Attachement 2.pdf
PDF 2 MB Posted
- Attached to
- J091--REMOVAL, DISPOSAL, and REPLACEMENT of EXISTING UNDERGROUND DIESEL FUEL STORAGE TANKS (VA-24-00048585)
- Solicitation number
- 36C24524B0016
About this file
This document contains a Statement of Work (SOW) for the removal, disposal, and replacement of two existing underground diesel fuel storage tanks at the Washington, DC VA Medical Center. The contract will require a UST certified contractor to provide all necessary materials, equipment, labor, and costs to execute the removal of the existing 10,000 and 30,000-gallon double wall fiberglass tanks and install two new matching tanks.
The SOW outlines key requirements such as surveying and soil testing, phasing and scheduling, coordination with hospital operations to minimize disruptions, disposal and environmental compliance, safety and security protocols, and specific construction and performance monitoring standards. The contract has an estimated value between $500,000 to $1 million and a period of performance of 180 calendar days from the Notice to Proceed. Contractors must be UST certified by the District of Columbia's Department of Energy and Environment and meet all VA regulatory requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI Response Number 15 Attachment.pdf | ||
| 36C24524B0016 RFI.pdf | ||
| 36C24524B0016 0002.docx | DOCX document | |
| 36C24524B0016 0001.docx | DOCX document | |
| Sign In Sheet.pdf | ||
| 2024_0325 Collated Specs Remove Replace Install Diesel Fuel USTs Rev.pdf | ||
| 36C24524B0016_1.docx | DOCX document | |
| S02. RFI Submission.docx | DOCX document | |
| P09. Removal Replacement of Exist 10k 30k USTs SOW Attachments ONLY.pdf | ||
| 2024_0311 Rev Compiled Drawings Site Plans and Utilities.pdf | ||
| P09. DOEE 30 Yr UST Notification.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT #688-24-112 25 March 2024 REMOVAL, DISPOSAL and REPLACEMENT of EXISTING
UNDERGROUND DIESEL FUEL STORAGE TANKS
01 35 26 - 15 subcontractor shall designate a minimum of one CP in compliance with 29
CFR 1926.20 (b)(2) that will be identified as a CP to administer their individual safety programs.
B. Further, all specialized Competent Persons for the work crews will be supplied by the respective contractor as required by 29 CFR 1926 (i.e.
Asbestos, Electrical, Cranes, & Derricks (ASME B30.6 Derricks), Demolition, Fall Protection, Fire Safety/Life Safety, Ladder, Rigging, Scaffolds, and).
C. These Competent Persons can have collateral duties as the subcontractor’s superintendent and/or work crew lead persons as well as fill more than one specialized CP role (i.e. Asbestos, Electrical, Cranes, & Derricks, Demolition, Fall Protection, Fire Safety/Life
Safety, Ladder, Rigging, Scaffolds)
D. However, the SSHO has be a separate qualified individual from the Prime
Contractor’s Superintendent and/or Quality Control Manager with duties only as the SSHO.
1. Hazards and Safety Plan shall be reviewed comprehensively.
2. Upon receipt of established work plan and forecasted number of workmen required to be on-site for this contract, the SSHO may be a working Foreman or
Superintendent.
3. If SSHO is permitted, as indicated in #2 above, and sign-off approval is obtained from the COR / CO, individual MUST carry the hour EM 385-1-1 training certification. NO
EXCEPTIONS.
E. The SSHO or an equally qualified Designated Representative/alternate will maintain a presence on the site during construction operations in accordance with FAR Clause 52.236-6: Superintendence by the Contractor.
CPs will maintain presence during their construction activities in accordance with above mentioned clause. A listing of the designated
SSHO and all known CPs shall be submitted prior to the start of work as part of the APP with the training documentation and/or AHA as listed in
Section 1.8 below.
F. The repeated presence of uncontrolled hazards during a contractor’s work operations will result in the designated CP as being deemed incompetent and result in the required removal of the employee in accordance with FAR Clause 52.236-5: Material and Workmanship, Paragraph (c).
https://www.osha.gov/pls/oshaweb/owadisp.show_document?p_id=9832&p_table=STANDARDS#:%7E:text=1910.181(a)(1),hoisting%20mechanism%20and%20operating%20ropes.
File details come from the government source that posted it. Updated .