688-24-111 Renovate Biomedical Engineering GC105 - Drawings.pdf
PDF 29 MB Posted
- Solicitation number
- 36C24524B0018
About this file
This document appears to be a Statement of Work for the renovation of the Biomedical Engineering Suite GC105 at the Washington, DC Veterans Affairs Medical Center (VAMC). The project involves interior renovations of approximately 2,830 square feet, including selective demolition, interior framing, finishes, mechanical, electrical, and plumbing work. Key details include:
The contract duration is 150 calendar days from the Notice to Proceed. Required deliverables include daily reports, status reports, project schedules, submittals, construction photos, and as-built drawings. The contractor must comply with safety, security, and abatement requirements, including maintaining existing systems during construction. Asbestos abatement is a requirement, and the contractor must submit an abatement plan. The contractor is responsible for coordinating with the Contracting Officer's Representative and other facility personnel. The Solicitation Number is 36C24524B0018, and the Contracting Officer is Liana J. Holland.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24524B0018 0004.docx | DOCX document | |
| 36C24524B0018 0003.docx | DOCX document | |
| 36C24524B0018 0002.docx | DOCX document | |
| 36C24524B0018 0001.docx | DOCX document | |
| 36C24524B0018_1.docx | DOCX document | |
| 688-24-111 Renovate Biomedical Engineering GC105 - SpecificationsR2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
'-1
EQ EQ EQ
3'
4'-0" MIN.
CLEAR
BID DOCUMENTS - FOR CONSTRUCTION
INTERIOR WORK FOR THE RENOVATION OF BIOMEDICAL ENGINEERING SUITE GC105. WORK TO INCLUDE:
PARTIAL DEMOLITION OF WALLS AND CEILINGS AND CONSTRUCTION OF NEW WALLS, NEW CEILINGS, NEW FLOOR FINISHES, NEW DOORS, AND NEW MILLWORK. SCOPE OF WORK ALSO INVOLVES THE DEMOLITION AND REPLACEMENT OF EXISTING ELECTRICAL PANELS AND LIGHTING, AS WELL AS THE ADDITION OF NEW
POWER AND DATA RECEPTACLES. THE MECHANICAL SCOPE WILL INCLUDE THE DEMOLITION AND
REPLACEMENT OF EXISTING HVAC EQUIPMENT, AND SUPPLY AND RETURN FIXTURES. THERE WILL BE NEW A PLUMBING FIXTURE INSTALLED IN THE BREAK ROOM. NEW PIPING WILL BE INSTALLED TO SUPPORT THE
NEW FIXTURE.
NOT TO SCALE
AREA OF WORK
A LABEL CLASS A DOOR
A/C AIR CONDITION
A/C UNIT AIR CONDITIONING UNIT
A/E ARCHITECT/ENGINEER
AAMA AMERICAN ARCHITECTURAL
MANUFACTURERS ASSOCIATION
AB ANCHOR BOLT
AC ASBESTOS CEMENT OR ASPHALTIC
CONCRETE
ACI AMERICAN CONCRETE INSTITUTE
ACM ASBESTOS CONTAINING MATERIAL
ACT ACOUSTICAL CEILING TILE
ADA AMERICANS WITH DISABILITIES ACT
ADC AUTOMATIC DOOR CLOSER
ADDL ADDITIONAL
ADDN ADDITION
ADH ADHESIVE
ADJ ADJACENT, ADJOINING, OR
ADJUSTABLE
ADMIN ADMINISTRATION
ADB AUTOMATIC DOOR BOTTOM
AFC ABOVE FINISHED COUNTER
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
AFS ABOVE FINISHED SLAB
AHJ AUTHORITY HAVING JURISDICTION
AHR ANCHOR
AHU AIR HANDLING UNIT
AIA AMERICAN INSTITUTE OF
ARCHITECTS
AISC AMERICAN INSTITUTE OF STEEL
CONSTRUCTION
ALT ALTERNATE
ALUM ALUMINUM
AMP AMPERE
AMT AMOUNT
ANSI AMERICAN NATIONAL STANDARDS
INSTITUTE
APPD APPROVED
APPROX APPROXIMATE
ASI ARCHITECT'S SUPPLEMENTAL
INSTRUCTION
ASTM AMERICAN SOCIETY FOR TESTING
AND MATERIALS
ATM AUTOMATIC TELLER MACHINE
ATS AUTOMATIC TRANSFER SWITCH
AUTO AUTOMATIC
AUX AUXILIARY
AV AUDIO VISUAL
AWI ARCHITECTURAL WOODWORKING
INSTITUTE
B LABEL CLASS B DOOR
BD BOARD
BHMA BUILDER'S HARDWARE
MANUFACTURER'S ASSOCIATION
BLDG BUILDING
BOT BOTTOM
BSMT BASEMENT
BTWN BETWEEN
C LABEL CLASS C DOOR
C TO C CENTER TO CENTER
CAB CABINET
CAC CEILING ATTENUATION CLASS
CBB CEMENTITIOUS (BACKER) BOARD
CCTV CLOSED CIRCUIT TELEVISION
CD CONSTRUCTION DOCUMENTS OR
CONTRACT DOCUMENTS
CF CONTRACTOR FURNISHED
CF/CI CONTRACTOR
FURNISHED/CONTRACTOR INSTALLED
CF/OI CONTRACTOR FURNISHED/OWNER
INSTALLED
CFM CUBIC FEET PER MINUTE
CHK CHECK
CL CENTER LINE
CLG CEILING
CLG HT CEILING HEIGHT
CLR CLEAR
CMU CONCRETE MASONRY UNIT
CO CARBON MONOXIDE, CERTIFICATE OF
OCCUPANCY, CLEANOUT, OR
COMPANY
CO₂ CARBON DIOXIDE
COL COLUMN
COMM COMMUNICATION
CONC CONCRETE
COND CONDENSER OR CONDITION
CONF CONFERENCE
CONT CONTINUE
COORD COORDINATE
COR CONTRACTING OFFICER
REPRESENTATIVE
CORR CORRIDOR
CPM CRITICAL PATH METHOD
CPT CARPET
CSI CONSTRUCTION SPECIFICATIONS
INSTITUTE
CSMT CASEMENT
CSWK CASEWORK
CT CERAMIC TILE
CTB CERAMIC TILE BASE
CTF CERAMIC TILE FLOOR
CU FT CUBIC FEET
D LABEL CLASS D DOOR
DBL DOUBLE
DC DIRECT CURRENT
DEG DEGREE
DEL DELETE
DEMO DEMOLITION
DEPT DEPARTMENT
DET DETAIL
DF DRINKING FOUNTAIN
DIA DIAMETER
DIFF DIFFERENCE OR DIFFUSER
DIM DIMENSION
DISP DISPENSER
DIST DISTANCE
DIV DIVIDE OR DIVISION
DR DOOR, DRAIN, DRESSING ROOM, OR
DRIVE
DR CL DOOR CLOSER
DR FR DOOR FRAME
DS DOWNSPOUT
DW DISHWASHER
DWG DRAWING
E LABEL CLASS E DOOR
EA EACH
EL ELEVATION
ELEC ELECTRIC
ELEC DR OP ELECTRIC DOOR OPENER
ELEV ELEVATOR
EMER EMERGENCY
ENGR ENGINEER
EPA ENVIRONMENTAL PROTECTION
AGENCY
EQ EQUAL
EQUIP EQUIPMENT
EQUIV EQUIVALENT
ETC AND SO FORTH OR ET CETERA
EWS EYE WASH STATION
EXH EXHAUST
EXIST EXISTING
EXP EXPANSION OR EXPOSED
EXT EXTERIOR, EXTERNAL, OR
EXTINGUISHER
F FAHRENHEIT OR FEMALE
FA FIRE ALARM
FD FLOOR DRAIN
FDC FIRE DEPARTMENT CONNECTION
FE FIRE EXTINGUISHER
FEC FIRE EXTINGUISHER CABINET
FF FINISH FACE
FF EL FINISH FLOOR ELEVATION
FF&E FURNITURE, FIXTURE, AND
EQUIPMENT
FIG FIGURE
FIN FINISH
FIN FLR FINISH FLOOR
FIN GR FINISH GRADE
FIN WD FINISH WOOD
FLASH FLASHING
FLEX FLEXIBLE
FLR FLOOR
FLR FIN FLOOR FINISH
FM FACTORY MUTUAL
FM-G FACTORY MUTUAL GLOBAL
FO FINISHED OPENING
FOC FACE OF CONCRETE OR FACE OF
CURB
FOF FACE OF FINISH
FOM FACE OF MASONRY
FPM FEET PER MINUTE
FR FIRE RATING, FIRE RESISTANT, OR
FRAME
FRP FIBER REINFORCED POLYESTER OR
FIBERGLASS REINFORCED PLASTIC
FT FEET OR FOOT
FTG FOOTING
FURN FURNISH OR FURNITURE
GA GAGE OR GYPSUM ASSOCIATION
GAL GALLON
GALV GALVANIC OR GALVANIZED
GALV STL GALVANIZED STEEL
GB GRAB BAR
GC GENERAL CONTRACTOR
GL GLASS
GYP GYPSUM
GYP BD GYPSUM BOARD
GYP PLAS GYPSUM PLASTER
H HIGH
HAZ MAT HAZARDOUS MATERIALS
HB HOSE BIBB
HC HOLLOW CORE
HCWD HOLLOW CORE WOOD DOOR
HDR HEADER
HDW HARDWARE
HDWD HARDWOOD
HEPA HIGH EFFICIENCY PARTICULATE AIR
(FILTER)
HF HIGH FREQUENCY
HM HOLLOW METAL
HMD HOLLOW METAL DOOR
HMDF HOLLOW METAL DOOR AND FRAME
HMF HOLLOW METAL FRAME
HNDRL HANDRAIL
HORIZ HORIZONTAL
HP HIGH PRESSURE OR HORSEPOWER
HT HEIGHT
HVAC HEATING, VENTILATING, AND AIR
CONDITIONING
HW HOT WATER
IAQ INDOOR AIR QUALITY
IBC INTERNATIONAL BUILDING CODE
