This file contains Request for Information (RFI) documents and pre-bid questions for a Department of Veterans Affairs (VA) construction project at the Clarksburg, WV VA Medical Center. The project involves constructing a mobile imaging pad, including interior utility connections, electrical routing, and site preparation. Key details include a bid due date of January 21, 2026, located in Huntington, WV, with a requirement for a West Virginia state contractor's license. The project involves specific technical requirements such as ICRA (Infection Control Risk Assessment) compliance, utility connections, and precise construction specifications for asphalt pavement, site fencing, and interior conduit installation.
The solicitation requires careful coordination with VA staff, including 21-day notification for major electrical interruptions and 15-day notification for water and waste interruptions. Notable technical specifications include a modified asphalt pavement section of 2.5" HMA Base Course and 1.5" HMA Wearing Course, use of HEPA carts for infection control during interior work, and strict staffing requirements for roles such as Site Safety and Health Officer (SSHO). The project scope encompasses utility connections, ceiling modifications, and site preparation, with an emphasis on minimal disruption to the existing hospital operations and adherence to VA construction standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Abstract Bids.pdf | ||
| 36C24526B0002 0004.docx | DOCX document | |
| 36C24526B0002 0003.docx | DOCX document | |
| 36C24526B0002 0002.docx | DOCX document | |
| 010000-GENERAL REQUIREMENTS Mobile Pad.pdf | ||
| 540-24-104 Clarksburg Mobile Pad - Bid Set Drawings-R1.pdf | ||
| Record of Attendance - Site Visit - Mobile Imaging Pad - 12-2-2025.pdf | ||
| 36C24526B0002 0001.docx | DOCX document | |
| 36C24526B0002_1 Final Copy 2.docx | DOCX document | |
| 540-24-104 Clarksburg Mobile Pad - Bid Set Specs - Copy.pdf | ||
| SAM Mobile Pad WD - Copy.pdf | ||
| VHA PCRA- Mobile Equipment Pad - AD signed - Copy.pdf | ||
| ICRA Mobile Pad- Interior Work-Signed - Copy.pdf | ||
| 36C24526B0002_1.docx | DOCX document | |
| 540-24-104 Clarksburg Mobile Pad - Bid Set Drawings - Copy.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Document Instance | Document Title | Question Number | Question | Response | |
| A | "Construct Mobile Imaging Pad RFIs" Word | RFI-001 – On-Site Staffing Roles | Please confirm whether one representative is allowed to serve as Project Manager, Superintendent, and SSHO on this project, provided that person meets all qualification and training requirements in Section 01 35 26 and related staffing sections. | Awarded contractor is required to follow specifcations as written. | |
| A | "Construct Mobile Imaging Pad RFIs" Word | RFI-002 – Interior Electrical Routing and ICRA Class | Please confirm that minor field adjustments to conduit routing within the same corridors shown on the drawings are acceptable to avoid existing utilities. | ||
| Also confirm the required ICRA class for the third-floor mechanical room, associated corridors, and basement mechanical room along this interior electrical route. | Field modifications will be acceptable pending review of shop drawings and requirements set forth in specificaitons. | ||||
| A | "Construct Mobile Imaging Pad RFIs" Word | RFI-003 | Please identify the exact points of connection (POCs) inside the existing building for all services feeding the mobile imaging unit, including Electrical (panel IDs, breaker sizes, and locations), Mechanical (systems or equipment to which we are connecting), and Plumbing (domestic water and sanitary mains, pipe sizes, and locations). | Contractor needs to review P series and E series sheets. | |
| A | "Construct Mobile Imaging Pad RFIs" Word | RFI-004 | Please also confirm whether these existing systems at the identified POCs have been verified to have sufficient spare capacity to serve the mobile imaging unit as designed. | Contractor needs to review P series and E series sheets. | |
| B | "RFIs Imaging Pad" | 1 | Please confirm the address for the bid delivery on the due date. | FMS Building 8 1540 Spring Valley Drive, Huntington, WV 25704 | |
| B | "RFIs Imaging Pad" | 2 | Can the due date please be extended by at least 14 days to allow contractors time to review RFI responses and complete pricing? | The bid due date has been extended until 1/21/2026. | |
| B | "RFIs Imaging Pad" | 3 | Please clarify the exact allowed working hours for interior utility connections, and whether the VA anticipates granting any exceptions for daytime work. | See GI002 pricing note 2. Day time work will only be acceptable at Vas discression depending on actual construction schedule. | |
| B | "RFIs Imaging Pad" | 4 | Please confirm whether an ICRA permit is required for exterior pad construction tasks or only for interior utility connection tasks. | ICRA is specific to interior construction. Contractor is still responsible for a temporary environmental controls and safety requiremetns listed in specifications. | |
| B | "RFIs Imaging Pad" | 5 | Does the VA require a CP on site during all off-hours work, including short-duration tasks (testing, tie-ins), or can CP coverage be delegated under certain conditions? | A competent person will have to be onsite regardless of the shift or duration of the project. An alternate CP can be listed in the safety submittal when listing personnel. | |
| B | "RFIs Imaging Pad" | 6 | Please confirm whether the VA will provide any additional as-built information or utility locating support beyond MISS UTILITY 811. Also confirm if additional test pits must be paid under base bid or will be treated as differing site conditions. | Known utility location in area of work is shown on XP101 and civil drawings. Contractor is responsible for locating utilities as indicated on drawings. Test pits are not anticipated to be requried but the contractor is not alleviated from work required to identify utilies and advising the VA if they differ from what is shown on plans. | |
| B | "RFIs Imaging Pad" | 7 | Please clarify whether geotechnical reports exist for this location, and whether remediation of unforeseen subsurface conditions (rock, unsuitable soils) will be handled as a change order. | Geotech report is available and can be provided for reference only. The contractor is responsible for determining if this is sufficient information to undestand existing conditions or if additional boring should be included in the bid effort. See Specification 01 00 00 section 1.11. | |
| B | "RFIs Imaging Pad" | 8 | Please confirm the trailer model, maximum loads, connection requirements, and any vibration criteria needed to ensure pad design compatibility. | No tratiler is installed as part of this project (listed as not in contract on plans). Scope is to make provisions for the facility if a trailer is ever required to support medical functions. | |
| B | "RFIs Imaging Pad" | 9 | Please confirm rebar grade, lap splice requirements, and concrete design strengths for all pad and foundation elements. | See structural drawings | |
| B | "RFIs Imaging Pad" | 10 | Please confirm required shutdown notification window, allowed shutdown hours, and whether VA engineering staff must be present during connections and flushing. | 21 days for major interruptions - Electrical |
15 days for minor interruptions - water and waste All must be coordinated with VA
| B | "RFIs Imaging Pad" | 11 | Please confirm whether the VA or the contractor pays laboratory fees for required potable water testing. | Contractor shall be responsible for all testing listed in construction documents and specifications |
| B | "RFIs Imaging Pad" | 12 | Please confirm amperage, voltage, grounding, and connection method for the future imaging trailer so conduit and feeders can be sized accurately. | See sheet E-601. |
| B | "RFIs Imaging Pad" | 13 | Please provide a definitive routing path and clarify whether ceiling removal beyond “one tile per 50 sq ft” is permitted for conduit installation. | See sheets E-101 through E-601. |
| B | "RFIs Imaging Pad" | 14 | Please confirm whether the VA will supply required baseline air particulate readings or if the contractor must hire an environmental testing service. | Contractor shall be responsible for all testing required. |
| B | "RFIs Imaging Pad" | 15 | Please confirm the approving authority and whether VA has already coordinated preliminary sewer capacity acceptance. | There are no additional tie ins to site sewer. Drain line for mobile pad is tying into building. |
| B | "RFIs Imaging Pad" | 16 | Please provide invert elevations and distances to verify feasibility without excessive regrading. | See sheets CS101 and P-102. |
| C | "RFIs Mobile" | 1 | Please confirm whether a State of West Virginia Contractor’s License is required to bid on this project and perform the work. | Yes, a state of West Virginia contractors license is required to perform work. |
| C | "RFIs Mobile" | 2 | Can the Superintendent also serve in the roles of Quality Control Manager and Site Safety and Health Officer? | Awarded contractor is required to follow specifcations as written. |
| C | "RFIs Mobile" | 3 | If the Superintendent cannot serve in those roles, may any of these positions be dual-hatted? | Awarded contractor is required to follow specifcations as written. |
| C | "RFIs Mobile" | 4 | We respectfully request clarification regarding the asphalt pavement requirements outlined in the specifications. The current documents indicate 6 inches of aggregate base and 3 inches of wearing surface. |
For reference, typical parking lot pavement sections generally consist of a minimum of 2 ½ inches of binder course and 1 ½ inches of wearing (surface) course, with heavier sections sometimes specified depending on traffic type and volume.
To ensure proper alignment with project intent and existing conditions, could you please confirm:
• Whether the specified section (6" aggregate base + 3" wearing surface) is the intended design requirement, or if a binder course is expected in addition to the wearing surface.
| • | What the existing pavement section is, so that the new construction can at least match or appropriately tie into the current structure. | Confirmed detail on CI501 will be modified as follows: The asphalt should be 2.5” HMA Base Course and 1.5” HMA Wearing Course. See revised plans | ||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 1 | The bid due date on the SF1442 is 12/31/2025 at 1:00 p.m. | |
| Question: Will the bid date remain the same as this is New Year’s Eve and bids are to be hand delivered or mailed? | The bid opening has been extended until 1/21/2026 | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 2 | The bid opening location on the SF1442 states it is Huntington, WV. | |
| Question: Will the bid opening location remain the same as the project is in Clarksburg, WV? | The bid opening will be in Huntington, WV. | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | Specification Section 01-00-00-1.06.K states Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom offences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR. | ||
| Question: It has been our experience that when fence fabric is utilized, it can allow the fence to be more susceptible to movement during high wind timeframes. With this being so close to the parking area where there will be vehicular traffic and parking, can the winning contractor forego adding the fence fabric to the construction fencing? | Contractor is to follow details on GC101 for site fence construction. | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 3 | Specification section 01-00-00-M.2 states contractor must submit a notice of interruption 7 days in advance of proposed interruptions. |
Specification section 01-00-00-M.4 states contractor must submit a notice of major interruption 15 days in advance of proposed interruptions.
Drawing CL-001 Construction Notes# 17 states contractor must submit a notice of planned interruptions to COR and CO 21 days in advance.
Drawing CL-001 Construction Notes# 21 states contractor must coordinate temporary interruptions with VAMC staff days prior.
Question: Can clarifications be provided as to what notifications are required / needed as per the timeline? 21 days for major interruptions - Electrical 15 days for minor interruptions - water and waste All must be coordinated with VA
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 4 | Question: Is the mechanical room Drawing #P102 Detail #3 labeled Mech Room B029 actually Mechanical Room B106 as indicated on drawing AD101? | |
| Question: If not, where do the new sanitary and water lines mentioned on drawing SS- 101 get tied-in? | Confirmed it is room B106, next to stair B105. | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 5 | Drawing AD111 has a Removal Key Note #R2 and it states: REMOVE PORTION OF CEILING, CEILING DEVICES/FIXTURE & DUCTWORK AS NECESSARY TO FACILITATE THE INSTALLATION OF CONDUIT. RETAIN FOR REINSTALLATION WITH RENOVATION WORK. EXACT ROUTE TO BE DETERMINED IN THE FIELD. COORDINATE LOCATION FOR REMOVAL WITH ELECTRICAL Question: Can ceiling and above ceiling pictures be provided for Corridors #104, 105, and #112 as identified for the conduit routing? |
Question: Are the ceilings referenced, gypsum board or ACT material?
Question: Is this work required to be performed during afterhours and weekends? Contractor to coordinate with VA if additional pre demolition site investigations are required to observe conduit routing path.
Ceiling material is understood to be gypsum board, contractor shall verify.
See GI001 Pricing Notes.
