Copy of B17AC RFI responses.xlsx
XLSX spreadsheet 22 KB Posted
- Solicitation number
- 36C24621R0126
About this file
This document contains a request for information (RFI) log and correspondence related to a federal contract opportunity to provide heating, ventilation and air conditioning (HVAC) installation and insulation services at two buildings on the Salisbury VA Medical Center campus in North Carolina. Key details include:
-
The scope of work involves adding insulation and HVAC units to Buildings 17A and 17C to provide reliable climate control for medical supply storage due to increased needs during the Covid-19 pandemic.
-
The estimated construction value is between $500,000 and $1,000,000. The North American Industry Classification System (NAICS) code is 236220 for commercial and institutional building construction.
-
The anticipated solicitation will be a total service-disabled veteran-owned small business set-aside. The solicitation is expected to be released on or around September 3, 2021 via www.sam.gov.
-
Questions must be directed only to the contracting officer via email. The pre-proposal site visit log, drawings and specifications are available on SAM.gov. Procore project management software is acceptable for use on this project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PICS.pdf | ||
| 36C24621R0126 0001_13.docx | DOCX document | |
| 36C24621R0126 0001_11.docx | DOCX document | |
| SITE VISIT SIGN IN SHEET .pdf | ||
| 36C24621R0126 0001_9.docx | DOCX document | |
| 36C24621R0126 0001_7.pdf | ||
| 4571 - 2021-05-20 100 percent Deliverable - Specs (1).pdf | ||
| 4571 - 100 percent CD Drawings 2021-05-20.pdf | ||
| 36C24621R0126 0001_4.pdf | ||
| 36C24621R0126 0001_5.docx | DOCX document | |
| 36C24621R0126.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFIs
| RFI LOG | CE 4571 | ||||||
| Project Name: VAMC Salisbury Service to Bldg. 17 A&C HVAC | Project Manager: ESM - Esther Moallen | ||||||
| Note for RFI responses below: Status column indicates VA or A/E responded. General questions abut Contracting administration/procedure should be emailed directly to the CO. | |||||||
| ITEM NO. | INFORMATION REQUESTED | RESPONSIBLE PARTY | DATE | ||||
| REQUESTED | DATE | ||||||
| COMPLETED | DISCIPLINE | STATUS | NOTES | ||||
| 1 | Per the Technical capability requirement, (only) one person is required on the site as project superintendent/SSHO. Please verify this statement is correct. | VA | 9/30/2021 | VA response | Correct; one overall Site Supt is required, as "Competent Person" who can also be SSHO. Site Supt must be employed directly by the selected GC; i.e. cannot be a subcontractor employee. | ||
| 2 | Has the building been tested for the presence of any hazardous materials (lead paint/ACM)? Provide reports if available. | VA | 9/30/2021 | VA response | No tests have been performed. The bldgs were erected circa 2012. No hazardous materials are anticipated however. | ||
| 3 | Confirm that the VA will provide temporary power available for GC trailer with understanding that GC will be responsible for connection / disconnection. | VA | 9/30/2021 | VA response | We should be able to arrange this from one of the storage bldgs or Bldg 18 however it would be affected anytime the power is cut to that bldg. | ||
| 4 | Will the VA provide document shared on virtual pre-bid meeting? | VA | 9/30/2021 | VA response | We can send out the photos and drawings via email as needed. Please request via CO Mark Griffith as the COR will change soon. | ||
| 5 | Issue the site sign-in sheet from the virtual pre-bid meeting. | VA | 9/30/2021 | ||||
| 6 | • Bid items and Alternates clarification: |
o Are all alternates cumulative?
o Is Coiling Door an additive alternate or deductive alternate? Solicitation and drawings are contradicting.
VA/CE 9/30/2021 A/E response Alternates are intended to be accepted individually.
Coiling door is a deductive alternate.
| 7 | Provide details for the electrical duct bank, sectional drawing and preferred route. | CE | 9/30/2021 | A/E response | Refer to specification section 230541 Underground Electrical Construction. Preferred route is shown on Sheet ES100. |
| 8 | Project scope calls for providing R-19 in the exterior and roof. What is the existing condition of the exterior walls and roof? Provide as built details. Are we tearing off internal drywall to have insulation in between stud spaces or is there no drywall on the inside of the exterior wall? | CE | 9/30/2021 | A/E response | Building 17A is a Metallic brand metal building. There is no insulation or drywall in the Warehouse. There is spray foam insulation around the Storage room as well as drywall on the interor walls of Storage. |
Building 17C is a Kirby brand metal building. This building is insulated and in good shape.
| 9 | Sheet G100: Demolition note 1: Clarify drywall requirements for installation | CE | 9/30/2021 | A/E response | Drywall is not required. The intent would be exposed insulation with jacket on the interior. |
| 10 | Sheet G100: Demolition note 2: Clarify what is extent repair of insulation, Building 17C | CE | 9/30/2021 | A/E response | See response to item 8. There is approximately a 6'x4' patch in the ceiling that requires repair. There are some locations along the seams that may require repair as well. |
| 11 | Sheet G100: New work note 5: Provide door specification for insulation requirements, door hardware (electrical or chain fall). Are there windows. What are mounting details | CE | 9/30/2021 | A/E response | Provide standard insulated door and mounting details. Door shall have a standard lift. Door shall be motor operated. Windows are not required. |
| 12 | Sheet G100: Demolition note 1 / New work 1, building 17A: Walls between Warehouse 100 / Emer Storage 101. |
o What is wall stud size and will R-19 insulation work?
| o What is wall total height? | CE | 9/30/2021 | A/E response | Studs are 4" depth. Walls are approximately 15' high. | ||||
| 13 | Sheet G100: Will spray foam insulation be acceptable as an alternate for the installation of R-19 batt insulation in building 17A. Spray foam will have a higher R value and may eliminate the need for drywall coverage | CE | 9/30/2021 | A/E response | No. Follow specification. Dry wall is not required. | |||
| 14 | Sheet G100: Can treated plywood be installed rather than installing drywall over R-19 batt insulation? | CE | 9/30/2021 | A/E response | Interior finish shall be exposed insulation with jacket. | |||
| 15 | Sheet G100: Are all walls to be painted? | CE | 9/30/2021 | A/E response | No | |||
| 16 | Sheet MH100: Provide mounting elevation for all new interior ductwork buildings 17A and 17C? | CE | 9/30/2021 | A/E response | Install ductwork as high as possible without conflict with structural members. | |||
| 17 | Sheet MH100: Provide wall penetration detail and requirements of new penetration for new exterior duct penetration buildings 17A and 17C | CE | 9/30/2021 | A/E response | Frame peneteration opening with metal studs. Where metal sheathing is cut, provide bent metal flashing. | |||
| 18 | Sheet MH100: Provide transfer grille mounting elevations buildings 17A and 17C | CE | 9/30/2021 | A/E response | Install transfer grille 12' above finished floor. | |||
| 19 | Sheet MH100: Provide supply air diffuser grilles for angle of duct. | CE | 9/30/2021 | A/E response | Grilles indicated are side discharge. | |||
| 20 | Amendment 1 stated that drawings and specifications were to be included. There were no drawings or spec attacments. When will these files be released? | VA response | These have since been re-posted to SAMS. However they can also be emailed upon request. | |||||
| 21 | Will the owner accept the use of the industry leading Procore Project Management software as the primary submittal and data tracking tool for this project? | VA response | Yes. Procore is acceptable. Authorized viewers/users must include any VA staff as (or if) requested by the CO or COR. | |||||
| 22 | Where will the designated parking & laydown area be for workers accessing the construction site? | VA response | The grassy area across the road (Bldg 16 large yard) may be used, as well as the area behind the red storage bldgs. Some VA parking will have to shift to the lot on the lower side of Bldg 16 which will free up asphalt area(s) imeeddiately in front of the red bldgs. | |||||
| 23 | We anticipate certain construction activities to generate high levels of noise. Please confirm that only the Contracting Officer can | |||||||
| suspend work via written notification to the Contractor. | VA response | We do not anticipate noise issues given the location. However, any appropriate VA leadership (COR, Safety, VA Police) may request temporary noise mitigation. Such requests from unfamiliar staff should be comunicated immediately to the COR or Engineering in Bldg 21B. It is correct that only the CO can formally suspend work. Note: a life threatening situation or extreme Safety violation may be an immediate "halt work" situation. | ||||||
