This document outlines a forthcoming solicitation for construction services to replace kitchen ventilation hoods at the Richmond VA Medical Center. The project includes demolishing the existing kitchen hood ventilation system and replacing it with a new system that meets all VA requirements and fits in the allocated space. Interested contractors must be registered in SAM.gov and VetCert and have the required NAICS code to be eligible for award. The solicitation is anticipated to be issued on February 22, 2024 via SAM.gov as an IFB with a 30-day response time. The construction value is estimated between $250,000 and $500,000. The set-aside is for Service-Disabled Veteran Owned Small Businesses. The statement of work, wage determination and other applicable documents will be made available electronically on the date of issuance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Richmond VA Medical Center

PROJECT NO. 652-52-124

Replace Kitchen Ventilation Hood System – 500L: IFC Submittal

U.S. Veteran Affairs 652-52-124

Hunter Homes McGuire Hospital Richmond VA Medical Center

1201 Broad Rock Blvd Richmond, VA 23249

652-52-124

Replace Kitchen Ventilation Hood System – 500L

SPECIFICATIONS

Issued for Construction Prepared by

Date: April 5, 2021

Project No. 652-52-124

Kevin Snapshot

Richmond, VA 652-52-124 Replace Kitchen Ventilation Hoods 100% Construction Documents

TABLE OF CONTENTS

00 01 10 - 1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-15

01 00 00.A1 Bid Form Template

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-13

01 33 23 Shop Drawings, Product Data, and Samples 02-17

01 35 26 Safety Requirements 02-17

01 42 19 Reference Standards 05-16

01 45 00 Quality Control 02-21

01 45 29 Testing Laboratory Services 06-16

01 57 19 Temporary Environmental Controls 01-11

01 58 16 Temporary Interior Signage 07-15

01 74 19 Construction Waste Management 09-13

01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 21 13 Site Surveys 08-16

02 41 00 Demolition 02-15

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete 02-16

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 02-16

05 36 00 Composite Metal Decking 10-15

05 50 00 Metal Fabrications 07-14

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 01 50.19 Preparation for Re-Roofing 02-16

07 22 00 Roof and Deck Insulation 02-16

07 54 23 Thermoplastic Polyolefin (TPO) Roofing 08-16

07 60 00 Flashing and Sheet Metal 07-14

07 71 00 Roof Specialties 10-15

07 72 00 Roof Accessories 10-15

TABLE OF CONTENTS

00 01 10 - 2

07 84 00 Firestopping 02-16

07 92 00 Joint Sealants 10-15

DIVISION 09 – FINISHES

09 51 00 Acoustical Ceilings 12-16

DIVISION 11 – EQUIPMENT

11 40 21 Food Service Equipment-Utility Distribution System 11-11

11 44 00 Food Cooking Equipment 11-11

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural Components 01-14

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16

21 22 00 Clean Agent Fire Suppression Systems 05-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16

22 08 00 Commissioning of Plumbing Systems 11-16

22 11 00 Facility Water Distribution 09-15

22 13 00 Facility Sanitary and Vent Piping 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-15