D "Construct Mobile Imaging Pad Pre-Bid RFIs" 6 Drawing GI001 Pricing Note #3 states: CONTRACTOR IS TO ASSUME THAT WORK REQUIRED TO ROUTE NEW CONDUITS WITHIN THE BUILDING SHALL
OCCUR WITHIN MOBILE HEPA CARTS FOR INFECTION CONTROL, AND ROOMS AND SPACES WILL NOT BE SHUTDOWN TO ACCOMODATE THE WORK.
| Question: Can it be confirmed HEPA carts can be utilized for this work? | HEPA cart should be assumed to be the primary use for installation and construction work. | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 7 | Drawing GI001 Pricing Note #2 states: CONTRACTOR IS TO ASSUME THAT ALL WORK WITHIN THE EXISTING HOSPITAL BUILDINGS FOR UTLITIY |
CONNECTIONS IS TO OCCUR DURING OFF HOURS AND OR WEEKENDS.
| Question: Can it be confirmed if this is in reference to the tie-in of the utility connections or does it also include all work above the ceiling in the corridors (i.e. installation of conduit, ceiling devices / fixtures & ductwork) as well? | This applies to all work inside of the hospital | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 8 | Drawing GI001 Pricing Note #2 states: CONTRACTOR IS TO ASSUME THAT ALL |
WORK WITHIN THE EXISTING HOSPITAL BUILDINGS FOR UTLITIY
CONNECTIONS IS TO OCCUR DURING OFF HOURS AND OR WEEKENDS.
| Question: Can it be confirmed if this is in reference to the tie-in of the utility connections or does it also include all work above the ceiling in the corridors (i.e. installation of conduit, ceiling devices / fixtures & ductwork) as well? | This applies to all work inside of the hospital | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 9 | Specification Section 01 00 00 1.24 details requirements for photographic documentation. |
| Question: Is a commercial photographer required for this project? | Not as long as the requirements in the specification are followed. | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 10 | Specification Section 01 35 26 1.09 requires a full-time SSHO with no additional duties. |
| Question: Can you please confirm that a full-time SSHO is required and this role is not permitted to be filled by the superintendent. | Spec should be followed as written. | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 11 | Spec 01 45 00 3.04B states that the superintendent is permitted to have additional duties as CQC Manager. |
| Question: Can you please confirm that this is acceptable? | Spec should be followed as written. | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 12 | Drawing GC101 Note #3 states: NO PERMITS ARE EXPECTED DUE TO THE MINIMAL DISTURBANCE. IN THE EVENT IT IS REQUIRED, THE |
CONTRACTOR SHALL, WITHIN 72 HOURS OF FILING AN APPLICATION WITH THE WVDEP DIVISION OF WATER AND WASTE MANAGEMENT (DWWM), INSTALL PUBLIC NOTICE SIGN NEAR THE ENTRANCE OF THE PROJECT OR, NEAR AN ACTIVE PART OF THE CONSTRUCTION PROJECT, THAT IS
ACCESSIBLE BY THE PUBLIC. THE PUBLIC NOTICE SIGN MUST REMAIN DISPLAYED FOR THE DURATION OF THE PROJECT.
Specification section 01-00-00-1.09.D states: Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge Elimination System (NPDES) permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices.
Question: Can you please clarify if a NPDES permit is required for this project required?
Question: For Bidding purposes, what is the cost of this permit?
| Question: For Bidding purposes, can this amount be carried as an allowance to ensure equal pricing amongst bidders for this scope? | NDPES permit does not appear to be required by State of WV given limited area of disturbance (< 1 acre). Spec section will be updated to remove requirement | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 13 | Drawing GC101 Phase 1 Note 9 states ESTABLISH SOIL STOCKPILES AND |
PROTECT WITH SILT FENCE. STRIP AND STOCKPILE TOPSOIL TO USE IN THE FINISH GRADING OPERATIONS. STOCKPILES SHALL BE SEEDED AND
MULCHED IF THEY ARE TO REMAIN UNDISTURBED FOR 14 DAYS OR LONGER.
Drawing GC101 General Note states: THE SITE HAS LIMITED SPACE AND DOES NOT HAVE ROOM FOR EXCAVATED/WASTE MATERIALS. THE
CONTRACTOR SHALL REMOVE THIS MATERIAL IMMEDIATELY. SPACE HAS BEEN PROVIDED FOR STAGING OF NEW MATERIALS.
| Question: This seems to be a contradiction. Can you please clarify if the contractor can stockpile the topsoil or if needs to be removed from site as well? | Contractor can propose stockpile areas if they find an area suitable to the VA, otherwise the assumption should be that materials should be removed. | ||||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 14 | Drawing CS102 is titled Mobile Trailer Decommission Plan (Not in Contract). | ||
| Question: Can you please confirm that none of the scope of work on this drawing is to be included in the bid? | Drawings will be revised to confirm that parking lot should be striped. CS101 will be revised to indicate this. CS102 indicates a future condition in which a mobile trailer will be installed; confirmed that no mobile trailer is being installed as part of this project. | ||||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 15 | Question: Will Ground Penetrating Radar be required for the areas to be excavated for the project? | Construction documents had GPR utilized to locate utilities, but do not take responsibility for identifying all possible utilities unders the construction area. Contractor is responsible for identifying utilities before digging as indicated on plans. | |
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 16 | Drawing CI001 Construction note #5 states: Contractor must obtain applicable permit(s) before any excavation takes place. Excavations over 3’11” will require a confined space permit. |
Question: What is the cost of this permit?
| Question: What is the contractor required to provide for this permit? | Contractor is responsible for coordinating these requirements with the VA and the state depending on excavation plans. See spec 01 35 26. | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 17 | Drawing CI001 Construction Note #2 states: DEVELOPMENT OF THE SITE INCLUDING CONSTRUCTION AND MATERIALS SHALL BE IN CONFORMANCE WITH THE U.S. DEPARTMENT OF VETERANS AFFAIRS REQUIREMENTS AND THE VIRGINIA DEPARTMENT OF TRANSPORTATION CONSTRUCTION STANDARDS AND SPECIFICATIONS, WHERE APPLICABLE. |
| Question: Can you please confirm that this note should reference West Virginia Department of Transportation instead of Virginia Department of Transportation? | Confirmed it should be WV. | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 18 | Drawing CI001 Construction note #6 states: INTEGRITY FEDERAL SERVICES DOES |
NOT CERTIFY TO THE SUB-SURFACE CONDITIONS OF THE SITE, THE
LOCATION OF UNDERLYING ROCK, OR THE LOCATION OF POTENTIAL
SINKHOLES. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE DIGGING
OF TEST HOLES TO VERIFY SUB-SURFACE CONDITIONS PRIOR TO
BEGINNING ANY CONSTRUCTION. IF SINKHOLES ARE FOUND IN THE FIELD,
REMEDIATION WILL BE REQUIRED AS SPECIFIED BY A QUALIFIED
GEOTECHNICAL ENGINEERING FIRM.
| Question: Can you please confirm that this would be addressed as a change order? | Unforseen conditions can be discussed with the VA. This does not alleviate the contractors scope as outlined in the construction documents and specifications. | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 19 | Drawing CI001 Drawing #10 states: ALL LAND ON OR OFF-SITE WHICH IS DISTURBED BY CONSTRUCTION AND WHICH IS NOT BUILT UPON OR SURFACED SHALL BE ADEQUATELY STABILIZED TO CONTROL EROSION AND SEDIMENTATION. |
| Question: Can you please clarify what off-site land is being referenced to in this note? | The note does not intend to call out speciifc areas off site, just that it is the contractors responsibility to verify that all areas disturbed construction activities, including transportation to the site, are the responsibility of the contractor to verify they are adequately stabilized. | |||
| D | "Construct Mobile Imaging Pad Pre-Bid RFIs" | 20 | Drawing AG-002 is titled ICRA Assessment Notes: |
Question: What Level of ICRA is this project considered? Based on scope of work, anticipated is Level II. Final level of ICRA shall be determined by contractor in conjunction with VA.