ID IDENTIFICATION, INSIDE DIAMETER,
OR INTERIOR DESIGN
ID NO IDENTIFICATION NUMBER
INFO INFORMATION
INSUL INSULATION
INT INTERIOR
INTL INTERNATIONAL
JAN JANITOR
J-BOX JUNCTION BOX
KD KILN DRIED OR KNOCKED DOWN
KIT KITCHEN
LAB LABORATORY
LAM LAMINATE
LAU LAUNDRY
LAV LAVATORY
LBS POUND
LDR LEADER
LED LIGHT EMITTING DIODE
LF LINEAR FEET (FOOT)
LH LEFT HAND
LHR LEFT HAND REVERSE
LIN LINEAR
LL LEAD LINED
LT LIGHT
LTG LIGHTING
LVR LOUVER
LYR LAYER
MATL MATERIAL
MAX MAXIMUM
MECH MECHANICAL
MEL MELAMINE
MEMB MEMBRANE
MEMO MEMORANDUM
MEZZ MEZZANINE
MF MILL FINISH
MFD MANUFACTURED
MFG MANUFACTURING
MFR MANUFACTURER
MFR REC MANUFACTURER'S
RECOMMENDATION
MIN MINIMUM MINUTE
MIN MINUTE MINIMUM
MIRR MIRROR
MISC MISCELLANEOUS
MLWK MILLWORK
MO MASONRY OPENING OR MOTOR
OPERATED
MTD MOUNTED
MTG MOUNTING
MTL METAL
N NORTH
NA NOT APPLICABLE
NATL NATIONAL
NC NOISE CRITERIA
NCOMBL NONCOMBUSTIBLE
NEC NATIONAL ELECTRICAL CODE
NEG NEGATIVE
NEMA NATIONAL ELECTRICAL
MANUFACTURERS ASSOCIATION
NFPA NATIONAL FIRE PROTECTION
ASSOCIATION
NIC NOT IN CONTRACT
NO NUMBER
NOM NOMINAL
NR NOISE REDUCTION
NRC NOISE REDUCTION COEFFICIENT
OC ON CENTER
OF/CI OWNER FURNISHED/CONTRACTOR
INSTALLED
OFF OFFICE
OF/OI OWNER FURNISHED/OWNER
INSTALLED
OH OVERHANG
OH DR OVERHEAD (COILING) DOOR
OPH OPPOSITE HAND
OPNG OPENING
OPP OPPOSITE
OPT OPTIONAL
OR OPERATING ROOM OR OUTSIDE
RADIUS
ORD ORDNANCE OR OVERFLOW ROOF
DRAIN
OSHA OCCUPATIONAL SAFETY AND HEALTH
ADMINSTRATION
PAR PARALLEL OR PARAPET
PHAR PHARMACY
PKG PACKAGE
PL PROPERTY LINE
PLAM PLASTIC LAMINATE
PLAS PLASTER OR PLASTIC
PLBG PLUMBING
PLYWD PLYWOOD
PNL PANEL
PO POST OFFICE PURCHASE ORDER
PO PURCHASE ORDER POST OFFICE
PREFAB PREFABRICATE
PRELIM PRELIMINARY
PREP PREPARATION
PRESS PRESSURE
PREV PREVIOUS
PROJ PROJECT
PTD PAPER TOWEL DISPENSER
PVC POLYVINYL CHLORIDE (PLASTIC)
PWR POWER
QA QUALITY ASSURANCE
QC QUALITY CONTROL
QTR QUARTER
QTY QUANTITY
R RADIUS OR RISER
RA RETURN AIR
RAD RADIATOR
RB RESILIENT BASE OR RUBBER BASE
RB HK ROBE HOOK
RCP REFLECTED CEILING PLAN
REC RECESSED
RECPT RECEPTACLE
REF REFERENCE OR REFRIGERATOR
REG REGISTER
REQ REQUIRE
REQD REQUIRED
RESIL RESILIENT
RET RETURN
REV REVISION
RF RADIO FREQUENCY
RFI REQUEST FOR INFORMATION
RFP REQUEST FOR PROPOSAL
RH RIGHT HAND
RHR RIGHT HAND REVERSE
RM ROOM
RO ROUGH OPENING
ROW RIGHT OF WAY
SA SUPPLY AIR
SALV SALVAGE
SAMP SAMPLE
SCHED SCHEDULE
SCWD SOLID CORE WOOD DOOR
SD SHOP DRAWINGS, SMOKE DETECTOR,
OR SOAP DISPENSER;
SECT SECTION
SF SQUARE FOOT (FEET)
SIM SIMILAR
SMK SMOKE
SND SANITARY NAPKIN DISPENSER
SNDU SANITARY NAPKIN DISPOSAL UNIT
SPEC SPECIFICATION
SPKLR SPRINKLER
SPKR SPEAKER
SPLY SUPPLY
SQ SQUARE
SQ IN SQUARE INCH
SST STAINLESS STEEL
STC SOUND TRANSMISSION CLASS
STD STANDARD
STOR STORAGE
SUB SUBSTITUTE
SURF SURFACE
SUSP SUSPEND
SUSP CLG SUSPENDED CEILING
SYM SYMBOL
SYS SYSTEM
T TREAD
TD TOWEL DISPENSER
TECH TECHNICAL
TEL TELEPHONE
TEMP TEMPERATURE OR TEMPORARY
THK THICKNESS
THRU THROUGH
TO TOP OF ___
TPD TOILET PAPER DISPENSER
TPH TOILET PAPER HOLDER
TR TOWEL RACK
TSTAT THERMOSTAT
TV TELEVISION
TYP TYPICAL
U HEAT TRANSFER COEFFICIENT
UC UNDERCUT
UL UNDERWRITERS LABORATORIES
UON UNLESS OTHERWISE NOTED
UPS UNINTERRUPTIBLE POWER SUPPLY
UTIL UTILITY
UV ULTRAVIOLET
V VOLT
VAC VACUUM
VAR VARIES
VCT VINYL COMPOSITION TILE VITRIFIED
CLAY TILE
VENT VENTILATION
VERT VERTICAL
VEST VESTIBULE
VIF VERIFY IN FIELD
VOC VOLATILE ORGANIC COMPOUND
VOL VOLUME
VOLT VOLTAGE
W WIDE OR WEST
W/ WITH
W/O WITHOUT
WBL WOOD BLOCKING
WC WALL COVERING OR WATER CLOSET
WC WL HNG WATER CLOSET, WALL HUNG
WD WOOD
WDW WINDOW
WP WATERPROOFING
WSCT WAINSCOT
WT WEIGHT
WWF WELDED WIRE FABRIC
X BRACE CROSS BRACE
XPS EXTRUDED POLYSTYRENE BOARD
(INSULATION)
YD YARD
YR YEAR
DEMOLITION LINE
ELEVATION INDICATOR
CENTER LINE INDICATOR
EXISTING TO REMAIN LINE
FEATURES ABOVE LINE INDICATOR
FIRE RESISTIVE RATED LINE, 1 HOUR
FIRE RESISTIVE RATED LINE, 2 HOUR
SMOKE TIGHT BARRIER LINE
HIDDEN FEATURES LINE
NEW LINE
BREAK, STRAIGHT (SEE SECTION INDICATORS,
BUILDING, WITH BREAK STANDARDS)
DETAIL INDICATOR
DETAIL INDICATOR
DIMENSION LINE
DOOR OPENING/BORROWED LIGHT IDENTIFIER
DRAWING BLOCK TITLE, TYPICAL
ELEVATION INDICATOR, EXTERIOR
ELEVATION INDICATOR, INTERIOR, MULTIPLE VIEW
ELEVATION INDICATOR, INTERIOR, SINGLE VIEW
CENTER LINE
FURNITURE, FIXTURE, & EQUIPMENT INDICATOR
CL
S
GC
ROOM NAME AND NUMBER
FEC
CG
AA
COLUMN GRID
KEYNOTE
WALL OR PARTITION TYPE
FIRE EXTINGUISHER CABINET
CORNER GUARD
NORTH ARROW
EXISTING CONSTRUCTION TO
REMAIN
EXISTING CONSTRUCTION TO
BE REMOVED
NEW CONSTRUCTION
CONCRETE
EARTH
BASE COURSE
RIGID
INSULATION
BATT
INSULATION
DETAIL NUMBER
SHEET WHERE REF.
SHEET WHERE DRAWN
BUILDING SECTION INDICATOR
DETAIL INDICATOR
DEDUCT ALTERNATE #1: ABANDONED PIPES AND DUCTS
· BASE BID: CONTRACTOR SHALL REMOVE ALL EXISTING ABANDONED PIPES AND DUCTWORK ABOVE
CEILING.
· DEDUCT ALTERNATE: EXISTING ABANDONED PIPES AND DUCTWORK TO REMAIN.
DEDUCT ALTERNATE #2: VAV-BOXES
· BASE BID: CONTRACTOR SHALL REMOVE AND REPLACE EXISTING VAV BOXES.
· DEDUCT ALTERNATE: EXISTING VAV BOXES TO REMAIN.
DEDUCT ALTERNATE #3: ACM REMOVAL
· BASE BID: CONTRACTOR SHALL ABATE ALL EXISTING ASBESTOS CONTAINING MATERIAL.
· DEDUCT ALTERNATE: ABATEMENT IS NOT IN CONTRACT AND IS REQUIRED TO BE COORDINATED WITH
VA COR AND VA SAFETY.
1. REFER TO DRAWING SHEETS FOR SPECIFIC DEMOLITION AND NEW
WORK NOTES.
2. DASHED LINES INDICATE WALLS AND OTHER ITEMS TO BE REMOVED
AS SHOWN ON THE PLANS. SEE LEGEND.
3. SEE SPECIFIC NOTES FOR DEMOLITION INFORMATION THAT
PERTAINS TO SPECIFICALLY DESIGNED AREAS ON THE DEMOLITION PLANS.
4. SEE LEGEND FOR DOOR DEMOLITION SYMBOL WHICH INDICATES
EXISTING DOORS, FRAMES AND HARDWARE SETS TO BE REMOVED.
COORDINATE SALVAGE OF THESE ITEMS WITH THE COR.
5. ALL REQUIRED DEMOLITION WORK FOR MECHANICAL (HVAC,
PLUMBING) AND ELECTRICAL SERVICES ARE NOT SPECIFICALLY SHOWN ON
THE DEMOLITION DRAWINGS. THESE ITEMS ARE TO BE IDENTIFIED AND
COORDINATED WITH THE APPLICABLE TRADE(S).
6. CONTRACTOR TO VERIFY ALL CONDITIONS AND DIMENSIONS IN THE
FIELD PRIOR TO UNDERTAKING ANY DEMOLITION WORK. ANY
DISCREPANCIES SHOULD BE BROUGHT TO THE COR'S ATTENTION
IMMEDIATELY.
7. WHERE EXISTING WALL, CEILING, OR FLOOR ARE TO REMAIN AND
ARE DISTURBED BY DEMOLITION AND/OR CONSTRUCTION, THEY SHALL BE
REPAIRED AS REQUIRED TO MATCH ORIGINAL INTEGRITY AND ADJACENT
CONSTRUCTION.
8. ALL CEILING FINISHES AND SUSPENSION SYSTEMS ARE TO BE
REMOVED WITHIN THE DEMOLITION CONTRACT AREA WHERE NEW
CEILINGS ARE SCHEDULED, UNLESS OTHERWISE INDICATED.