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 02-15

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15

23 07 11 HVAC and Boiler Plant Insulation 02-15

23 08 00 Commissioning of HVAC Systems 11-16

23 09 23 Direct-Digital Control System for HVAC 09-11

23 31 00 HVAC Ducts and Casings 03-13

23 34 00 HVAC Fans 02-15

23 37 00 Air Outlets and Inlets 02-15

23 38 13 Commercial-Kitchen Hoods 01-11

DIVISION 25 – INTEGRATED AUTOMATION

TABLE OF CONTENTS

00 01 10 - 3

25 10 10 Advanced Utility Metering System 02-10

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17

26 05 26 Grounding and Bonding for Electrical Systems 01-17

26 05 33 Raceway and Boxes for Electrical Systems 05-14

26 08 00 Commissioning of Electrical Systems 11-16

26 09 23 Lighting Controls 05-14

26 24 16 Panelboards 05-14

26 27 26 Wiring Devices 01-16

26 51 00 Interior Lighting 08-14

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 06-15

27 05 26 Grounding and Bonding for Communications Systems 06-15

27 05 33 Raceways and Boxes for Communications Systems 06-15

27 08 00 Commissioning of Communications Systems 11-16

27 10 00 Control, Communication and Signal Wiring 06-15

27 15 00 Communications Structured Cabling 01-16

GENERAL REQUIREMENTS

01 00 00 - 1

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 SAFETY REQUIREMENTS

1.2 GENERAL INTENTION

1.3 STATEMENT OF BID ITEM(S)

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.5 CONSTRUCTION SECURITY REQUIREMENTS

1.6 OPERATIONS AND STORAGE AREAS

1.7 ALTERATIONS

1.8 DISPOSAL AND RETENTION

1.10 PHYSICAL DATA

1.11 AS-BUILT DRAWINGS

1.14 USE OF ROADWAYS

1.15 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.16 TEMPORARY USE OF EXISTING ELEVATORS

1.17 AVAILABILITY AND USE OF UTILITY SERVICES

1.18 TESTS

1.19 INSTRUCTIONS

1.20 SAFETY SIGN

1.21 HISTORIC PRESERVATION

GENERAL REQUIREMENTS

01 00 00 - 2

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

1. Contractor shall the purpose of this project is to provide a renovation, new construction, equipment replacements, and utility modifications to replace the Kitchen hoods ventilation.

The renovation shall include demolishing out the entire kitchen hood ventilation system on both sides of the grills and replacing it with new. New hood must meet all VA requirements, new hood must also be a perfect fit in the provided space. New hood arrangement allows for maintenance on a single hood at a time without shutting down the entire kitchen.

Contractor shall provide hoods so they can be individually worked on without affecting the others. If one of the hoods are to be commission, it would not affect the other hoods.

Existing hoods include (2) 102 3/16” X 52” and (3) 114 3/16” X 52” boxed style canopy’s welded stainless steel ducted hoods.

Deductive Alternate #1 eliminates the scope associated with replacing Hood #1 and

Hood #2 and fire suppression system.

Add Alternate #1 includes replacing the Utility Distribution Systems associated with the hoods.

Add Alternate #2 includes replacing the grease duct serving the existing hood and providing new stainless-steel duct.

The exhaust fan for these hoods is on the 5th floor roof. Contractor shall replace the existing exhaust fan, circuit breaker and wiring with and reuse existing ductwork under the base bid. Add alternate #2 includes replacement of grease duct to the exhaust fan.

1. Normal Working Hours are 0730 to 1600, Monday to Friday.

2. For working outside these hours requires prior written approval from the COR.

Due to the work site location, it is anticipated that off-hours work will be required to perform this project work.

3. Contractor shall coordinate all shut downs to limit the impact on Kitchen operations and hood replacements shall be phased to replace a single hood at a time during off-hours.

4. Temporary construction provisions/poly barriers shall be used to isolate the individual hood being replaced.

5. HEPA carts shall be used to perform all ceiling/diffuser modifications.

GENERAL REQUIREMENTS

01 00 00 - 3

6. Renovation includes requirements for Testing and Balancing (TAB) the HVAC for the existing and new systems configuration. Preconstruction TAB shall be performed on existing terminal units, air handling unit, make up air unit and exhaust fans serving the space. Preconstruction TAB reports shall be submitted to AE/VA for confirmation on final CFM for each device being modified by this renovation.

B. Visits to the site by Bidders may be made only by appointment with the Medical Center

Engineering Officer.

C. Offices of Offices of Triple C – The A&E Group with offices at 2266 S. Dobson Road, Suite 200, Mesa, AZ 85202, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the

Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. All testing shall be by certified testing laboratories subcontracted by the Contract. The

Government shall not be required to contract testing for any trade.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

F. The Government does not provide courtesy, pre-inspections of area during the construction. The Contractor shall request progress inspections and communicate requests for inspections at least one week in advance.

