This document is an amendment to a solicitation for updating the public address system at the Salisbury VA Medical Center.

The amendment adds language requiring the vendor to report any witnessed fraud, waste or abuse to the Integrity and Compliance Officer. It also provides additional details on the scope of work. Specifically, it identifies 21 existing buildings that will have their existing paging speakers and cabling reused, and 7 additional buildings that require new public address systems installed. It describes the network of tunnels and manholes used to route cable pathways between buildings. The amendment provides details on the source equipment for buildings currently fed from others, and equipment replacements and upgrades needed. It outlines project requirements for installing new paging and network infrastructure with single-mode fiber, as well as equipment for buildings currently without systems. All public address head end units will be replaced to transition to a new IP-based system integrated with fire alarm, nurse call and VoIP systems where applicable. The work must be conducted per VA specifications and with minimal space disruption.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--Update PA System, newest first.
File Type Posted
Bid Opening Attendance 12-13-23.pdf PDF
36C24624B0001 0005.docx DOCX document
Bid Abstract - 36C24624B0001.pdf PDF
36C24624B0001 0004.docx DOCX document
Revised 659-22-201 Drawings 12-7-23.pdf PDF
36C24624B0001 0003.docx DOCX document
36C24624B0001 0001.docx DOCX document
S02 - Revised 659-22-201 Specifications 10-27-23.pdf PDF
36C24624B0001_1.docx DOCX document
S02 - Revised 659-22-201 Drawings 10-27-23.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 11-1 -2023 659-22-201 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 To all Offerors/Bidders

36C24624B0001 11-08-2023

X X X

X one (1) The purpose of this amendment is to include additional information to the Statement of Work:

1. The following language is hereby added to the bottom of the Statement of Work:

"The vendor has responsibility for “Duty to Report” any fraud, waste, and abuse witnessed while on VA premises to the Integrity and Compliance Officer."

STATEMENT OF WORK

SCOPE OF WORK:

The Salisbury VAMC would like to expand and upgrade their existing Public Address (PA) System within numerous buildings across their campus. Currently, about 21 buildings have existing paging speakers and cabling that will be re-used. Cable pathways that serve the building’s PA system equipment is routed through a campus wide network of tunnels and manholes.

In support of the addition of a PA system in buildings 13, 14W, 14E, 15, 16, 17, and 18, existing gypsum board ceilings, acoustic ceiling panels, and other finished concealed locations shall be removed to allow for the installation of the new infrastructure. The existing gypsum board ceilings, acoustic ceiling panels, and other finishes removed shall be patched to match existing.

The buildings below have existing paging speakers and cabling that will be re-used:

· Building 1: Administrations Building

· Building 2: G. M & S Building

· Building 3, Outpatient Clinics

· Building 4: Patient Treatment (Mental Health)

· Building 5: Main Kitchen

· Building 6: Recreation Building

· Building 7: R.M.S. & Core Clinic Building

· Building 8: Patient Treatment (Mental Health)

· Building 11, 11A, 11B, 11C: Mental Health Offices

· Building 12: Police Headquarters

· Building 19: Chapel

· Building 20: Laboratory Buildings

· Building 21: Endoscope, Podiatry, Oncology, Sleep Clinic

· Building 21A: Fee Basic

· Building 21B: Engineering

· Building 31: Chiller Plant

· Building 42: Gero-Psychiatric Building

· Building 43: Hospices Building

Buildings that do not have a paging system and will require new systems are identified below:

· Building 9: Parking Garage

· Building 13: Student Lodging

· Building 14W: W Duplex Quarters

· Building 14E: E Duplex Quarters

· Building 15: Visin

· Building 16: Laundry

· Building 17: Warehouse

· Building 18: Boiler Plant

· Building 28: Paint Booth

Of the buildings that have an existing PA system, eight are fed from other buildings on campus. See below for the locations of source PA equipment and the buildings that they serve:

· Building 4 serves Building 8. Building 8 will require new control equipment, but no amplifier.

· Building 8 has amplified speakers that are existing to remain.

· Building 11 serves Buildings 11A, B, and C. This configuration is to remain.

· Building 2 serves Building 20. Building 20 will require new headend equipment.

· Building 21 serves building 21A and 21B. This configuration is to remain.

· Building 42 serves Building 43. Building 42 will serve 43 with a new dedicated amplifier for building 43 speakers only.

EXISTING CONDITIONS:

Copper cabling is routed from the main campus’ backbone, which appears to be within Building 5, to each building’s PA system head end equipment. Downstream of the head in equipment, shielded cabling is used to interconnect amplifiers, speaker and rack mounted equipment via conduit, cable tray or j-hooks.

PROJECT REQUIREMENTS:

The goal of this project will be the installation of new paging equipment and campus wide network infrastructure to support the PA System. Network infrastructure will consist of single-mode fiber ran between equipment locations. New fiber will be routed in new conduit within existing tunnel systems to serve each building’s new PA Head End Equipment which will, in turn, provide service downstream to new and existing speakers. New direct buried conduit will be provided in areas where there are no existing tunnel systems. Buildings that currently don’t have a PA system will receive new equipment consisting of amplifiers, mixers, speakers in corridors, volume controls, rack mounted or wall mounted cabinets, and associated wiring. The main system will include UPS of battery backup to allow normal operation and function in the event of loss or fluctuations in power for a minimum of 2 hrs.

The new PA System will utilize zoning to allow isolated communication to the specific areas as necessary or to allow campus wide messaging when desired. The system will have volume control by zone. Each building where there are current integrations of Fire Alarm, Nurse Call and VoIP systems will continue to be fully integrated in the new system. In buildings where there is no existing Nurse Call, they will not be integrated as a part of this project scope. However, with an IP PA System the integration will be much easier for future systems or buildings with existing Nurse Call Systems even if they are not currently integrated. All PA Head End Units would be replaced as a part of this work. Multi-button microphone stations will be included in Building 12 (Police Headquarters) and Building 21 (specialty Clinics) for capability to call upon separate zones.

Per the VA Telecommunications and Special Telecommunications Systems Design Manual, the PA System has been identified as an emergency communications system and performs the Primary Facility NFPA Life Safety Code Blue Team Notification. PA System Head End equipment will be located in existing Telecom Room closets. The PA System will be remote controlled and operated in accordance with VA standards. Existing receptacles on the emergency power systems will serve the new PA equipment.

Existing analog speakers will be used with new IP system head ends utilizing a network audio bridge. Reusing existing speakers will not allow for re-zoning of paging speakers in those areas of the VAMC. New speakers will be IP speakers connected via daisy chain and CAT6A cabling. Digital systems do not require End of Line resistors in the same manner as analog systems. New equipment racks and switches will be added as necessary to support the new IP equipment.

Construction will be done IAW; VA specifications, Design guides, Infection Control guidelines and all applicable codes. Construction will also be structured to require minimum interruption of space function during construction.

The vendor has responsibility for “Duty to Report” any fraud, waste, and abuse witnessed while on VA premises to the Integrity and Compliance Officer.