9. REMOVE ALL EXISTING FLOOR FINISHES (INCLUDING MASTICS AND
ADHESIVES) IN AREAS WHERE NEW FLOOR FINISHES ARE SCHEDULED OR
DETAILED. CONTRACTOR SHALL PREPARE SURFACES AS REQUIRED FOR
NEW FLOOR FINISHES AS SCHEDULED. COORDINATE FINISH SCHEDULE
FOR NEW FLOOR FINISHES WITH VA INTERIOR DESIGNER.
10. REMOVE ALL EXISTING BASE MATERIAL IN AREAS WHERE NEW
BASE MATERIAL IS SCHEDULED.
11. REMOVE ALL EXISTING WALL FINISHES (INCLUDING MASTICS AND
ADHESIVES) IN AREAS WHERE NEW WALL FINISHES ARE SCHEDULED OR
DETAILED. PREPARE SURFACES AS REQUIRED FOR NEW WALL FINISHES AS
SCHEDULED.
12. ALL EXISTING WALLS, CEILING, FLOORING, ETC. WHICH ARE
DAMAGED DUE TO DEMOLITION WORK SHALL BE PATCHED (REGARDLESS
OF SIZE) TO MATCH EXISTING AND/OR NEW FINISHES SCHEDULED.
13. REMOVE AND REINSTALL CEILINGS AS REQUIRED BY MECHANICAL,
ELECTRICAL OR OTHER ABOVE CEILING WORK IN AREAS WHERE NO
ARCHITECTURAL DEMOLITION WORK OR LIMITED DEMO WORK IS BEING
DONE. REINSTALL CEILINGS AND PATCH TO MATCH EXISTING.
14. WHERE PLUMBING FIXTURES INCLUDING EXISTING MEDICAL GAS
OUTLETS ARE DESIGNED TO BE REMOVED, CAP ALL EXISTING PIPING
NOTED AS DEMOLISHED AT MAIN REGARDLESS OF VALVE LOCATION TO
MINIMIZE OCCURRENCE OF DEAD LEG PIPING IN ACCORDANCE WITH VA
DIRECTIVE 1061. REFER TO MECH. & PLUMBING DEMOLITION DWGS.
15. WHERE PLUMBING FIXTURES ARE SHOWN TO REMAIN THEY SHOULD
BE CLEANED AND REPAIRED AS REQUIRED. SEE PLUMBING DRAWINGS
FOR ADDITIONAL INFORMATION.
16. ALL FLOOR, WALL, AND CEILING MOUNTED EQUIPMENT WITHIN THE
CONTRACT DEMOLITION AREAS IS TO BE REMOVED. U.N.O. COORDINATE
SALVAGE OF EXISTING EQUIPMENT WITH THE COR BEFORE REMOVAL
FROM THE SITE.
17. ANY DEMOLITION WORK NECESSARY ON FLOOR BELOW (DEMO OR
REQUIRED TO INSTALL NEW WORK) SHALL BE SCHEDULED WITH THE COR.
ANY FINISHES DISTURBED OR DAMAGED SHOULD BE PATCHED OR
REPLACED TO MATCH EXISTING.
18. THE REQUIRED DEMOLITION SHALL NOT BE LIMITED TO. THAT
PORTION SHOWN ON THE PLANS ALONE. WORK COINCIDENTAL THERE TO
WHICH IS NECESSARY TO ACCOMPLISH THE INTENT OF THE CONTRACT
DOCUMENTS IS ALSO PART OF WORK.
19. THE CONTRACTOR SHALL SCHEDULE ALL WORK, INCLUDING ANY
INTERRUPTION OF UTILITIES PRIOR TO STARTING WORK. THE BUILDING
SHALL BE OCCUPIED AND IN USE DURING THE TIME THE WORK IS BEING
PERFORMED. CONTRACTOR MUST NOTIFY/SCHEDULE INTERRUPTIONS
WITH COR'S APPROVAL.
20. ALL BUILDING SPECIALTIES INCLUDING, BUT NOT LIMITED TO,
HANDRAILS, WALL AND CORNER GUARDS, CHALKBOARDS, TOILET
ACCESSORIES, CUBICLE CURTAINS/TRACKS, SIGNAGE, ETC. WITHIN THE
DEMOLITION CONTRACT BOUNDARY ARE TO BE REMOVED U.N.O.
COORDINATE SALVAGE OF EXISTING SPECIALTIES WITH THE COR BEFORE
REMOVAL FROM THE SITE.
21. WHERE EXISTING WALLS/PARTITIONS ARE SHOWN TO REMAIN
WITHIN THE LIMITS OF THE DEMOLITION CONTRACT BOUNDARY (OR ON
THE BOUNDARY), AND NEW FINISHES ARE SCHEDULED TO BE APPLIED
(PER THE ROOM FINISH SCHEDULE) THE CONTRACTOR SHALL HAVE THE
OPTION OF: 1) REMOVING ONLY THE WALL FINISH (NOT THE SUBSTRATE
AND PATCHING THE EXISTING SUBSTRATE, OR 2) REMOVING THE FINISH
AND THE SUBSTRATE (AND REPLACING WITH A LIKE SUBSTRATE). IN ALL
CASES, THE WALL/PARTITON SUBSTRATE SHALL BE PREPARED TO BE
ACCEPTABLE FOR THE PROPOSED FINISH APPLICATION AS SPECIFIED.
22. PRIOR TO STARTING DEMOLITION WORK THE CONTRACTOR SHALL
MEET WITH THE COR TO COORDINATE ALL ITEMS TO BE SALVAGED AND/OR
RELOCATED. ALL SALVAGED ITEMS MUST BE REMOVED TO AVOID DAMAGE,
PROTECTED AND STORED IN A LOCATION DIRECTED BY THE COR.
23. REFER TO OTHER DISCIPLINE (MECHANICAL, ELECTRICAL,
PLUMBING) DEMOLITION PLANS FOR ADDITIONAL ITEMS TO BE REMOVED.
COORDINATE GENERAL DEMOLITION REQUIREMENTS WITH MECHANICAL
AND ELECTRICAL DEMOLITION WORK. PATCH AND REPAIR ALL FINISHES
AND DEVICES DISTURBED BY DEMOLITION WORK.
24. PATCH HOLES AND VOIDS (REGARDLESS OF SIZE) IN EXISTING
CONCRETE FLOORS OCCURRING AS A RESULT OF DEMOLITION OR
CONSTRUCTION. MATCH THICKNESS OF EXISTING CONCRETE.
25. WHERE PLUMBING CASEWORK ARE SHOWN TO REMAIN THEY
SHOULD BE PROTECTED DURING CONSTRUCTION, CLEANED AND
REPAIRED AS REQUIRED.
26. PROTECT ALL FINISHES SCHEDULED TO REMAIN AS REQUIRED TO
MAINTAIN THEIR INTEGRITY.
27. COORDINATE REMOVAL OF DEBRIS FROM PROJECT SITE WITH COR.
28. EXISTING PARTITIONS THAT ARE INDICATED TO BE REMOVED SHALL
BE REMOVED TO THEIR FULLEST HEIGHT U.N.O.
29. WHERE CUTTING OF EXISTING SURFACES OR REMOVAL OF
EXISTING FINISHES OR FIXTURES IS REQUIRED TO PERFORM THE WORK
UNDER THIS CONTRACT, FILL RESULTING OPENINGS, PATCH THE SURFACE
AND FINISH TO MATCH THE ADJACENT EXISTING SURFACES. HOLES,
PENETRATIONS AND OTHER OPENINGS CAUSED BY THE DEMOLITION OR
NEW CONSTRUCTION SHALL BE FILLED WITH AN APPROVED FIRE
STOPPING MATERIAL. CATALOG DATA ON ALL FIRE STOPPING MATERIAL TO
BE USED SHALL BE SUBMITTED TO THE CONTRACTING OFFICER
REPRESENTATIVE (COR) FOR REVIEW AND APPROVAL PRIOR TO
INSTALLATION.
30. REMOVE AND SALVAGE FOR REUSE FIRE EXTINGUISHERS AND FIRE
ALARM DEVICES/SIGNS.
COORDINATE IN ADVANCE WITH VA IF HAZARDOUS MATERIAL WILL BE
ENCOUNTERED.