G. Contractor shall appoint a third-party individual, company or firm to act as the

Commissioning Agent. The Commissioning Agent is the designated person, company, or entity that plans, schedules, and coordinates the commissioning team to implement the commissioning process. See 01 91 00 for more details.

H. Comprehensive 3rd party inspections, testing and written reports for all Divisions (paid by the General Contractor). Contractor shall employ third party inspection consultants to perform all inspections required by this contract. The VA has no inspection capability. Any reference to VA inspections shall be by a third-party inspector qualified to perform the work. Credentials shall be supplied to the VA/AE as required by this contract. All inspections, testing, certifications, and permits are to be paid for by the

General Contractor. The VA will not pay for or perform any required inspections. VA inspections are for VA use only, when performed, and do not reduce the inspection burden on the Contractor. Third party inspection services must be submitted for acceptance by the VA after award. Submission to include resumes of inspectors, with alternates, projected days on site, qualifications of inspectors showing similar projects, related portfolio, and description of communication protocol with Owner.

Acceptable 3rd Party inspectors include the following:

Parsons Brinckerhoff http://www.wsp-pb.com/en/WSP-USA/What-we-do-

USA/Services/All- Services-A-Z/Bridge-Engineering/Construction-Inspection/

Booz Allen http://www.boozallen.com http://www.wsp-pb.com/en/WSP-USA/What-we-do-USA/Services/All-http://www.wsp-pb.com/en/WSP-USA/What-we-do-USA/Services/All-http://www.boozallen.com/

GENERAL REQUIREMENTS

01 00 00 - 4

US Army Corps of Engineers http://www.usace.army.mil/ Bureau Veritas http://www.bureauveritas.com/

Stantec http://www.stantec.com/our-work/services/construction-qa-qc-monitoring-inspection- services.html

HDR, Inc. http://www.hdrinc.com/

Gilbane http://www.gilbaneco.com

Minimum inspections required:

Mechanical, Electrical, Plumbing, Fire Protection, low voltage systems, communications, controls system integration, commissioning support

I. Contractor to provide Submittal Exchange® , Autodesk A360® Project Site dedicated for this project, or approved equal (substitutions must be submitted with Contractor

Bid), for the duration of the contract. Contractor will provide VA access to the site.

Contractor will keep this site current and will use it for all submittals, RFIs, change documents, Record Drawing, electronic file management, and communication logs for the duration of the contract.

J. Contractor to provide Infection Control Plan as required by Memorandum 111-40, Subj: VHA Directive 7715 Safety and Health During Construction dated April 6, 2017. Submit to COR for approval prior to the start of work.

K. Prior to commencing work, general contractor shall provide proof that a OSHA designated “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present. CP will have authority letter.

L. Pricing Proposal transparency requirements: this project requires pricing proposals to include breakdown pricing for the General Contractor and all subcontractors. All price proposals, including subcontractor pricing must include a breakdown of pricing per the format included with tis specification. Third-party inspections must be included as a line item in the price proposal. See example at the end of GENERAL REQUIREMENTS section.

M. Refer to specifications for installation requirements for each Division. Refer to drawings for estimated quantities and schematic layouts/locations. Contractor to provide a complete, commissioned, functioning product. The VA is not required to inspect or install any portion of this project. Contractor bears all installation and testing costs.

Contractor to provide all testing reports prior to the start of commissioning. This project requires phased commissioning and turnover by building. This project will require night and weekend work.

1.3 STATEMENT OF BID ITEM(S)

ITEM I, General Construction:

Contract documents, drawings and specifications, indicate the scope of work. This project provides the new construction, renovation, and infrastructure required to provide new kitchen hood ventilation system.

http://www.usace.army.mil/ http://www.bureauveritas.com/ http://www.stantec.com/our-work/services/construction-qa-qc-monitoring-inspection-http://www.stantec.com/our-work/services/construction-qa-qc-monitoring-inspection-http://www.hdrinc.com/ http://www.gilbaneco.com/

GENERAL REQUIREMENTS

01 00 00 - 5

Bids shall be provided as Contract Line Item Number (CLIN) in the format shown in

Appendix A, and as summarized below. The work for all CLINs shall be completed in a maximum of 180 days. The work for each building/CLIN shall be completed as follows:

1. CLIN 01: All work as identified by the Base Bid drawings and specifications shall be completed in 180 days.

2. CLIN 02: All work as identified by the drawings and specifications pertaining to

Deductive Alternate No. 1 shall be completed in 30 days.