| 24 | Site drawing ES-100 does not reflect existing conditions. Building 17A,B,C are fronted with asphalt paving. Building 17C is wrapped with asphalt paving. ES-100 calls for electrical line from building 16 | |||||||
| to new generator behind 17B. There is approximately up to 200LF of asphalt paving where electrical line will be installed. There are two methods for installation of the electrical line. (1) open cut/trench with asphalt repair and (2) directional boring. There are cost benefits with open/trench cut with asphalt repair. There is an additive cost associated with directional underground boring with a benefit of having no asphalt patch / repair appearance. Which method shall we include in our proposals that will benefit the government/VA facility? | VA response | Bidders may provide both options for comparison; neither option is excluded. Boring/directional boring has been used successfully on campus before. We suggest including a time comparison between the two as well. | ||||||
| 25 | There are bus charging stations at building 17C exterior. Will these charging stations be active during construction? If yes, how shall we proceed when the charging buses are in our way and within the limits of our work? | VA response | VA will move the busses during work in that area. Given the outlet location, it may be feasible to pull busses forward enough to continue charging during the day (or with electrical extension cord). The busses may have to access the outlets at night however. This will be coordiated but should not impede the project. | |||||
| 26 | Drawing PS-100 calls for 3/4" chilled water line run from building 18 | |||||||
| to building 17C. The drawing shows the lines run through the existing former tank foundations. Can the lines be routed around the tank foundations and limit adding cost to demo existing concrete tank foundations. | VA response | If the foundations prove to be an obstacle , the CW can be routed around. We do not desire demo of the tank foundations. | ||||||
| 27 | Drawing PS-100 and ES-100 show underground electrical and plumbing lines to be installed. The drawings do not show existing underground conditions. Are there existing underground utilities such as gas, electrical, sanitary sewer, or drainage in the area? Has this been confirmed? If not, are contractors to include underground utility location cost in proposals? | VA response | VA has only old and incomplete drawings from prior to the red storage barns; these will be provided. VA will research storm drain and sanitary sewer as well. Locate services can be included as a line (deduct) item in proposals. | |||||
| 28 | On the site walk it was noted that building 17A and C VA have |
rotating stock material and is in continuous movement in and out of
| the buildings. During construction, will the VA relocate the stock material to another building? If no, how shall contractors perform the work around the rotating stock material? | VA response | As mentioned in the site walk, proposals can include a line item for a possible CONEX type storage unit for temporary placement of stock. However, VA Logistics inventory manager has since indicated willingness to have VA staff forklift material from side to side as needed for inside work; on dry days, stock may be moved forklifted imeddiately outside onto the asphalt and returned inside at close of business. (Note that the operator will not be at the contractors disposal continuously during the day). The contractor has permission to move smaller items by hand as needed. | ||||
| 29 | ||||||
| 30 | ||||||
| 31 | Instructions to bid paragraph 2.6C "The bid amount of bid guarantee shall be percent of bid price or , whichever is less. What's is | |||||
| the bid bond percentage? | 9/28/2021 | CS response | 20% | |||
| 32 | Amendment 1 states all correspondence shall be sent to Mark Griffin. Does this include RFI's? | 9/28/2021 | CS response | Yes | ||
| 33 | Page set up for proposal. Is there a preferred font style we are to use? None is stated. | 9/28/2021 | CS response | (a) A page is defined as one side of sheet, 8 1/2″ × 11″, with at least one inch margins on all sides, using not smaller than 12 point type. Foldouts count as an equivalent number of 8 1/2″ × 11″ pages. The metric standard format most closely approximating the described standard 8 1/2″ × 11″ size may also be used. Other limitations/instructions identified as follows: (fill-in, if there are other limitations/instructions). |
(b) Identify any exclusions to the page limits that are excluded from the page counts specified in paragraph (a) of this provision (e.g. title pages, table of contents) as follows: (fill-in). In addition, the Cost section of your proposal is not page limited. However, this section is to be strictly limited to cost and price information. Information that can be construed as belonging in one of the other sections of the proposal will be so construed and counted against that section's page limitation.
(c) If final proposal revisions are requested, separate page limitations will be specified in the Government's request for that submission.
(d) Pages submitted in excess of the limitations specified in this provision will not be evaluated by the Government and will be returned to the offeror.
| 34 | Is there a page limit for the proposal for Factor Part 1, part 2? | 9/28/2021 | CS response | see answer to question 33 | ||
| 35 | Is there a page limit for the entire proposal? | 9/28/2021 | see answer to question 33 | |||
| 36 | For proposal email submittal, are there any delivery requirements such as file size or file type? | 9/28/2021 | Server capacity is 10MB for file attachments, per email. | |||
| 37 | Per Amendment 1, all correspondence is sent to Contract Specialist Mark Griffin, does this include the actual emailed proposal? | 9/28/2021 | Yes | |||
| 38 | Amendment 1 stated that drawings and specifications were to be included. There were no drawings or spec attachments. When will these files be released? | 9/28/2021 | currently on SAM.gov | |||
| 39 | Are RFI's to be submitted on a VA preformatted RFI form? Is yes, please provide. | 9/28/2021 | RFIs were submitted via email no special form | |||
| 40 | Will the owner accept the use of the industry leading Procore Project Management software as the primary submittal and data | |||||
| tracking tool for this project? | 9/28/2021 | Yes | ||||
| 41 | As a result of the effect of COVID-19 throughout the U.S., and the resulting Federal, State and local governments’ responses /requirements of safe distancing and potential advocations of working remotely and/or complete organization closures, please advise how the Government intends to address delays resulting there as it pertains to the current solicitation schedule for this and all future projects. | 9/28/2021 | The Government's response to delays caused by the COVID-19 pandemic will be dealt with on a case by case basis. | |||
| 42 | Is this project tax exempt, and will the CO/COR provide the necessary tax exempt certificates | 9/28/2021 | No | |||
| 43 | After award, the Contracting Officer will provide a NTP to the awardee .What is the approximant duration between issuing the award | |||||
| and issuing the NTP? | 9/28/2021 | within 15 days of award | ||||
| 44 | For planning the preliminary project schedule, what is the anticipated award date? | 9/28/2021 | With in 90 days of receipt of proposals | |||
| 45 | What is the anticipated duration between issuance of contract award and issuance of the NTP? | 9/28/2021 | That will be based on the date of the pre construction meeting. Could be between 5 to 30 days. | |||
| 46 | How many calendar days should be included in the critical-path schedule for owner and A/E review and respond to RFIs? | 9/28/2021 | RFI period is up. Questions about the project can be asked at anytime during the project. | |||
| 47 | How many calendar days should be included in the critical-path method schedule for owner and A/E submittal review? | 9/28/2021 | 5 days | |||
| 48 | ||||||
| 49 | ||||||
| 50 | ||||||
| END OF LIST | ||||||
| ** To insert additional rows, highlight the entire row (or rows), right click, and select "insert". Select the row immediately above the newly inserted row(s), and drag down to copy cell formatting. |