AutoCAD SHX Text N
AutoCAD SHX Text
WHEEL
AutoCAD SHX Text
CHAIR
AutoCAD SHX Text
MECH
AutoCAD SHX Text
SLDR
AutoCAD SHX Text
TO SUB-BASEMENT
AutoCAD SHX Text
TO SUB-BASEMENT
AutoCAD SHX Text
TO SUB-BASEMENT
AutoCAD SHX Text
TO SUB-BASEMENT
AutoCAD SHX Text
WF
AutoCAD SHX Text
DOOR BELOW FLOOR
AutoCAD SHX Text
SLOPE
AutoCAD SHX Text
ROLLING SHUTTER
AutoCAD SHX Text
ROLLING SHUTTER
AutoCAD SHX Text
SLDR
AutoCAD SHX Text
EQUIP YARD
AutoCAD SHX Text
EQUIP YARD
AutoCAD SHX Text
ROLLING SHUTTER
AutoCAD SHX Text
DOOR BELOW FLOOR
AutoCAD SHX Text
CRAFT
AutoCAD SHX Text
RM
AutoCAD SHX Text
TO SUB-BASEMENT
AutoCAD SHX Text
ROOF
AutoCAD SHX Text
OVERHANG
AutoCAD SHX Text
CAGE AREA
AutoCAD SHX Text
CONCRETE EDGE
AutoCAD SHX Text
49" CAGE DOOR
AutoCAD SHX Text
ROLLING DOOR
AutoCAD SHX Text
CONCRETE EDGE
AutoCAD SHX Text
ACCENT
AutoCAD SHX Text
PANEL
AutoCAD SHX Text
SLOPE UP
AutoCAD SHX Text
RAMP
AutoCAD SHX Text
DOWN
AutoCAD SHX Text
LIFT
AutoCAD SHX Text
PLATFORM
AutoCAD SHX Text
LOWER LIFT
AutoCAD SHX Text
RAMP
AutoCAD SHX Text
POWER
AutoCAD SHX Text
UNIT
AutoCAD SHX Text
LOADING DOCK
AutoCAD SHX Text
LOADING
AutoCAD SHX Text
DOCK
AutoCAD SHX Text
LEVELER
AutoCAD SHX Text
SLDR
AutoCAD SHX Text
SLDR
AutoCAD SHX Text
COFFEE
AutoCAD SHX Text
FRIDGE
AutoCAD SHX Text
30X96 WORKBENCH
AutoCAD SHX Text
COPIER/PRINTER
AutoCAD SHX Text
(2) MICRO WAVE
AutoCAD SHX Text
COPIER/ PRINTER
AutoCAD SHX Text
30X96 WORKBENCH
AutoCAD SHX Text
FILING / STORAGE
AutoCAD SHX Text
(2) MOBILE WORKSTATIONS
AutoCAD SHX Text
COMPUTER TOWERS ON 2 TIERS OF SHELVING
AutoCAD SHX Text
GFI
AutoCAD SHX Text
GFI
AutoCAD SHX Text
GFI
AutoCAD SHX Text
+44 AFF
AutoCAD SHX Text
+44 AFF
AutoCAD SHX Text
+44 AFF
AutoCAD SHX Text
+44 AFF
AutoCAD SHX Text
EMG
AutoCAD SHX Text
EMG
AutoCAD SHX Text
EMG
AutoCAD SHX Text
WAP
AutoCAD SHX Text
WAP
AutoCAD SHX Text
WAP
AutoCAD SHX Text C
AutoCAD SHX Text C
AutoCAD SHX Text
CR
AutoCAD SHX Text
CR
AutoCAD SHX Text Drawing Title
AutoCAD SHX Text Approved: Project Director
AutoCAD SHX Text Project Title
AutoCAD SHX Text Date
AutoCAD SHX Text Location
AutoCAD SHX Text Checked
AutoCAD SHX Text Building Number
AutoCAD SHX Text Project Number
AutoCAD SHX Text Drawing Number
AutoCAD SHX Text Drawn
AutoCAD SHX Text Dwg. of
AutoCAD SHX Text Revisions:
AutoCAD SHX Text Date
AutoCAD SHX Text
CONSULTANTS:
AutoCAD SHX Text
ARCHITECT/ENGINEERS:
AutoCAD SHX Text one eighth inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text B
AutoCAD SHX Text A
AutoCAD SHX Text C
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text F
AutoCAD SHX Text three inches = one foot
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text one and one half inches = one foot
AutoCAD SHX Text one inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three quarters inch = one foot
AutoCAD SHX Text one half inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three eighths inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text one quarter inch = one foot
AutoCAD SHX Text
VA FORM 08-6231
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text F
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text C
AutoCAD SHX Text B
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text Office of Construction and Facilities Management
AutoCAD SHX Text
FACILITIES MANAGEMENT SERVICES
AutoCAD SHX Text
CHIEF OF PROJECTS
AutoCAD SHX Text
GREGORY LUCAS
AutoCAD SHX Text 03-29-2024
AutoCAD SHX Text
BP
AutoCAD SHX Text
PK
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text A-001
AutoCAD SHX Text
COVER SHEET
AutoCAD SHX Text
BIOMEDICAL ENGINEERING
AutoCAD SHX Text
AFFAIRS - RENOVATION OF
AutoCAD SHX Text
DEPARTMENT OF VETERANS
AutoCAD SHX Text
AutoCAD SHX Text
50 IRVING ST, NW WASHINGTON DC 20722
AutoCAD SHX Text
BLDG 1, STE GC105
AutoCAD SHX Text 688-24-111
AutoCAD SHX Text
RENOVATION OF BIOMEDICAL ENGINEERING
AutoCAD SHX Text WASHINGTON DC VETERANS AFFAIRS MEDICAL CENTER 50 IRVING STREET NW, SUITE GC105, WASHINGTON DC 20422
AutoCAD SHX Text
BID DOCUMENTS - FOR CONSTRUCTION
AutoCAD SHX Text
BASEMENT KEY PLAN
AutoCAD SHX Text
PROJECT SCOPE OF WORK
AutoCAD SHX Text
GRAPHIC SYMBOLS
AutoCAD SHX Text
ABBREVIATIONS
AutoCAD SHX Text
DRAWING BLOCK TITLE
AutoCAD SHX Text 1 1/2" = 1'-0"
AutoCAD SHX Text C4
AutoCAD SHX Text A-201
AutoCAD SHX Text A4
AutoCAD SHX Text
AutoCAD SHX Text A2
AutoCAD SHX Text A-202
AutoCAD SHX Text A
AutoCAD SHX Text B
AutoCAD SHX Text C
AutoCAD SHX Text D
AutoCAD SHX Text A-202
AutoCAD SHX Text A2
AutoCAD SHX Text A-201
AutoCAD SHX Text A4
AutoCAD SHX Text A-512
AutoCAD SHX Text D2
AutoCAD SHX Text A-512
AutoCAD SHX Text D2
AutoCAD SHX Text C2
AutoCAD SHX Text
CORRIDOR
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text
NORTH
AutoCAD SHX Text A4
AutoCAD SHX Text A-201
AutoCAD SHX Text
AutoCAD SHX Text A3.1
AutoCAD SHX Text A4.3
AutoCAD SHX Text
DRAWING INDEX
AutoCAD SHX Text
ARCHITECTURAL
AutoCAD SHX Text A-001 COVER SHEET COVER SHEET A-002 GENERAL NOTES AND DETAILS GENERAL NOTES AND DETAILS A-003 INFECTION CONTROL GENERAL NOTES INFECTION CONTROL GENERAL NOTES AD-101 PARTIAL BASEMENT PLAN - DEMOLITION PARTIAL BASEMENT PLAN - DEMOLITION AD-102 PARTIAL BASEMENT REFLECTED CEILING PLAN - DEMOLITION PARTIAL BASEMENT REFLECTED CEILING PLAN - DEMOLITION A-101 PARTIAL BASEMENT PLAN - NEW WORK PARTIAL BASEMENT PLAN - NEW WORK A-102 PARTIAL BASEMENT REFLECTED CEILING PLAN - NEW WORK PARTIAL BASEMENT REFLECTED CEILING PLAN - NEW WORK A-103 PARTIAL BASEMENT PLAN - FINISHES PLAN PARTIAL BASEMENT PLAN - FINISHES PLAN A-201 MILLWORK ELEVATIONS AND DETAILSMILLWORK ELEVATIONS AND DETAILS
AutoCAD SHX Text
GENERAL DEMOLITION NOTES
AutoCAD SHX Text
MATERIALS LEGEND
AutoCAD SHX Text
MECHANICAL
AutoCAD SHX Text M-001 COVER SHEET - MECHANICAL COVER SHEET - MECHANICAL MD-001 PARTIAL BASEMENT PLAN - MECHANICAL DEMOLITION PARTIAL BASEMENT PLAN - MECHANICAL DEMOLITION M-001 PARTIAL BASEMENT PLAN - MECHANICAL NEW WORK PARTIAL BASEMENT PLAN - MECHANICAL NEW WORK M-501 DETAILS - MECHANICALDETAILS - MECHANICAL
AutoCAD SHX Text
ELECTRICAL
AutoCAD SHX Text E-001 COVER SHEET - ELECTRICAL COVER SHEET - ELECTRICAL ED-001 PARTIAL BASEMENT PLAN - ELECTRICAL DEMOLITION PARTIAL BASEMENT PLAN - ELECTRICAL DEMOLITION EL-001 PARTIAL BASEMENT PLAN - ELECTRICAL LIGHTING NEW WORK PARTIAL BASEMENT PLAN - ELECTRICAL LIGHTING NEW WORK EP-001 PARTIAL BASEMENT PLAN - ELECTRICAL POWER NEW WORK PARTIAL BASEMENT PLAN - ELECTRICAL POWER NEW WORK E-501 DETAILS - ELECTRICALDETAILS - ELECTRICAL
AutoCAD SHX Text
PLUMBING
AutoCAD SHX Text P-001 COVER SHEET - PLUMBING COVER SHEET - PLUMBING PD-001 PARTIAL BASEMENT PLAN - PLUMBING DEMOLITION PARTIAL BASEMENT PLAN - PLUMBING DEMOLITION P-001 PARTIAL BASEMENT PLAN - PLUMBING NEW WORKPARTIAL BASEMENT PLAN - PLUMBING NEW WORK
AutoCAD SHX Text
DEDUCT ALTERNATES
AS SCHEDULED
AS
S
CH
ED
UL
ED
AS SCHEDULED
AS
S
CH
ED
UL
ED
" M
IN
9" M
IN
9" MIN. 9" MIN.
2"
2"
A B F1
AS SCHEDULED
AS
S
CH
ED
UL
ED
AS SCHEDULED
AS
S
CH
ED
UL
ED
C
AS SCHEDULED
2"
2"
F2
AS SCHEDULED
AS
S
CH
ED
UL
ED
2"1'-0"
2"
AS SCHEDULED
1/4"
TEMPERED
GLASS
1/4"
TEMPERED
GLASS
CEILING GRID ANGLES
CONTINUOUS TRACK
GYP. BD. ONE LAYER EACH SIDE,
SEE PARTITION NOTES FOR
TYPICAL TYPE
CONTINUOUS FLOOR TRACK
FINISH FLOOR
WALL BASE PER SCHEDULE
SUSPENDED CEILING SYSTEM
TYPE AA 3 5/8" METAL STUD
STRUCTURE ABOVE
TYPE AX INFILL, MATCH ADJ.
EXISTING METAL STUD
PROVIDE SOUND
ATTENUATION TO MATCH
EXISTING
4" U
.N .O
MAINTAIN FIRE RATING AT
EXISTING CONDITIONS
EXTEND STUDS TO STRUCTURE ABOVE; ANCHOR AND
PROVIDE KICKERS AS NECESSARY FOR PROPER SUPPORT
EXTEND GYPSUM BOARD 4" ABOVE BOTTOM OF
FINISHED CEILING - TYP.
SUSPENDED ACOUSTIC PANEL CEILING SYSTEM
1/2" GYPSUM BOARD ON METAL STUDS, TYPICAL. SEE FLOOR
PLAN AND PARTITION TYPES FOR MORE INFORMATION.
MA
TC
H
EX
IS
TI
NG
CE
ILI
NG
H
EI
GH
T
CEILING GRID ANGLES
2"
CEILING GRID ANGLES
CONTINUOUS TRACK
GYP. BD. ONE LAYER, SEE
PARTITION NOTES FOR
TYPICAL TYPE
CONTINUOUS FLOOR TRACK
FINISH FLOOR
WALL BASE PER SCHEDULE
SUSPENDED CEILING SYSTEM
TYPE F 3 5/8" METAL STUD
STRUCTURE ABOVE
PROVIDE SOUND
ATTENUATION TO MATCH
EXISTING
EXISTING PARTITION TO REMAIN
BID DOCUMENTS - FOR CONSTRUCTION
NO.
1. ALL DOORS SHALL BE 1 3 4" THICK SOLID CORE HARDWOOD UNLESS NOTED OTHERWISE.
2. ALL DOORS SHALL HAVE NO FIRE RATING UNLESS NOTED OTHERWISE.
3. ALL RATED DOORS SHALL HAVE A FRAME OF EQUAL RATING UNLESS NOTED OTHERWISE.
4. ALL INTERIOR VISION PANELS SHALL BE 14" TEMPERED GLASS UNLESS NOTED OTHERWISE.
5. ALL DOOR JAMBS ARE TO RECEIVE DOUBLE STUDS ON BOTH SIDES (MINIMUM).
6. ALL DOORS TO BE 4 INCHES OFF HINGE SIDE OF ADJACENT WALL TO THE LEADING EDGE OF THE FRAME (CLEAR) UNLESS OTHERWISE NOTED
7. GENERAL CONTRACTOR TO SUBMIT SHOP DRAWINGS FOR REVIEW AND APPROVAL OF VA PRIOR TO INSTALLATION.
8. COORDINATE AND PROVIDE HARDWARE AS DETAILED IN THE SPECIFICATIONS OR, IF NOT SPECIFIED, PROVIDE HARDWARE (OF EQUAL QUALITY TO THAT SPECIFIED, AND MOST SIMILAR IN FUNCTION
TO TYPE OF DOOR) REQUIRED FOR DOORS TO OPERATE AND APPEAR AS INTENDED ON DRAWINGS.
9. PROVIDE BRUSHED STAINLESS STEEL KICK PLATES ON PUSH SIDE OF DOORS WITH PUSH BARS OR CLOSER DEVICES. KICK PLATE TO BE INSET 1/2" FROM EACH SIDE OF DOOR, AND MAXIMUM 8" HIGH
OR 1/2" BELOW EDGE OF GLASS LIGHT (IF PRESENT).
10. PROVIDE EXPOSED HARDWARE WITH BRUSHED FINISH AND "SILVER" METALLIC IN COLOR (ALUMINUM, CHROME, OR STAINLESS STEEL).
11. WHEN EXPOSED CLEAR FINISHED WOOD DOORS ARE PAIRED, TAKE CARE TO SELECT MATCHING GRAIN TYPE AND COLOR FOR EACH DOOR IN PAIR
12. IF CONFLICT EXISTS BETWEEN DOOR RATING AS SCHEDULED AND WALL/PARTITION TYPE FIRE RATING AS SHOWN ON PLANS, PROVIDE DOOR(S) WITH THE GREATER FIRE RATING OF THE TWO
13. VERIFY ALL DIMENSIONS AND CLEARANCES, AND COORDINATE UNDERCUTTING REQUIRED TO CLEAR ADJACENT FLOOR MATERIALS.
14. IF A DISCREPANCY EXISTS BETWEEN THE DOOR SCHEDULE REMARKS AND THE HARDWARE SCHEDULE IN THE SPECIFICATIONS, PROVIDE THE HARDWARE NEEDED TO MEET THE MORE STRINGENT
OF THE REQUIREMENTS.
15. TYPICAL DOOR UNDERCUT IS ¾” UNLESS NOTED OTHERWISE.
16. COORDINATE ALL ELECTRIC DOOR OPERATION WITH ELECTRICAL DRAWINGS.
1. PROVIDE 3 5/8" STEEL STUDS UNLESS OTHERWISE NOTED (OR MATCH EXISTING).
2. PROVIDE 5/8" THICK GYPSUM BOARD AT ALL PARTITIONS UNLESS OTHERWISE NOTED.
3. ALL PARTITIONS AND WALLS ARE DIMENSIONED TO THE FINISH FACE OF GYPSUM BOARD
UNLESS OTHERWISE NOTED.
4. PROVIDE FRAMING SPACED AT 16 INCHES ON CENTER (MAX) AT ALL NON-LOAD BEARING
PARTITIONS UNLESS OTHERWISE NOTED.
5. ALL WALL HUNG AND FLOOR SUPPORTED CABINETS OR WALL MOUNTED ACCESSORIES SHALL
HAVE CONTINUOUS 14 GAUGE X 6 INCH BACKER PLATES ATTACHED DIRECTLY TO THE WALL
STUDS.
6. PROVIDE WATER RESISTANT GYPSUM BACKER BOARDS FOR WALLS IN KITCHENS, TOILET
ROOMS (RESTROOMS) AND OTHER WALLS WITHIN 36" (MIN.) LATERALLY OF PLUMBING
FIXTURES, WHERE TILE IS NOT THE SCHEDULED FINISH.
7. CORNER BEADS ARE TO BE INSTALLED AT EVERY GYPSUM EXTERIOR CORNER.
8. INTERIOR GYPSUM BOARD SHALL NOT EXCEED 30'-0" CONTINUOUS WITHOUT A CONTROL JOINT
9. ELECTRICAL AND SERVICE OUTLETS (DATA, VOICE, AV JACKS, ETC.) FOR ADJECENT ROOMS ARE
TO BE POSITIONS A MINIMUM OF 24 INCHES APART AND IN SEPARATE STUD SPACES
10. USE SANITARY SEALANT TO CLOSE GAPS BETWEEN SERVICE OUTLETS (ELECTRICAL,
TELEPHONE, DATA, ETC.) AND GYPSUM BOARD.
TYPE WIDTH HEIGHT THICKNESS MATERIAL FINISH TYPE MATERIAL
HARDWARE
SET REMARKSFINISH
FRAMEDOOR
GC105A
GC105C
GC105D
GC105E
GC105F
C B A A A
3'-0", 2'-0" 7'-0" 1 3/4" STEEL PTD F1 HM PTD HW -SH9
3'-0" 7'-0" 1 3/4" WD, GL STD F1 HM PTD HW -7
3'-0" 7'-0" 1 3/4" WD STD F1 HM PTD HW -3E
3'-0" 7'-0" 1 3/4" WD STD F1 HM PTD HW -3E
3'-0" 7'-0" 1 3/4" WD STD F1 HM PTD HW -3E
HW-3E GENERAL INTERIOR - OFFICE
HINGES QTY AND TYPE AS REQ'D
1 OFFICE LOCK F04
1 FLOOR STOP L02121 X 3 FASTENERS
1 SET SELF-ADHESIVE SEALS R0Y154
1 COAT HOOK L03121
HW-7 GENERAL INTERIOR SLIDING DOOR
1 SET TRACK HARDWARE TYPE REQUIRED FOR DOOR
MATERIAL, WEIGHT, AND MOUNTING
DETAILS (COMPLETE WITH TRACK,
TRACK BRACKETS, HANGERS,
GUIDES, BUMPERS, AND INTERNAL
TRACK STOPS)
2 PULLS TYPE AS REQUIRED
1 SLIDING DOOR LOCK E8281/E8291 (SLIDING DOOR LOCK)
2 CYLINDER
(FOR SLIDING DOOR LOCK) TYPE AS REQUIRED
HW-SH9 ELECTRIC LOCKSET - PAIR
EACH [AC, EL, REX, DPS] PAIR TO HAVE: RATED
HINGES QUANTITY & TYPE AS REQUIRED
1 TRANSFER HINGE 4-WIRE TYPE AS REQUIRED
1 SET AUTO FLUSH BOLTS TYPE 25
1 DUST PROOF STRIKE L04021
1 ELECTRIFIED LOCK F07 (E01-REX, E06) 24VDC
1 POWER SUPPLY REGULATED, FILTERED, 24VDC,
AMPERAGE AS REQUIRED
1 COORDINATOR TYPE 21A
1 OVERLAPPING ASTRAGAL WITH R0Y634 X R0Y154 X THRU-BOLTS
SELF-ADHESIVE SEAL
2 CLOSERS C02011/C02021
2 KICK PLATES J102 (@ STORAGE ROOMS ONLY)
2 FLOOR STOPS L02121 X 3 FASTENERS
1 SET SELF-ADHESIVE SEALS R0Y154
2 ALARM CONTACTS
120VAC POWER, CONDUIT, AND WIRING BY DIVISION 26. CARD READER BY OTHERS.
PROVIDE AUTOMATIC DOOR OPERATOR, ACCESS CONTROL DEVICES. TIE INTO FIRE ALARM SYSTEM TO ALLOW FREE EGRESS IN THE EVENT OF AN EMERGENCY. PROVIDE REQUEST TO EXIT PUSH BUTTON ON ROOM SIDE OF DOOR.
HW-4 GENERAL INTERIOR - CLASSROOM
HINGES QTY AND TYPE AS REQ'D
1 CLASSROOM LOCK F05
1 OVERHEAD STOP C04541
3 SILENCERS L03011
1/2" MIN.
NOTE 1:
OMIT BRACE WHEN "D" DIMENSION IS LESS THAN 2'-0" FOR
GYP. WALLBD. OR 16" FOR PLASTER PARTITION.
SECTION B
VERTICAL STUDS @ 2'-0" MAX. W/GYPSUM
WALLBD. 1'-4" W/ GYPSUM LATH & PLASTER
DOUBLE STUDS FOR SUPPORTING CONC.
BACKER BOARD.
PROVIDE CONTINUOUS BRACING WHEN
STUDS EXCEED 10'-0" & ARE FINISHED
BOTH SIDES
JAMB ANCHOR CLIPS 3 PER SIDE -
COORDINATE W/ HINGE REINFORCEMENT.
DETAIL D
SEE
NOTE 1
1/2"
CONST. JOINT
RUNNER
BET.
STUDS
SEE DOOR
SCHEDULE
SHIM AS
REQ'D.
SEC. B
GYPSUM
WALLBD. PANELS
CONTROL
JOINT
ISOMETRIC OF CONSTR. JT.
ELEVATION AT DOOR FRAME
DETAIL D
PROVIDE SOUND
DEADENING
WHERE REQ'D.
SANITARY
STOP
METAL
DOOR
FRAME
METAL ANCHOR
CLIP
SHIM AS REQ'D.
DETAIL C
JAMB
ANCHOR
SECTION A
DOUBLE
STUDS
DETAIL C
/2"
JAMB ANCHORS
(FURNISHED WITH FRAME)
EQ
EQ
.VA
RI
ESVARIES
MET. DOOR
FRAME
6" M
AX
1/2"
CRIPPLE STUD DO NOT
ANCHOR TO BEARING STUD
A A
D
EQ
EQ
3/4 " M
IN
WIDTH
STUD
MINUS 3/16"
JAMB DEPTH
3/4 " M
IN
3/4 " M
IN
WIDTH
STUD
FRAME FACE
MINUS 3/16
MINUS 3/16
FRAME FACE12"MIN.
5/8"MAX.