3. CLIN 03: All work as identified by the drawings and specifications pertaining to

Additive Alternate No. 1 shall be completed in 30 days

4. CLIN 04: All work as identified by the drawings and specifications pertaining to

Additive Alternate No. 2 shall be completed in 60 days

The expected construction period duration for each CLIN includes all pre-construction activity and post-construction testing, third-party inspections and commissioning.

Contractor is to phase and staff the construction appropriately such that the total project duration including all CLIN does not exceed 365 days. CLIN construction activities must occur concurrently to meet this Construction Schedule. Contractor shall submit a comprehensive schedule of work in compliance with 01 32 16.15 PROJECT

SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD). Contractor to perform

Commissioning of all new systems and existing systems impacted by the project according to requirements in sections: 01 91 00 – GENERAL COMMISSIONING

REQUIREMENTS; 23 08 00 – COMMISSIONING OF HVAC SYSTEMS; 26 08 00 –

COMMISSIONING OF ELECTRICAL SYSTEMS; and 27 08 00 – COMMISSIONING OF

COMMUNICATIONS SYSTEMS. A detailed commissioning plan is required to ensure that all devices are calibrated, programmed, and all graphic displays are accurate and approved by applicable VA staff.

ITEM II, Electrical, Communications and Security Systems Work: Includes all labor, material, equipment and supervision to perform the required electrical construction work on this project including Contractor shall provide load monitoring data to the COR/AE.

New circuit breakers and wiring/conduit shall be provided for the new hood, fire suppression system, hood controls and exhaust fan.

All panels, at the time of design survey (December 2020) had the required capacity. This test is required by NEC 220.87 for verification that no loads have been added since the design level survey. Electrical service shall be provided to the new hoods, exhaust fans and fire suppression systems. Add Alternate #1 includes replacing the Utility Distribution

System as indicated on the drawings.

ITEM III, Mechanical, Plumbing and Fire Protection Work: Work includes all labor, material, equipment and supervision to perform the required Mechanical construction work on this project including provide material and construction equipment to Contractor shall submit coordination drawings prior to commencing work showing new and existing systems and all provisions for coordinating existing utilities. Add Alternate #2 includes

GENERAL REQUIREMENTS

01 00 00 - 6 replacing the grease duct from the Kitchen hoods to the exhaust fan as indicated on the drawings.

Contractor is required to Test and Balance (TAB) new and existing HVAC systems per

23 05 93. This work requires preconstruction TAB readings to establish baseline performance for all existing HVAC systems. All new and existing systems within the

Scope of Work shall be commissioned (or recommissioned) per Specification 01 91 00.

Bids shall identify CLIN 01 – CLIN 04 as separate bid line items. See 01 00 00 Appendix A “Sample Bid Form” for format.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the

Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the

Contracting Officer.

4. VA reserves the right to close down or shut down the project site and order

General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

5. Contractor shall secure all IT closet spaces at the end of each day.

6. Ceiling tiles must be in place at the end of each working day to provide smoke barrier.

C. Key Control:

1. Contractor will be issued VA Keys and will require a signature confirming that they received the key(s) listed on signature form. General Contractor is responsible for returning these keys upon separation of project or at any time the

VA requests. Lost or misplaced keys are to be reported to VA COR immediately

GENERAL REQUIREMENTS

01 00 00 - 7 and additional costs to replace keys and all cores associated with that key series will be calculated at that time with the VA Locksmith Shop and charged to the contractor.

2. The General Contractor shall provide duplicate keys and lock combinations to the

Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

3. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management

Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2 to 5) permits shall be issued for General Contractor and its employees for parking in designated areas only.

GENERAL REQUIREMENTS

01 00 00 - 8

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on

Government premises to areas authorized or approved by the Contracting Officer. The

Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as determined by the

COR.

1. Exterior Working space are to be fully maintained to include securing fencing, providing fabric screening on fencing, controlling dust through application of water as required, protecting the site with the use of rock, gravel material to control dust and erosion.

E. Workmen are subject to rules of Medical Center applicable to their conduct. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

F. Execute work so as to interfere as little as possible with normal functioning of Medical as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to

Medical Center areas required to remain in operation.

GENERAL REQUIREMENTS

01 00 00 - 9

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems

(except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Contractor.

H. Phasing: The Medical Center must maintain its operation 24 hours a day 7 days a week.

Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

1. To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to insure accomplishment of this work in successive phases mutually agreeable to

Medical Center Director, COR and Contractor.

Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.

I. Immediate areas of alterations will be temporarily vacated while alterations are performed.

J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company

GENERAL REQUIREMENTS

01 00 00 - 10

(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

K. Utilities Services: Maintain existing utility services for Medical Center at all times.

Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS

FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR

COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK

RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 30 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of

Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 30 calendar days prior to the desired time and shall be performed as directed by

COR .

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

M. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

GENERAL REQUIREMENTS

01 00 00 - 11

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

N. Coordinate the work for this contract with other construction operations as directed by the COR. This includes the scheduling of traffic and the use of roadways, as specified in

Article, USE OF ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the

COR in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of Building 41

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur, and which have been agreed upon COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of Resident Engineer COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by

Contractor with new items in accordance with specifications which will be furnished by

Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled

"DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and

VAAR 852.236-88).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved.

They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

GENERAL REQUIREMENTS

01 00 00 - 12

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by

Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the

Government. When rooms and spaces are vacated by the Department of

Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged. Existing work

(walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems

(including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in

GENERAL REQUIREMENTS

01 00 00 - 13 accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and

"DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.10 PHYSICAL DATA

A. Data and information furnished or referred to below is for the Contractor's information.

The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

1.11 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings.

To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

E. Contractor is to provide a LIDAR survey of the renovated area and the interstitial spaces above and below the affected area as part of the close out process. This LIDAR survey will serve as documentation that the work was completed and shall work in conjunction with the as-built drawings. The unregistered (raw) point cloud data and registered, linked, point cloud model shall be turned over the Government at project close out.

1.14 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

1.15 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, GENERAL REQUIREMENTS

01 00 00 - 14 motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014

Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the

Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the

Government.

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.

1.16 TEMPORARY USE OF EXISTING ELEVATORS

A. Use of existing elevators for handling building materials and Contractor's personnel will be permitted subject to following provisions:

1. Contractor makes all arrangements with the COR for use of elevators. COR will ascertain that elevators are in proper condition. Contractor may use elevators in

Building No. 41 for for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the

Department of Veterans Affairs.

2. Contractor covers and provides maximum protection of following elevator components:

a. Entrance jambs, heads soffits and threshold plates.

b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.

c. Finish flooring.

3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during

GENERAL REQUIREMENTS

01 00 00 - 15 temporary use, they shall be removed and replaced by new hoisting ropes at the contractor’s expense.

4. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining at the contractors expense.

5. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the contractors expense, if recommended by elevator inspector after elevator is released by Contractor.

6. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.

1.17 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the

Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

C. Contractor shall install meters at Contractor's expense and furnish the Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.

D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted.

Maintain minimum temperatures as specified for various materials:

1. Obtain heat by connecting to Medical Center heating distribution system.

E. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.

F. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system.

Provide reduced pressure backflow preventer at each connection as per code.

Water is available at no cost to the Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation

(COR discretion) of use of water from Medical Center's system.

GENERAL REQUIREMENTS

01 00 00 - 16

1.18 TESTS

A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.

B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.

C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.

E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.

F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.

1.19 INSTRUCTIONS

A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.

B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece

GENERAL REQUIREMENTS

01 00 00 - 17 of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.

C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections.