING
BOT BOTTOM
BRG BEARING
BSFRM BASE FRAME
C CHANNEL
CE CARBON EQUIVALENT
CENT CENTERED
CFMF COLD-FORMED METAL FRAMING
CFS COLD-FORMED STEEL
CIP CAST IN PLACE
CJ CONTROL JOINT/CEILING JOIST
CJP COMPLETE JOINT PENETRATION
CL CENTERLINE
CLR CLEAR
CMU CONCRETE MASONRY UNIT
COL COLUMN
CONC CONCRETE
COND CONDITION
CONN CONNECT, CONNECTION
CONST CONSTRUCTION
CONT CONTINUOUS
CONTR CONTRACTOR
COORD COORDINATE
COR CORNER
CWB CAPILLARY WATERBARRIER
D DEEP, DEPTH
DEG DEGREE
DEM DEMOLISH, DEMOLITION
DEP DEPRESSED
DET DETAIL
DIA DIAMETER
DIAG DIAGONAL
DL DEADLOAD
DO DITTO
DT DRAG TRUSS
DWG(S) DRAWINGS
DWL DOWEL
EA EACH
EF EACH FACE
EFF EFFECTIVE
ELEC ELECTRICAL
ELEV ELEVATION
EMBED EMBEDDED, EMBEDMENT
EN EDGE NAIL
EQ EQUAL
EQN EQUATION
EQUIP EQUIPMENT
ES EACH SIDE
EW EACH WAY
EXIST EXISTING
EXT EXTERNAL, EXTERIOR
FF FAR FACE/FINISH FLOOR
FFE FINISH FLOOR ELEVATION
FG FINISH GRADE
FJ FLOOR JOIST
FRM FRAME
FRMG FRAMING
FN FIELD NAIL
FND FOUNDATION
FO FACE OF
FOC FACE OF CONCRETE
FOM FACE OF MASONRY
FOS FACE OF STUD
FS FAR SIDE
FT, ' FOOT
FTG FOOTING
Fy YIELD STRESS
GA GAUGE
GLB GLUED LAMINATED BEAM
GT GIRDER TRUSS
GUSS GUSSET
GYP BD GYPSUM BOARD
HD HOLD DOWN
HDR HEADER
HGR HANGER
HK HOOK
HORIZ HORIZONTAL
HP HIGH POINT
HSS HOLLOW STRUCTURAL SECTION
HT HEIGHT
HVAC HEATNG/ VENTILATING/ AIR CONDITIONING
I MOMENT OF INERTIA
IBC INTERNATIONAL BUILDING CODE
ICF INSULATED CONCRETE FORM
ID INSIDE DIAMETER
IN, " INCH
INCL INCLUDE
INFO INFORMATION
INS INSULATED, INSULATION
JST JOIST
K, KIPS THOUSAND POUNDS
L LENGTH, ANGLE
LB POUND
LG LONG
LL LIVE LOAD
LLH LONG LEG HORIZONTAL
LLV LONG LEG VERTICAL
LOC LOCATE, LOCATION
LONG LONGITUDINAL
LP LOW POINT
LW LIGHT WEIGHT
MAS MASONRY
MB MACHINE BOLT
MBR MEMBER
MCJ MASONRY CONTROL JOINT
MECH MECHANICAL
MED MEDIUM
MEZZ MEZZANINE
MF MOMENT FRAME
MFR MANUFACTURER
MFG MANUFACTURING
MIN MINIMUM
MO MASONRY OPENING
MOD MODIFY, MODIFIED
MFR MANUFACTURER
NF NEAR FACE
NOM NOMINAL
NS NEAR SIDE
OC ON CENTER
OD OUTSIDE DIAMETER
OH OPPOSITE HAND, OVERHEAD
OP OPERATING
OPNG OPENING
OWSJ OPEN WEB STEEL JOIST
P/C PIN CONNECTED
PAR PARALLEL
PCC PRECAST CONCRETE
PCF POUNDS PER CUBIC FOOT
PEN PENETRATION
PFJ PERIMETER FELT JOINT
PL PLATE
PLYWD PLYWOOD
PNL PANEL
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
PT PRESSURE TREATED, POINT, PRETENSIONED
REINF REINFORCING, REINFORCED
REQ REQUIRE
REQD REQUIRED
REQMT REQUIREMENT
RET RETURN, RETAINING
REV REVISION, REVISED
RF ROOF RFT RAFTERS
RPM REVOLUTIONS PER MINUTE
RS ROUGH SAWN
RT ROOF TRUSS
S SECTION MODULUS
SC SLIP CRITICAL
SCBRW SEGMENTAL CONCRETE BLOCK RETAINING WALL
SCHED SCHEDULE
SDI STEEL DECK INSTITUTE
SECT SECTION
SEIS SEISMIC
SEOR STRUCTURAL ENGINEER OF RECORD
SEP SEPARATION
SHT SHEET
SHTHG SHEATHING
SIM SIMILAR
SJI STEEL JOIST INSTITUTE
SMS SHEET METAL SCREW
SOG SLAB ON GRADE
SPEC(S) SPECIFICATION(S)
SPRT SUPPORT
SQ SQUARE
SS STAINLESS STEEL
ST SNUG TIGHT
STD STANDARD
STIF/STIFF STIFFENER
STL STEEL
STRUCT STRUCTURAL, STRUCTURE
SUSP SUSPENDED
SYM SYMMETRICAL
T&B TOP AND BOTTOM
T&G TONGUE AND GROOVE
THK THICK, THICKNESS
TL TOTAL LOAD
TN TOE NAIL
TO TOP OF
TOB TOP OF BEAM
TOC TOP OF CONCRETE
TOGB TOP OF GRADE BEAM
TOF TOP OF FOOTING
TOS TOP OF STEEL
TOW TOP OF WALL
TYP TYPICAL
UFC UNITED FACILITES CRITERIA
UNO UNLESS NOTED OTHERWISE
UON UNLESS OTHERWISE NOTED
VB VAPOR BARRIER
VERT VERTICAL
VIF VERIFY IN FIELD
W WIDTH, WEST, WIDE FLANGE
W/ WITH
W/O WITHOUT
WF WIDE FLANGE
WPT WORKING POINT
WWF WELDED WIRE FABRIC
WWM WELDED WIRE MESH
x BY, TIMES
GENERAL NOTES
1. ALL MATERIALS AND WORKMANSHIP SHALL BE PERFORMED IN ACCORDANCE WITH LOCAL STANDARDS
AND APPLICABLE PROVISIONS OF THE CURRENT BUILDING CODES LISTED HEREIN. ASTM REFERENCES
ARE FROM THE LATEST ISSUE AND LATEST REVISION, UNLESS OTHERWISE NOTED.
2. THE GENERAL CONTRACTOR SHALL VERIFY ALL DIMENSIONS AND CONDITIONS AT THE JOB SITE, AND SHALL BE RESPONSIBLE FOR CONDITIONS OF ALL WORK AND MATERIALS, INCLUDING THOSE FURNISHED
BY SUB-CONTRACTORS. ANY DISCREPANCIES AND/OR VARIATIONS SHALL BE BROUGHT TO THE
ATTENTION OF THE ARCHITECT AND STRUCTURAL ENGINEER PRIOR TO FABRICATION OR
CONSTRUCTION.
3. THE CONTRACT STRUCTURAL DRAWINGS AND REPRESENT THE FINISHED STRUCTURE. UNLESS
OTHERWISE INDICATED, THEY DO NOT INDICATE THE METHOD OF CONSTRUCTION. THE CONTRACTOR SHALL PROVIDE ALL MEASURES NECESSARY TO PROTECT THE STRUCTURE, WORKMEN, AND OTHER PERSONS DURING CONSTRUCTION. SUCH MEASURES SHALL INCLUDE, BUT NOT LIMITED TO BRACING, SHORING FOR CONSTRUCTION EQUIPMENT, SHORING FOR THE BUILDING, SHORING FOR THE EARTH BANKS, FORMS, SCAFFOLDING, PLANKING, SAFETY NETS, SUPPORT AND BRACING FOR CRANES AND GIN POLES, ETC. THE CONTRACTOR SHALL SUPERVISE AND DIRECT THE WORK AND HE SHALL BE SOLELY
RESPONSIBLE FOR ALL CONSTRUCTION MEANS, METHODS, TECHNIQUES, SEQUENCES AND
PROCEDURES. OBSERVATION VISITS TO THE SITE BY THE ARCHITECT OR THE ENGINEER SHALL NOT INCLUDE THE INSPECTION OF THE ABOVE ITEMS. CONSTRUCTION MATERIALS, PLACED ON STRUCTURAL MEMBERS, SHALL BE POSITIONED SUCH THAT THE LOADING DOES NOT EXCEED DESIGN LOADS LISTED
HEREIN.
4. DETAILS SHOWN ON DRAWINGS APPLY AT ALL LIKE CONDITIONS. THESE DRAWINGS SHOW ONLY
REPRESENTATIVE AND TYPICAL DETAILS TO ASSIST THE CONTRACTOR. THE DRAWINGS DO NOT
ILLUSTRATE EVERY CONDITION. ALL ATTACHMENT, CONNECTIONS, FASTENINGS, ETC. TO BE PROPERLY
SECURED IN CONFORMANCE WITH BEST PRACTICE, AND THE CONTRACTOR IS RESPONSIBLE FOR
PROVIDING AND INSTALLING THEM.
5. DRAWINGS SHALL NOT BE SCALED FOR CONSTRUCTION PURPOSES.
6. NO PIPES, CONDUITS, OR DUCTS SHALL BE PLACED IN STRUCTURAL MEMBERS UNLESS SPECIFICALLY
DETAILED OR APPROVED BY THE ENGINEER.
7. REFER TO MECHANICAL DRAWINGS FOR ALL DIMENSIONAL INFORMATION AND NON-STRUCTURAL ITEMS
NOT SHOWN HEREIN, INCLUDING:
a. ALL FLOOR, ROOF, & WALL OPENINGS.
8. REFER TO MECHANICAL, PLUMBING, AND ELECTRICAL DRAWINGS FOR ALL INFORMATION RELATED TO
MEP ITEMS & DISTRIBUTION SYSTEMS EXCEPT AS SHOWN OR NOTED HEREIN.
9. CONSTRUCTION MATERIALS, PLACED ON STRUCTURAL MEMBERS, SHALL BE POSITIONED SUCH THAT
THE LOADING DOES NOT EXCEED DESIGN LOADS LISTED HEREIN.
10. DETERMINE THE LOCATION OF UTILITY SERVICES IN AREAS TO BE EXCAVATED BEFORE BEGINNING EXCAVATION. EXERCISE EXTREME CAUTION IN EXCAVATING AND TRENCHING. DAMAGE CAUSED AS A RESULT OF FAILING TO EXACTLY LOCATE AND PRESERVE ALL EXISTING UNDERGROUND UTILITIES IS THE
RESPONSIBILITY OF THE CONTRACTOR.
11. THE CAD DRAWING FILES ARE THE PROPERTY OF THE STRUCTURAL ENGINEER AND WILL NOT BE
RELEASED TO THE CONTRACTOR OR SUBCONTRACTORS FOR THEIR USE.
12. STRUCTURAL DRAWINGS TO BE USED IN CONJUNCTION WITH MECHANICAL DRAWINGS BY: DAVENERGY
SOLUTIONS
DEMOLITION NOTES
1. THESE PLANS REPRESENT INFORMATION TAKEN FROM THE ORIGINAL CONSTRUCTION DOCUMENTS
WHERE AVAILABLE AND SITE OBSERVATION. DURING DEMOLITION ALL CONDITIONS LISTED AS EXISTING ARE TO BE CONFIRMED IN THE FIELD. ALL CONDITIONS FOUND TO BE DIFFERENT FROM THE CONDITIONS REPRESENTED IN THESE PLANS AND THOSE OF OTHER DISCIPLINES ARE TO BE REPORTED TO THE
ENGINEER IMMEDIATELY.
2. THE CONTRACTOR SHALL SUPPLY ALL SHORING AND TEMPORARY BRACING AND STRUCTURAL
ENGINEERING NECESSARY TO PERFORM WORK EXCEPT WHERE SPECIFICALLY DETAILED IN THESE DRAWINGS. ALL ENGINEERING IS TO BE PERFORMED BY A CIVIL OR STRUCTURAL ENGINEER REGISTERED
IN THE STATE OF CALIFORNIA.
3. ALL BUILDING COMPONENTS SUCH AS ROOF BEAMS, GIRDERS AND SUB-PURLINS SHALL BE PROPERLY
SHORED AND BRACED AS DESIGNED PRIOR TO REMOVAL OF ANY SUPPORTING MEMBERS.
4. ALL TEMPORARY SHORING AND BRACING SHALL REMAIN IN PLACE UNTIL NEW SUPPORTING FRAMING IS PROPERLY SECURED AND/OR ANCHORED IN PLACE AND EXISTING SHORED BUILDING COMPONENTS ARE
PROPERLY ATTACHED ACCORDING TO THE DETAILS SPECIFIED HEREIN.
5. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR THE VERIFICATION OF UTILITIES SHUTDOWN PRIOR TO DEMOLITION (I.E. GAS, WATER, ELECTRICAL SUPPLIES). ANY SHUTDOWN OF THE FIRE PROTECTION SYSTEM IS TO BE COORDINATED WITH THE LOCAL FIRE DEPARTMENT AND THE FIRE PROTECTION SYSTEM
CONSULTANT.
6. IN PREPARATION OF THESE DRAWINGS IT HAS BEEN NECESSARY TO ASSUME SOME AS-BUILT CONDITIONS TO EXIST TO COMPLETE THE DESIGN WORK. WHERE THESE ASSUMPTIONS ARE MADE THE CONDITION IS IDENTIFIED AS "ASSUMED" OR "VERIFY IN FIELD (V.I.F)" ON THE DRAWINGS. CONTRACTOR SHALL VERIFY THESE CONDITIONS AND REPORT ANY DISCREPANCIES TO THE SEOR IF THE WORK
REQUIRES MODIFICATION OF THESE AS- BUILT CONDITIONS.
CAR
Rpo
STRUCTURAL OBSERVATION NOTES
1. THE OWNER SHALL EMPLOY THE ENGINEER RESPONSIBLE FOR THE STRUCTURAL DESIGN, TO PERFORM
STRUCTURAL OBSERVATION AS DEFINED IN IBC. OBSERVED DEFICIENCIES SHALL BE REPORTED IN WRITING TO THE OWNER'S REPRESENTATIVE, SPECIAL INSPECTOR, CONTRACTOR AND THE BUILDING OFFICIAL. ALL DOCUMENTED OBSERVED DEFICIENCIES MUST BE RESOLVED FOR THE STRUCTURAL SYSTEM TO BE DEEMED IN COMPLIANCE WITH THE APPROVED PLANS & SPECIFICATIONS. THE STRUCTURAL OBSERVER SHALL SUBMIT TO THE AHJ A WRITTEN STATEMENT THAT THE SITE VISITS HAVE BEEN MADE AND IDENTIFIED, REPORTED DEFICIENCIES HAVE, TO THE BEST OF THE STRUCTURAL OBSERVER'S KNOWLEDGE, HAVE BEEN RESOLVED. THE CONTRACTOR SHALL CONTACT THE STRUCTURAL ENGINEER A MINIMUM OF 5 WORKING DAYS PRIOR TO THE PROJECT REACHING THE PRESCRIBED MILESTONES OF CONSTRUCTION LISTED BELOW.
ADDITIONALLY, WITHIN TWO DAYS AFTER THE START OF CONSTRUCTION, THE CONTRACT SHALL PROVIDE A PROJECT SCHEDULE TO THE STRUCTURAL ENGINEER OUTLINING THE ESTIMATED DATES THE STRUCTURAL
OBSERVATIONS WILL BE REQUIRED.
2. STRUCTURAL OBSERVATION IS THE VISUAL OBSERVATION OF THE STRUCTURAL SYSTEM BY SEOR FOR GENERAL CONFORMANCE TO THE APPROVED CONSTRUCTION DOCUMENTS AT CONSTRUCTION STAGES
LISTED BELOW SPECIAL INSPECTIONS SHALL ALSO BE PROVIDED AS REQUIRED HEREIN.
3. THE STRUCTURAL OBSERVER SHALL PERFORM SITE VISITS AT THOSE STEPS IN THE PROGRESS OF THE
WORK THAT ALLOW FOR CORRECTION OF THE DEFICIENCIES WITHOUT SUBSTANTIAL EFFORT OR
UNCOVERING OF THE WORK INVOLVED. AT A MINIMUM, THE FOLLOWING SIGNIFICANT CONSTRUCTION STAGES REQUIRE A SITE VISIT AND AN OBSERVATION REPORT FROM THE STRUCTURAL OBSERVER:
4. NO STRUCTURAL DETAILS ARE TO BE COVERED PRIOR TO STRUCTURAL OBSERVATION. CONTRACTOR SHALL SCHEDULE PROJECT ACCORDINGLY TO ALLOW ALL STRUCTURAL DETAILS TO BE OBSERVE DURING ONE OF
THE THREE STRUCTURAL OBSERVATIONS.
ITEMS TO BE OBSERVED:
1. ANCHORAGE OF DOWELS WITH EPOXY
(CONCRETE CURB)
A. FRAMING
CONSTRUCTION STAGES:
SHOP DRAWINGS/SUBMITTALS
1. THE FOLLOWING SUBMITTAL SHALL BE SUBMITTED TO THE SEOR PRIOR TO FABRICATION FOR APPROVAL:
2. STRUCTURAL FRAMING AND REINFORCING LISTS, QUANTITIES AND LENGTHS OF ALL MATERIALS IS THE RESPONSIBILITY OF THE CONTRACTOR TO ENSURE COMPLIANCE WITH THE CONTRACT DOCUMENTS. THESE
ITEMS ARE NOT INCLUDED IN SEOR REVIEW.
3. REVIEW OF SHOP DRAWINGS BY THE SEOR IS FOR GENERAL COMPLIANCE WITH THE CONTRACT DOCUMENTS AND STRUCTURAL DESIGN INTENT. ALL ERRORS IN DETAILING, FABRICATION, AND FOR CORRECT FITTING OF ALL STRUCTURAL MEMBERS INCLUDING COORDINATION WITH OTHER TRADES IS THE RESPONSIBILITY OF THE CONTRACTOR. SHOP DRAWING SUBMITTALS PROCESSED BY THE ENGINEER DO NOT CONSTITUTE CHANGE ORDERS. ANY PROPOSED CHANGES MUST BE SUBMITTED IN A LETTER OR DETAIL
TO THE SEOR FOR APPROVAL.
4. SHOP DRAWINGS SHALL BE SUBMITTED AT LEAST TWO WEEKS PRIOR TO THE SCHEDULED FABRICATION DATE. A DIGITAL SET CLEARLY MARKED WITH ANY COMMENTS WILL BE RETURNED TO THE CONTRACTOR.
5. ANY SHOP DRAWINGS SHALL BE INDEPENDENTLY CREATED BASED ON THE INFORMATION SHOWN IN THE
APPROVED STRUCTURAL DRAWINGS.
a. MIX DESIGN FOR:
i. CONCRETE
b. REINFORCING BAR LAYOUT FOR:
i. CONCRETE
CONCRETE
1. CEMENT SHALL CONFORM TO ASTM C150, TYPE II/V.
2. CONDUITS EMBEDDED HORIZONTALLY IN THE SLAB SHALL HAVE AN OUTSIDE DIAMETER NO GREATER THAN 1/3 THE THICKNESS OF THE SLAB. CONDUIT SHALL NOT BE EMBEDDED IN A SLAB THAT IS LESS THAN 3 1/2" THICK. EXCEPT FOR LOCAL OFFSETS, MIN. CLEAR DISTANCE BETWEEN CONDUITS SHALL BE 6". REFER TO MECHANICAL AND ELECTRICAL DRAWINGS FOR LOCATION OF ALL PIPES, CONDUITS, ETC. NO PIPES OR DUCTS SHALL BE PLACED IN CONCRETE BEAMS, FOOTINGS, OR SLABS, UNLESS SPECIFICALLY DETAILED IN
THESE PLANS, OR AS APPROVED BY THE STRUCTURAL ENGINEER.
3. AGGREGATES FOR NORMAL WEIGHT CONCRETE SHALL CONFORM TO ASTM C33, 1 1/2" MAXIMUM SIZE.
AGGREGATES FOR LIGHTWEIGHT CONCRETE SHALL CONFORM TO ASTM C330, 1" MAXIMUM SIZE.
4. THE MAXIMUM CONCRETE SLUMP SHALL BE PER SCHEDULE BELOW PRIOR TO THE ADDITION OF ANY
PLASTICIZING ADMIXTURES.
5. ADMIXTURES MAY BE USED WITH PRIOR WRITTEN APPROVAL OF THE ENGINEER. APPROVAL MUST BE RECEIVED DURING THE BUILDING PERIOD. ADMIXTURES SHALL COMPLY WITH ASTM A494 AND BE OF THE TYPE THAT INCREASE THE WORKABILITY OF THE CONCRETE, BUT SHALL NOT BE CONSIDERED TO REDUCE
THE SPECIFIED MINIMUM CEMENT CONTENT. (CALCIUM CHLORIDE SHALL NOT BE USED).
6. READY-MIX CONCRETE SHALL BE MIXED AND DELIVERED IN ACCORDANCE WITH ASTM C94.
7. ALL REINFORCING BARS AND INSERTS SHALL BE SECURED IN PLACE PRIOR TO CONCRETE, POUR.
8. NON-STRUCTURAL STEEL MEMBERS EMBEDDED IN CONCRETE SHALL BE GALVANIZED OR PAINTED. ALL
DAMAGED GALVANIZED AREAS SHALL BE REPAIRED PRIOR TO EMBEDMENT.
9. LIGHT-WEIGHT CONCRETE FILL SHALL HAVE A MAXIMUM DRY DENSITY OF 110 pcf. ALL OTHER CONCRETE SHALL HAVE A MAXIMUM DRY DENSITY OF 150 pcf.
10. MINIMUM CONCRETE COMPRESSIVE STRENGTH AND MAXIMUM SLUMPS:
11. PROVIDE (2) #4 DIAGONAL BARS AT CORNERS OF ALL OPENINGS IN CONCRETE FLOORS AND ROOFS.
12. PROVIDE CONSTRUCTION AND CONTROL JOINTS AS SHOWN ON PLANS AND IN TYPICAL DETAILS UNLESS SPECIFIED OTHERWISE. LOCATION OF JOINTS NOT SPECIFICALLY INDICATED SHALL BE REVIEWED BY THE
SEOR PRIOR TO PLACING REINFORCING STEEL.
13. DRY PACK SHALL BE ONE PART CEMENT AND 2 3/4 PARTS SAND WITH SUFFICIENT WATER TO HYDRATE CEMENT AND FORM A BALL SHOWING MOISTURE ON THE SURFACE WHEN SQUEEZED. IT SHALL BE RAMMED IN TIGHT TO MAXIMUM DENSITY ATTAINABLE, AND SHALL HAVE A MINIMUM STRENGTH OF 5000 PSI AT 28
DAYS.
14. NON-SHRINK GROUT SHALL HAVE A MINIMUM COMPRESSIVE STRENGTH AT 28 DAYS OF 7,000 psi PER ASTM
C109. GROUT BASE PLATES AFTER PLUMBING OF COLUMN.