INTERIOR SLIDING DOOR
GC105J A 3'-0" 7'-0" 1 3/4" WD STD F2 HM PTD HW -4
GC105H C 3'-0", 3'-0" 7'-0" 1 3/4" STEEL PTD PTD HW -SH9
DUAL AUTHENTICATION CARD READER (CARD AND PIN)
DUAL AUTHENTICATION CARD READER (CARD AND PIN)F1 HM
AutoCAD SHX Text Drawing Title
AutoCAD SHX Text Approved: Project Director
AutoCAD SHX Text Project Title
AutoCAD SHX Text Date
AutoCAD SHX Text Location
AutoCAD SHX Text Checked
AutoCAD SHX Text Building Number
AutoCAD SHX Text Project Number
AutoCAD SHX Text Drawing Number
AutoCAD SHX Text Drawn
AutoCAD SHX Text Dwg. of
AutoCAD SHX Text Revisions:
AutoCAD SHX Text Date
AutoCAD SHX Text
CONSULTANTS:
AutoCAD SHX Text
ARCHITECT/ENGINEERS:
AutoCAD SHX Text one eighth inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text B
AutoCAD SHX Text A
AutoCAD SHX Text C
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text F
AutoCAD SHX Text three inches = one foot
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text one and one half inches = one foot
AutoCAD SHX Text one inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three quarters inch = one foot
AutoCAD SHX Text one half inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three eighths inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text one quarter inch = one foot
AutoCAD SHX Text
VA FORM 08-6231
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text F
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text C
AutoCAD SHX Text B
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text Office of Construction and Facilities Management
AutoCAD SHX Text
FACILITIES MANAGEMENT SERVICES
AutoCAD SHX Text
CHIEF OF PROJECTS
AutoCAD SHX Text
GREGORY LUCAS
AutoCAD SHX Text 03-29-2024
AutoCAD SHX Text
BP
AutoCAD SHX Text
PK
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text A-002
AutoCAD SHX Text
GENERAL NOTES AND DETAILS
AutoCAD SHX Text
BIOMEDICAL ENGINEERING
AutoCAD SHX Text
AFFAIRS - RENOVATION OF
AutoCAD SHX Text
DEPARTMENT OF VETERANS
AutoCAD SHX Text
AutoCAD SHX Text
50 IRVING ST, NW WASHINGTON DC 20722
AutoCAD SHX Text
BLDG 1, STE GC105
AutoCAD SHX Text 688-24-111
AutoCAD SHX Text
DOOR SCHEDULE
AutoCAD SHX Text
DOOR HARDWARE
AutoCAD SHX Text
GENERAL DOOR TYPE AND HARDWARE NOTES
AutoCAD SHX Text
DOOR AND FRAME TYPES
AutoCAD SHX Text
AutoCAD SHX Text
TYPICAL BULKHEAD
AutoCAD SHX Text N.T.S.
AutoCAD SHX Text
AutoCAD SHX Text N.T.S.
AutoCAD SHX Text
GENERAL PARTITION TYPE NOTES
AutoCAD SHX Text
TYPICAL PARTITION-TYPE 'AX' & 'AA'
AutoCAD SHX Text N.T.S.
AutoCAD SHX Text
AutoCAD SHX Text
PARTITION FRAMING FOR DOORS
AutoCAD SHX Text
AutoCAD SHX Text N.T.S.
AutoCAD SHX Text
FURRING PARTITION-TYPE 'F'
AutoCAD SHX Text N.T.S.
BID DOCUMENTS - FOR CONSTRUCTION
ACTIVITY CATEGORY: CATEGORY C-D SMALL TO LARGE SCALE CONSTRUCTION,
RENOVATION, OR MAINTENANCE
PATIENT RISK CATEGORY: LOW -HIGHEST RISK
LEVEL OF PRECAUTION: LEVEL III - IV
1. A PRE-CONSTRUCTION INFECTION CONTROL RISK ASSESSMENT (ICRA) IS CONDUCTED BY THE
INFECTION CONTROL NURSE AND IS REQUIRED FOR ALL CONSTRUCTION, RENOVATIONS AND
MAINTENANCE WORK ACTIVITY. IT IS USED IN CONJUNCTION WITH THE PRE-CONSTRUCTION
RISK ASSESSMENT (PCRA) CONDUCTED BY THE FACILITY PROJECT MANAGER.
2. THE ICRA DESCRIBES MINIMAL REQUIRED CONTROL MEASURES FOR THE LEVEL OF INFECTION
CONTROL PRECAUTIONS NEEDED BEFORE, DURING, AND UPON COMPLETION OF ACTIVITY.
3. PRIOR TO START OF WORK, THE REQUIRED INFECTION CONTROL MITIGATION RESPONSE
STRATEGIES SHALL BE COMPLETED BY THE CONTRACTOR BASED ON THE REQUIREMENTS
SET FORTH IN THE VHA INFECTION CONTROL RISK ASSESSMENT (ICRA) MATRIX
REQUIREMENTS IN CONSULTATION WITH THE INFECTION CONTROL NURSE, FACILITY STAFF
AND SAFETY OFFICER FOR ALL HOSPITAL, CBOCS AND CLINIC SPACES. DETERMINANTS OF
MITIGATION RESPONSE INCLUDE BUT ARE NOT LIMITED TO: PATIENT AND DEPARTMENT RISK
CATEGORY, SCOPE AND DURATION OF WORK, DEFINED LOCATION AND EXTENT OF
TEMPORARY BARRIERS, CONTROL OF AIR FLOW, CONTAINMENT OF DUST AND DEBRIS,
TRANSPORTATION OF MATERIALS AND CLEANUP.
4. WORK WITHIN OCCUPIED SPACES SHALL BE SCHEDULED IN COLLABORATION WITH THE
LEADERSHIP OF THE SPACE TO MINIMIZE DISRUPTION TO FACILITY OPERATIONS AND
WORKFLOW, AS MUCH AS PRACTICABLE. WORK WITHIN OCCUPIED SPACES SHALL BE PHASED
TO LIMIT TASKS TO THOSE THAT MAY BE COMPLETED WITHIN A SINGLE WORK SHIFT, IF
POSSIBLE, INCLUDING CONTAINMENT, TASK COMPLETION, AND CLEANUP.
PRE-CONSTRUCTION ARRANGEMENTS MUST BE MADE IN ADVANCE OF THE START OF THE
WORK.
5. NOTIFY AND MEET WITH LEADERSHIP OF THE DEPARTMENT OR UNIT IN THE IMMEDIATE AREA
PRIOR TO THE START OF WORK.
6. BEFORE ANY CONSTRUCTION ON SITE BEGINS, ALL CONTRACTOR PERSONNEL INVOLVED IN
THE CONSTRUCTION OR RENOVATION ACTIVITY SHALL BE IN-SERVICED/TRAINED IN INFECTION
CONTROL MEASURES ESTABLISHED BY THE MEDICAL CENTER. AFTER THE BARRIERS ARE IN
PLACE AND APPROVED BY INFECTION CONTROL, FACILITY AND SAFETY STAFF, THE
“INFECTION CONTROL RISK ASSESSMENT (ICRA) FORM SHALL BE COMPLETED, SIGNED BY
INFECTION CONTROL AND THE FACILITY STAFF PROJECT MANAGER AND ISSUED TO FACILITY
PROJECT MANAGER/ENGINEER/STAFF. THE COMPLETED ICRA FORM MUST BE POSTED ON ALL
OF THE EXTERIOR DOORS OF THE WORK SITE.
7. A PRE-CONSTRUCTION DUST CONTROL PROGRAM WILL BE ESTABLISHED AND MAINTAINED AS
PART OF THE CONTRACTOR'S INFECTION PREVENTIVE MEASURES IN ACCORDANCE WITH THE
VHA ICRA AND PCRA GUIDELINES. PRIOR TO START OF WORK, PREPARE A PLAN DETAILING
PROJECT-SPECIFIC DUST PROTECTION MEASURES WITH ASSOCIATED PRODUCT DATA,
INCLUDING PERIODIC STATUS REPORTS, AND SUBMIT TO PROJECT ENGINEER AND FACILITY
STAFF FOR REVIEW FOR COMPLIANCE WITH CONTRACT REQUIREMENTS IN ACCORDANCE
WITH VHA ICRA AND PCRA CONSTRUCTION AND DESIGN DIRECTIVES.
8. MEDICAL CENTER INFECTION CONTROL NURSE MONITOR'S FOR THE RISK OF AIRBORNE
CONTAMINANTS DURING AND AFTER CONSTRUCTION.
PRE-CONSTRUCTION AND THROUGHOUT CONSTRUCTION WORK:
1. OBTAIN INFECTION CONTROL RISK ASSESSMENT PERMIT FROM THE FACILITY STAFF, AFTER IT
IS COMPLETED, SIGNED, APPROVED, AND ISSUED BY THE INFECTION CONTROL NURSE. POST
THE ICRA PERMIT OUTSIDE THE DOOR AT ALL POINTS OF ENTRY INTO THE CONSTRUCTION
SITE. IF THE SCOPE OF WORK CHANGES AND/OR EXPANDS OUTSIDE OF THE ORIGINAL
SPECIFIED SCOPE AND SPACE, THE ICRA MUST BE RE-VISITED WITH THE INFECTION CONTROL
NURSE, REVIEWED AND UPDATED ACCORDINGLY.
2. REMOVE OR ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT
CONTAMINATION OF DUCT SYSTEM. PROTECT NEW DUCT WHEN BROUGHT INTO THE
CONSTRUCTION SITE AT ALL TIMES (PRIOR TO AND AFTER INSTALLATION)
3. COMPLETE ALL CRITICAL BARRIERS I.E. SHEETROCK, PLYWOOD, PLASTIC, TO MAINTAIN AT
LEAST A SEALED 1-HOUR SEPARATION FROM NON-WORK AREA OR IMPLEMENT CONTROL
CUBE METHOD (CART WITH PLASTIC COVERING AND SEALED CONNECTION TO WORK SITE
WITH HEPA FILTRATION VACUUM, FOR VACUUMING PRIOR TO EXIT) BEFORE CONSTRUCTION
BEGINS. INSTALL 1-HOUR CONSTRUCTION BARRIERS AND CEILING PROTECTION CAREFULLY,
OUTSIDE OF NORMAL WORK HOURS.
4. MAINTAIN NEGATIVE AIR PRESSURE, 0.01 INCHES OF WATER GAUGE (VERIFIED THROUGH
VAMC INDUSTRIAL HYGENIST AND INFECTION CONTROL), WITHIN WORK SITE UTILIZING HEPA
FILTRATION EQUIPPED AIR FILTRATION UNITS AND CONTINUOUSLY MONITORED WITH A
DIGITAL DISPLAY, RECORDING AND ALARM INSTRUMENT, WHICH MUST BE CALIBRATED ON
INSTALLATION, MAINTAINED WITH PERIODIC CALIBRATION AND MONITORED BY THE
CONTRACTOR.
5. CONTAIN AND SEAL ALL CONSTRUCTION WASTE IN TIGHTLY COVERED CONTAINERS BEFORE
REMOVAL FORM CONSTRUCTION SITE AND PRIOR TO TRANSPORT.
6. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS IT IS A FITTED, SOLID
LID.