15. CHAMFER ALL EXPOSED EDGES OF CONCRETE 3/4 INCH.
16. ALL CONCRETE WHICH DURING THE LIFE OF THE STRUCTURE WILL BE SUBJECT TO FREEZING TEMPERATURES WHILE WET, SHALL HAVE A WATER CEMENT RATIO NOT EXCEEDING 0.45 BY WEIGHT AND SHALL CONTAIN ENTRAINED AIR PER ACI 613. SUCH CONCRETE SHALL INCLUDE EXTERIOR SLABS, PERIMETER FOUNDATIONS, EXTERIOR CURBS, ETC.
17. CONTRACTOR SHALL SUBMIT CONCRETE MIX DESIGNS, INCLUDING AGGREGATE GRADATION, FOR CONCRETE STRENGTH F'c > 2500 PSI.
MIN f'c
(28 DAYS) MAX SLUMP W/C
ALL NEW CONCRETE 3,000 psi 4" +/- 1" 0.55
*2500 PSI DESIGNED STRENGTH, SPECIAL INSPECTION NOT REQUIRED, SEE
INTERIOR FLOOR SLAB NOTES ON THIS SHEET FOR ADDITIONAL REQUIREMENTS
REINFORCING STEEL
1. METAL REINFORCING:
2. ALL REINFORCING SHALL BE DETAILED, FABRICATED, AND ERECTED IN ACCORDANCE WITH THE LATEST
ACI STANDARDS AND THE LATEST EDITION OF THE GOVERNING CODES HEREIN.
3. ALL REINFORCING SHALL BE ADEQUATELY SUPPORTED TO PREVENT DISPLACEMENT BY CONCRETE
PLACEMENT OR WORKERS.
4. FOR WELDING OF REINFORCING BARS SPECIAL INSPECTION IS REQUIRED. TESTING IS REQUIRED FOR
ALL WELDS THICKER THAN 5/16".
5. WHERE REINF. BARS ARE CALLED OUT TO BE CONTINUOUS (CONT.) PROVIDE CONTINUOUS BARS OR FULL SPLICES PER SPLICE TABLE SCHEDULE. IT IS CONTRACTOR'S OPTION TO PROVIDE CONTINUOUS
BARS WHERE SPLICES ARE SHOWN.
6. MESH SPLICES SHALL BE A MINIMUM OF TYPICAL GRID SPACING PLUS 2" (8" MINIMUM) MEASURED
BETWEEN CROSS WIRES.
7. PROVIDE MINIMUM CONCRETE COVER FOR REINFORCING IN ACCORDANCE WITH THE LATEST ACI
STANDARDS AND THE LATEST EDITION OF THE CURRENT BUIDLING CODE HEREIN:
8. ALL REINFORCING STEEL, ANCHOR BOLTS, DOWELS AND INSERTS SHALL BE WELL SECURED IN
POSITION PRIOR TO PLACING CONCRETE OR GROUT.
9. FURNISH #3 SPACER TIES AT APPROXIMATELY 2'-6" ON CENTER IN ALL BEAMS AND FOOTINGS TO
SECURE REINFORCING IN PLACE, UNLESS OTHERWISE NOTED.
10. ALL REINFORCEMENT SHALL BE BENT COLD. REINFORCEMENT PARTIALLY EMBEDDED IN CONCRETE
SHALL NOT BE FIELD BENT.
11. COORDINATE PLACEMENT OF CAST-IN-PLACE EMBEDS AND ANCHOR RODS. SET ANCHOR RODS WITH A
TEMPLATE. SECURELY ATTACH EMBED ITEMS TO FORMWORK OR REINFORCING.
12. PROVIDE CLASS "B" REINFORCEMENT SPLICES FOR CONTINUOUS REINFORCEMENT. PROVIDE
STANDARD 90-DEGREE HOOKS IN ACCORDANCE WITH ACI 318, UNLESS NOTED OTHERWISE.
13. DO NOT WELD OR BEND REINFORCEMENT IN THE FIELD UNLESS SPECIFICALLY SHOWN OR APPROVED
BY STRUCTURAL ENGINEER.
14. WHERE REQUIRED, PROVIDE…