7. PLACE DUST MATS AT ENTRANCE AND EXIT OF WORK AREAS AND REPLACE THEM DAILY.
8. WATER MIST WORK SURFACES TO CONTROL DUST WHILE CUTTING.
IN GENERAL, THE FOLLOWING PREVENTIVE MEASURES SHALL BE ADOPTED DURING
CONSTRUCTION TO CONTROL DUST AND PREVENT MOLD.
1. CONTRACTOR SHALL VERIFY THAT CONSTRUCTION EXHAUST TO EXTERIOR IS NOT
REINTRODUCED TO THE MEDICAL CENTER THROUGH INTAKE VENTS, OR BUILDING OPENINGS.
HEPA FILTRATION IS REQUIRED.
2. EXHAUST HOSES SHALL BE EXHAUSTED SO THAT DUST IS NOT REINTRODUCED TO THE
MEDICAL CENTER.
3. ADHESIVE WALK-OFF/CARPET WALK-OFF STICKY MATS SHALL BE USED AT ALL INTERIOR
TRANSITIONS FROM THE CONSTRUCTION AREA TO MEDICAL CENTER AREAS THAT ARE
OCCUPIED. THESE MATS SHALL BE CHANGED AS OFTEN AS REQUIRED TO MAINTAIN CLEAN
WORK AREAS DIRECTLY OUTSIDE CONSTRUCTION AREA AT ALL TIMES.
4. VACUUM AND WET MOP ALL TRANSITION AREAS FROM CONSTRUCTION TO THE OCCUPIED
MEDICAL CENTER AT THE END OF EACH WORKDAY. VACUUMING SHALL UTILIZE HEPA
FILTRATION. MAINTAIN CLEANLINESS OF SURROUNDING AREA FREQUENTLY. REMOVE DEBRIS
AS IT IS CREATED. TRANSPORT THE DEBRIS OUTSIDE OF THE CONSTRUCTION AREA IN RIGID
CONTAINERS WITH TIGHTLY FITTED RIGID LIDS.
5. THE CONTRACTOR SHALL NOT HAUL DEBRIS THROUGH PATIENT-CARE AREAS WITHOUT PRIOR
APPROVAL OF THE RESIDENT ENGINEER, INFECTION CONTROL AND THE MEDICAL CENTER.
WHEN, APPROVED, DEBRIS SHALL BE HAULED IN ENCLOSED DUST PROOF RIGID CONTAINERS
OR WRAPPED IN PLASTIC AND SEALED WITH DUCT TAPE. NO SHARP OBJECTS SHOULD BE
ALLOWED TO CUT THROUGH THE PLASTIC.
6. WIPE DOWN THE EXTERIOR OF THE WORK CARTS AND CONTAINERS WITH MOIST
DISINFECTANT WIPES OR EQUIVALENT TO REMOVE DUST PRIOR TO ENTERING THE HOSPITAL.
7. ALL EQUIPMENT, TOOLS, MATERIAL, ETC. TRANSPORTED THROUGH OCCUPIED AREAS SHALL
BE MADE FREE FROM DUST AND MOISTURE BY HEPA FILTRATION VACUUMING AND A MOIST
WIPE DOWN.
8. THERE SHALL BE NO STANDING WATER DURING CONSTRUCTION. THIS INCLUDES WATER IN
EQUIPMENT DRIP PANS AND OPEN CONTAINERS WITHIN THE CONSTRUCTION AREAS. ALL
ACCIDENTAL SPILLS MUST BE CLEANED UP AND DRIED WITHIN 12 HOURS. REMOVE AND
DISPOSE OF POROUS MATERIALS THAT REMAIN DAMP FOR MORE THAN 72 HOURS.
UPON COMPLETION: Levels III - IV
THE CONSTRUCTION AREAS MUST BE INSPECTED BY INFECTION CONTROL NURSE(S) AND
ENGINEERING REPRESENTATIVE (AND OTHERS AS DETERMINED BY THE FACILITY) FOR FINAL
ACTIVITY/PROJECT CLOSE OUT AND REMOVAL OF INFECTION PREVENTION AND CONTROL
MEASURES (CONTAINMENT, BARRIERS, HEPA FILTRATION NEGATIVE AIR PRESSURE UNITS, ETC.).
RETURN THE ICRA PERMIT DOCUMENT TO THE INFECTION CONTROL NURSE AT THE COMPLETION
OF THE EACH PROJECT.
WORK AREA CLEANING:
1. CLEAN WORK AREAS INCLUDING ALL ENVIRONMENTAL SURFACES, HIGH HORIZONTAL
SURFACES AND FLOORING MATERIALS. USE CLEAN MOP HEADS. FILL WITH CLEAN WATER AND
DISINFECTANT AT THE BEGINNING OF EACH DAY. DO NOT LEAVE STANDING WATER IN
BUCKETS OR FLOORS OVER NIGHT. EMPTY AND CLEAN THE MOP BUCKET AT THE END OF
EACH DAY.
2. CHECK ALL SUPPLY AND RETURN AIR REGISTERS FOR DUST ACCUMULATION ON UPPER
SURFACES AS WELL AS AIR DIFFUSER SURFACES AND CLEAN THEM.
REMOVAL OF CRITICAL BARRIERS:
1. CRITICAL BARRIERS MUST REMAIN IN PLACE DURING ALL WORK INVOLVING DRYWALL
REMOVAL, CREATION OF DUST AND ACTIVITIES BEYOND SIMPLE TOUCH-UP WORK. THE
BARRIER MAY NOT BE REMOVED UNTIL A WORK AREA CLEANING HAS BEEN PERFORMED.
ADDITIONAL CLEANING MAY BE NEEDED AFTER REMOVAL OF BARRIER.
2. ALL (PLASTIC OR HARD) BARRIER REMOVAL ACTIVITIES MUST BE COMPLETED IN A MANNER
THAT PREVENTS DUST RELEASE. USE THE FOLLOWING PRECAUTIONS WHEN REMOVING HARD
BARRIERS:
i. CAREFULLY REMOVE SCREWS AND PAINTER TAPE.
ii. IF DUST WILL BE GENERATED DURING SCREW REMOVAL, USE HAND-HELD HEPA
FILTRATION VACUUM.
iii. CLEAN ALL STUD TRACKS WITH HEPA FILTRATION VACUUM BEFORE REMOVING OUTER
HARD BARRIER.
iv. DRYWALL CUTTING IS PROHIBITED DURING REMOVAL PROCESS. REMOVE DRYWALL OR
GYPSUM BOARDS IN INTACT SECTIONS.
v. USE A PLASTIC BARRIER TO ENCLOSE AREA IF DUST COULD BE GENERATED.
NEGATIVE AIR REQUIREMENTS:
1. THE USE OF NEGATIVE AIR MUST BE DESIGNED TO REMOVE CONTAMINANTS FROM THE WORK
AREA.
2. NEGATIVE AIR DEVICES (FANS, FILTERS, MONITORING AND DOCUMENTATION EQUIPMENT)
MUST ALWAYS REMAIN OPERATIONAL AND IN PLACE FOR A PERIOD AFTER COMPLETION OF
DUST CREATING ACTIVITIES TO REMOVE CONTAMINANTS FROM THE WORK AREA AND BEFORE
REMOVAL OF CRITICAL BARRIERS.
HVAC SYSTEMS:
1. UPON REMOVAL OF CRITICAL BARRIERS, REMOVE ISOLATION OF HVAC SYSTEM IN AREAS
WHERE WORK IS BEING PERFORMED.
2. VERIFY THAT HVAC SYSTEMS ARE CLEAN AND OPERATIONAL.
3. VERIFY AND DOCUMENT THROUGH A TAB REPORT THAT THE HVAC SYSTEMS MEETS ORIGINAL
AND REQUIRED AIRFLOW AND AIR EXCHANGE DESIGN SPECIFICATIONS.
WATER SYSTEMS:
1. UNTIL THE POTABLE WATER SYSTEM IS ACTIVATED AND IN USE, FLUSHING OF ALL WATER
OUTLETS AND DRAINS SHALL CONTINUE AT LEAST TWICE PER WEEK IN ACCORDANCE WITH
VHA DIRECTIVE 1061. DOCUMENT ALL FLUSHING ACTIVITY IN A LOG AND PROVIDE A COPY TO
FACILITY STAFF.CONTROL MEASURES ARE TO BE IN PLACE FOR THE DURATION OF THE
ACTIVITY.1. PERFORM WORK ACTIVITY IN A MANNER THAT DOES NOT CREATE DUST.
2. IMMEDIATELY REPLACE ANY CEILING TILE, CLOSE ACCESS PANELS, ETC., UPON COMPLETION
OF WORK.
3. ANY MATERIALS AND EQUIPMENT BEING BROUGHT INTO THE FACILITY MUST BE FREE OF
CONTAMINANTS AND LOOSE MATERIAL.
LEVEL III: ALL CONTROL MEASURES IN LEVEL I & II OF ICRA FORM INCLUDING THE FOLLOWING:
1. PROVIDE ACTIVE MEANS TO CONTROL AIRBORNE DUST FROM DISPERSING INTO OCCUPIED
AREAS AND/OR WATER MIST SURFACE TO CONTROL DUST (E.G., MOBILE DUST CONTAINMENT
CART OR SOME OTHER SYSTEM).
2. ENSURE WORKER CLOTHING IS CLEAN AND FREE OF VISIBLE DUST BEFORE LEAVING THE
WORK AREA.
3. REMOVE OR ISOLATE AIR DIFFUSERS (SUPPLY AND RETURN) TO PROTECT THE HVAC SYSTEM
FROM DUST AND REDUCE AIR TURBULENCE. REBALANCE SYSTEM TO ADDRESS DIFFUSER
ISOLATION.
4. WHEN THE WORK INVOLVES OR IMPACTS POTABLE WATER SYSTEMS INCLUDING STAGNATION
DUE TO REDUCED USAGE, THE PIPING SHALL BE FLUSHED TWICE A WEEK OR ISOLATED FROM
THE MAIN SYSTEM.
5. SEAL DOORS, TO PREVENT DUST MIGRATION.
6. CONTAIN ALL TRASH AND DEBRIS IN THE WORK AREA. PERFORM DAILY CLEANING AND
DISPOSAL OF TRASH (COVERED) FROM WORK AREA USING AN IDENTIFIED EXIT ROUTE.
7. ANY EQUIPMENT, TOOLS, OR MATERIALS REMOVED FROM THE WORK AREA MUST BE IN
SEALED CONTAINERS AND/OR CLEANED OF DUST AND DEBRIS PRIOR TO REMOVAL FROM THE
AREA.
8. NONPOROUS/SMOOTH AND CLEANABLE CONTAINERS (WITH A HARD LID) MUST BE USED TO
TRANSPORT TRASH AND DEBRIS FROM THE CONSTRUCTION AREAS. THESE CONTAINERS
MUST BE DAMP-WIPED CLEANED AND FREE OF VISIBLE DUST/DEBRIS BEFORE LEAVING THE
CONTAINED WORK AREA.
9. INSTALL A STICKY (DUST COLLECTION) MAT AT ENTRANCE OF CONTAINED WORK AREA BASED
ON FACILITY POLICY. STICKY MATS MUST BE CHANGED ROUTINELY AND WHEN VISIBLY
SOILED.
10. MAINTAIN CLEAN SURROUNDINGS WHEN AREA IS NOT CONTAINED BY DAMP MOPPING OR
HEPA FILTRATION VACUUMING SURFACES AT LEAST DAILY.11. ENSURE AVAILABILITY OF
EQUIPMENT FOR CLEANING HANDS.
12. CONSTRUCT AND COMPLETE CRITICAL BARRIERS MEETING NFPA 241 REQUIREMENTS.
BARRIERS MUST EXTEND TO THE CEILING OR IF CEILING TILE IS REMOVED, TO THE DECK
ABOVE.
13. ALL (PLASTIC OR HARD) BARRIER CONSTRUCTION ACTIVITIES MUST BE COMPLETED IN A
MANNER THAT PREVENTS DUST RELEASE. PLASTIC BARRIERS MUST BE EFFECTIVELY AFFIXED
TO FLOOR AND CEILING (OR FLOOR/ROOF DECK ABOVE) AND SECURE FROM MOVEMENT OR
DAMAGE.
14. SEAL ALL PENETRATIONS IN CONTAINMENT BARRIERS, INCLUDING FLOORS AND CEILING,
USING APPROVED MATERIALS (UL SCHEDULE FIRESTOP IF APPLICABLE FOR BARRIER TYPE).
15. MAINTAIN 0.01 INCHES /WATER GAUGE NEGATIVE PRESSURE DIFFERENCE WHT RESPECT TO
ALL SURROUNDING SPACES WITH THE USE OF HEPA FILTRATION EXHAUST AIR SYSTEMS
DIRECTED OUTDOORS. THIS MUST BE MAINTAINED CONTINUOUSLY 24/7 FOR THE DURATION
OF THE PROJECT. EXHAUST DISCHARGED DIRECTLY TO THE OUTDOORS THAT IS 25 FEET OR
GREATER FROM ENTRANCES, AIR INTAKES AND WINDOWS IS NOT REQUIRED TO BE
HEPA-FILTERED. EXHAUSTING DISCHARGED AIR INTO SHARED OR RECIRCULATING HVAC
SYSTEMS, OR OTHER SHARED EXHAUST SYSTEMS (E.G., BATHROOM EXHAUST) IS PROHIBITED.
IN HIGHEST RISK AREAS, MAINTAIN 0.03 INCHES/WATER GAUGE NEGATIVE PRESSURIZATION
OF THE ENTIRE SPACE BY USE OF HEPA FILTRATION EXHAUST AIR SYSTEMS.
16. INSTALL A DIFFERENTIAL PRESSURE SENSING DEVICE (E.G., MAGNEHELIC, MANOMETER, OR
DIGITAL MONITORING) ON EXTERIOR OF WORK CONTAINMENT TO CONTINUALLY MONITOR AND
DOCUMENT NEGATIVE PRESSURIZATION. THE “BALL IN THE WALL” OR SIMILAR APPARATUS
ARE NOT ACCEPTABLE. BASIS OF DESIGN: OMNIGUARD PRESSURE 6 MONITOR.
LEVEL IV: ALL CONTROL MEASURES OF LEVEL I, II & III OF ICRA FORM, INCLUDING THE
FOLLOWING:
1. BARRIERS MUST BE HARD BARRIERS UNLESS TEMPORARY TO INSTALL FINAL BARRIER.
2. CONTAINMENT MUST INCLUDE AN ANTEROOM TO ENSURE PRESSURE CONTROL, ANTEROOM
MUST BE LARGE ENOUGH FOR EQUIPMENT STAGING, CART CLEANING, WORKERS' PPE, AND
CLEANING.
3. WORKER CLOTHING AND/OR PPE MUST BE REMOVED OR CLEAN AND FREE OF VISIBLE DUST
BEFORE LEAVING THE WORK AREA ANTEROOM. HEPA FILTRATION VACUUMING OF CLOTHING
OR USE OF COVER SUITS IS ACCEPTABLE.
4. WORKERS MUST WEAR SHOE COVERS OR HAVE A METHOD TO CLEAN SHOES IN THE
ANTEROOM. SHOE COVERS MUST BE REMOVED PRIOR TO EXITING THE ANTEROOM TO THE
OCCUPIED SPACE (NON-WORK AREA). DAMAGED SHOE COVERS MUST BE CHANGED
IMMEDIATELY.
CONSTRUCTION BARRIERS SHALL BE CONSTRUCTED AS REQUIRED BASED UPON ICRA
PRECAUTIONS: LEVELs III & IV RESPECTIVELY:
1. DOOR WITH CLOSURE MASKING TAPE APPLIED OVER THE METAL FRAME AND DOOR IS
ACCEPTABLE FOR PROJECTS THAT CAN BE CONTAINED IN A SINGLE ROOM. ALL DOORS
SEPARATING THE CONSTRUCTION SITE FROM THE MEDICAL CENTER MUST BE AT LEAST ¾
HOUR FIRE RATED AND WITH A DOOR CLOSURE.
2. CONSTRUCTION, DEMOLITION OR RECONSTRUCTION NOT CAPABLE OF CONTAINMENT WITHIN
A SINGLE ROOM MUST HAVE THE FOLLOWING BARRIERS ERECTED AND MADE PRESENTABLE
ON HOSPITAL OCCUPIED SIDE:
3. (WHERE DUST CONTROL IS THE ONLY HAZARD, AND AN AGREEMENT IS REACHED WITH THE
INFECTION CONTROL AND THE RESIDENT ENGINEER AND MEDICAL CENTER) - AIRTIGHT
PLASTIC BARRIER THAT EXTENDS FROM THE FLOOR TO CEILING. SEAMS MUST BE SEALED
WITH DUCT TAPE TO PREVENT DUST AND DEBRIS FROM ESCAPING
4. 1-HOUR DRYWALL BARRIER ERECTED WITH JOINTS COVERED OR SEALED TO PREVENT DUST
AND DEBRIS FROM ESCAPING.
5. SEAL ALL PENETRATIONS IN EXISTING BARRIER AIRTIGHT AND WITH FIRE STOP
6. BARRIERS ARE FLOOR TO SLAB ABOVE AS WELL AS CHASES AND CEILING SPACES TO STOP
MOVEMENT AIR AND DEBRIS
7. AT ELEVATORS SHAFTS OR STAIRWAYS CONTINUE THE 2-HOUR RATING AND SEAL ALL
PENETRATIONS WITH FIRE STOP
8. PRODUCTS AND MATERIALS
A. BARRIER DOORS: SELF CLOSING ONE-HOUR FIRE-RATED SOLID CORE WOOD IN STEEL FRAME, PAINTED
B. DUST PROOF BARRIER: 1 HOUR FIRE-RATED DRYWALL TAPED AND PAINTED
C. HIGH EFFICIENCY PARTICULATE AIR-EQUIPPED FILTRATION MACHINE RATED AT 99% CAPTURE
OF 0.1 MICRONS INCLUDING POLLEN, MOLD SPORES, AND DUST PARTICLES. HEPA FILTERS
SHOULD HAVE ASHRAE 85 OR OTHER PREFILTER TO EXTEND THE USEFUL LIFE OF THE HEPA
FILTER. PROVIDE BOTH PRIMARY AND SECONDARY FILTRATIONS UNITS. MAINTENANCE OF
EQUIPMENT AND REPLACEMENT OF THE HEPA FILTERS AND OTHER FILTERS WILL BE IN
ACCORDANCE WITH MANUFACTURER'S INSTRUCTIONS.
D. EXHAUST HOSES: HEAVY DUTY, FLEXIBLE STEEL REINFORCED; VENTILATION BLOWER HOSE
E. ADHESIVE WALK-OFF MATS: PROVIDE MINIMUM SIZE MATS OF 24 INCHES X 36 INCHES AT ALL
INGRESS AND EGRESS LOCATIONS.
F. DISINFECTANT: USE THE HOSPITAL-APPROVED DISINFECTANT OR EQUIVALENT PRODUCT
G. PORTABLE CEILING ACCESS MODULES CAN BE USED AS APPROPRIATE FOR OPEN CEILING
ACCESS DURING MINOR ABOVE THE CEILING ACTIVITY
EXTERIOR CONSTRUCTION
1. CONTRACTOR SHALL VERIFY THAT DUST WILL NOT BE INTRODUCED INTO THE MEDICAL
CENTER USING NEGATIVE AIR THROUGH BUILDING OPENINGS OR INTAKE VENTS - INTAKE
VENTS MUST BE CONFIRMED THROUGH VAMC DC HVAC MANAGER. HEPA FILTRATION ON
INTAKE VENTS IS REQUIRED WHERE DUST MAY BE INTRODUCED.
2. DUST CREATED FROM DISTURBANCE OF SOIL SUCH AS FROM VEHICLE MOVEMENT WILL BE
WETTED WITH USE OF A WATER TRUCK AS NECESSARY
3. ALL CUTTING, DRILLING, GRINDING, SANDING, OR DISTURBANCE OF MATERIALS SHALL BE
ACCOMPLISHED WITH TOOLS EQUIPPED WITH EITHER LOCAL EXHAUST VENTILATION (I.E.
VACUUM SYSTEMS) OR WET SUPPRESSION CONTROLS AND MUST COMPLETE THE VA'S “HOT
WORK PERMIT” FORM.
REFERENCES:
1. U.S. DEPARTMENT OF VETERANS AFFAIRS. VETERANS HEALTH ADMINISTRATION (2023).
HEALTHCARE ENVIRONMENT AND FACILITIES PROGRAMS. VHA INFECTION CONTROL RISK
ASSESSEMENT (ICRA). VHA Infection Control Risk Assessment (ICRA) | Healthcare Environment and Facilities Programs (va.gov)
2. U.S. DEPARTMENT OF VETERANS AFFAIRS. VETERANS HEALTH ADMINISTRATION (2023).
HEALTHCARE ENVIRONMENT AND FACILITIES PROGRAMS. PRE-CONSTRUCTION RISK
ASSESSMENT/INFECTION CONTROL RISK ASSESSEMENTS (PCRA)/(ICRA) Pre-Construction Risk Assessments/Infection Control Risk Assessments (PCRA) / (ICRA) | Healthcare Environment and Facilities Programs (va.gov)
3. U.S. DEPARTMENT OF VETERANS AFFAIRS. VETERANS HEALTH ADMINISTRATION (2023).
HEALTHCARE ENVIRONMENT AND FACILITIES PROGRAMS.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .