36C24524B0001.docx
DOCX document 137 KB Posted
- Solicitation number
- 36C24524B0001
About this file
This solicitation is for a construction project to decommission mechanical medical vacuum equipment at a Department of Veterans Affairs medical center. The scope of work includes removing the existing medical vacuum system and installing new vacuum piping, valving, and tie-ins. The project is set aside for Service-Disabled Veteran-Owned Small Businesses. Bids are due on December 12, 2023, and the project is estimated to take 120 days to complete. Pricing shall be submitted using the bid schedule in the solicitation. A bid guarantee, payment bond, and performance bond are required.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24524B0001 0002.docx | DOCX document | |
| ceiling 1.jpg | JPG image | |
| ceiling 2.jpg | JPG image | |
| Solicitation RFI Responses Decommission Med Vac Huntington.pdf | ||
| 36C24524B0001 0001.docx | DOCX document | |
| Record of Attendance Decommission Med Vac Huntington WV VAMC Pre Bid.pdf | ||
| 23-112 Spec Binder (1) General Spec.pdf | ||
| Wage Determination P07 Construction .pdf | ||
| Decommission Mechanical Med Vac Equipment .pdf | ||
| VHA ICRA 2023 .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24524B0001
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5.
REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE
DOCUMENTS (
Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL
SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
1. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than ____ ___________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24524B0001 X 11-09-2023 581-23-112 Department of Veterans Affairs Network Contracting Office 5 (NCO 5) 90C
NCO 5
1540 Spring Valley Dr.
Huntington WV 25704
Aaron Morrison 304-429- 6741 x The contractor shall provide all resources necessary to accomplish a construction project titled " Decommission Mechanical Med Vac Equipment" described per the provided specifications and drawings. The project scope includes decommissioning and proper off-site removal of existing medical vacuum system, installation of new vacuum piping and valving, and tying new piping into existing. Prior to commencing work, general contractor shall provide proof that an OSHA Certified "Competent Person" CP (29CFR 1926.20 (b) (2) will mainta in a presence at the work site whenever the general or subcontractors are present.
Project Name: Decommission Med Vac Equipment Project Number:
581-23-112 Attachments: Drawings/Specifications, General Conditions, ICRA, Wage Determination
The solicitation and any amendments are available electronically on the SAMS Website (http:/www.sam.gov).
Bidders are cautioned that it is their responsibility to access the website for any amendments that may be issued under this solicitation. Pricing shall be submitted utilizing the bid schedule included in the solicitation.
All requests for information about this solici tation must be in writing and received prior to 2:00 p.m.
November 21, to allow for amendment issuance prior to bid due date. Requests for information shall be submitted via email to aaron.morrison@va.gov and include return contact information i ncluding email and telephone number.
IAW FAR 36.204 the magnitude for construction for this project is between $25,000 and $100,000.
It is strongly recommended that bidders send a representative to attend the pre-bid site visit on Tuesday November 14, at 2 p.m. at the VA Medical Center, FMS Building 8, 1540 Spring V alley Drive Huntington, WV 25704.
We will meet outside of the FMS Building. Individual site visits will not be conducted.
This is a 100% Service-Disabled Veteran Owned Small Business Set -Aside pursuant to 38 USC 8127 (d) and PL 109-461.
The SDVOSB status must be verified prior to submitting a bid in accordance with VAAR 819.7003.
Contractors are reminded that they are r esponsible for obtaining required State and Local Licenses as well as the payment of local Business and Occupation (B&O) Taxes.
A public bid opening will be held at 2 p.m. Tuesday December 12, in the FMS Building 8 located at 1540 Spring Valley Drive, Huntington, WV 25704. Electronic submissions will not be accepted.
X 52.211-10 X 14:00
EST
12-12-2023 X
14. NAME AND ADDRESS OF
OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL
AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Bid Item 1 (BASE BID) $_____________________________________ Department of Veterans Affairs Network Contracting Office 5 (NCO 5) Satellite Office 1540 Spring Valley Drive Huntington WV 25704
PAYMENT WILL BE MADE BY
FSC e-Invoice Payment Invoice must be submitted electronically http://www.fsc.va.gov/einvoice.asp Invoice Setup Information 1-877-489-6135 Aaron Morrison
VA-VHA-RPOE-2023-0117
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| STATEMENT OF WORK | 5 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 9 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 10 |
| 2.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 14 |
| 2.2 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 15 |
| 2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 16 |
| 2.4 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 17 |
| 2.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 17 |
| 2.6 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY NOTICE (FEB 2023) | 18 |
| REPRESENTATIONS AND CERTIFICATIONS | 19 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023) | 19 |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 23 |
| GENERAL CONDITIONS | 26 |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 26 |
| 4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (NOV 2021) | 26 |
| 4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 27 |
| 4.4 52.219-27 NOTICE OF SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (OCT 2022) | 27 |
| 4.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2023) | 29 |
| 4.6 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022) | 31 |
| 4.7 52.228-1 BID GUARANTEE (SEP 1996) | 36 |
| 4.8 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000) | 37 |
| 4.9 52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014) | 37 |
| 4.10 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021) | 41 |
| 4.11 52.249-1 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (SHORT FORM) (APR 1984) | 41 |
| 4.12 52.249-1 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (SHORT FORM) (APR 1984) ALTERNATE I (APR 1984) | 41 |
| 4.13 52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012) | 42 |
| 4.14 52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012) ALTERNATE I (SEPT 1996) | 45 |
| 4.15 52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012) ALTERNATE II (SEPT 1996) | 49 |
| 4.16 52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012) ALTERNATE III (SEPT 1996) | 52 |
| 4.17 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 56 |
| 4.18 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020) | 56 |
| 4.19 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 58 |
| 4.20 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 59 |
| 4.21 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 60 |
| 4.22 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 60 |
| 4.23 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 61 |
| 4.24 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 62 |
| 4.25 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 62 |
| 4.26 IT CONTRACT SECURITY | 64 |
| 4.27 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022) | 74 |
| 4.28 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 74 |
| 4.29 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020) | 74 |
| 4.30 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 74 |
| 4.31 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 74 |
| 4.32 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018) | 75 |
| 4.33 VAAR 852.246-71 REJECTED GOODS (OCT 2018) | 77 |
STATEMENT OF WORK
36C24524B0001
Page 1 of Page 1 of
STATEMENT OF WORK 581-23-112
A. GENERAL INFORMATION
Title of Project: Decommission Mechanical Med Vac Equipment Scope of Work: The contractor shall provide all resources necessary to accomplish a construction project described per the provided specifications and drawings. The project scope includes decommissioning and proper off-site removal of existing medical vacuum system, installation of new vacuum piping and valving, and tying new piping into existing. Decommissioning work included but is not necessarily limited to general construction activities for removal of motor(s), tank, electrical, plumbing, all associated system components, and miscellaneous items as detailed on plans and indicated in the specifications. Installation and tie-in work included but is not necessarily limited to new medical vacuum supply piping, valving, and all other associated systems.
Background: The project will decommission original medical vacuum mechanical system that is at end of life and inefficient and will install new vacuum piping, valving, and tie-in points.
Performance Period: It is anticipated the work required under this project should be completed in (120 days) or less from receipt of the Notice to Proceed, unless otherwise directed by the Contracting Officer (CO) through modifications to the contract. The time is due to most of the work being performed after hours, to ensure minimal downtime to normal VA operations, allow proper review of project protocols, approval of submittals and schedules, and delivery of equipment.
B. CONTRACT AWARD MEETING
A pre-construction meeting shall be held with all concerned parties, at which time the notice to proceed will be effective for the contract performance period. The contractor shall not commence performance on the tasks in this SOW until the CO has conducted a pre-construction meeting, or has advised the contractor that a pre-construction meeting is waived.
C. GENERAL REQUIREMENTS
All written deliverables shall be phrased in layperson language. Statistical and other technical terminology shall not be used without providing a glossary of terms.
Where a written milestone deliverable is required in draft form, the VA will complete their review of the draft deliverable within 10 business days from the date of receipt. The contractor shall have 7 business days to deliver the final deliverable from date of receipt of the Government’s comments.
If for any reason any written milestone deliverable cannot be reviewed by the COR and delivered back to the contractor within the scheduled time frame, the COR is required to explain why in writing to the CO, including a firm commitment of when the work shall be completed. If deliverable cannot be delivered within the scheduled time frame, compensation may be due to the contractor.
Non-disruptive work shall be accomplished during normal business hours (8:00 am - 4:30 pm, Monday through Friday). All work involving core drilling, demolition, and work that would interrupt VA operations shall be completed on non-business hours. All power shutdowns or outages are to take place on weekends or non-business hours. It is expected that most of this work must be completed during non-business hours.
D. SPECIFIC MANDATORY TASKS AND ASSOCIATED DELIVERABLES
Description of Tasks and Associated Deliverables: The contractor shall decommission and remove from site existing medical vacuum system, install new vacuum piping and valving, and tie new piping into existing. Decommission work included but is not necessarily limited to general construction activities for removal of motor(s), tank, electrical, plumbing, all associated system components, and miscellaneous items as detailed on plans and indicated in the specifications. Installation and tie-in work included but is not necessarily limited to new medical vacuum supply piping, valving, and all other associated systems. ¾” pipe is shown on the drawing package for tie-ins, but pipe is to match existing. Contractor to verify size.
The contractor shall furnish all labor, material, equipment, and supervision to perform all work in accordance with the terms, conditions, drawings, and specifications. Work includes demolition, construction, alterations, new room finishes (floors, walls, and ceilings), painting, and any other miscellaneous appurtenances required for a complete project. Refer to drawings and specifications for detailed description of tasks to be completed.
E. SCHEDULE FOR DELIVERABLES
The contractor shall maintain progress in accordance with the approved construction schedule as indicated in the specifications. When the progress falls out of the approved schedule range by 10% or greater, the CO will require the contractor to provide the justification for the lapse in progress. All changes to the progress schedule will be approved by the VA through modifications to the contact. If approved through a modification the contractor is required to provide a new updated progress schedule. The CO will make a determination of cause for delay in progress and issue an appropriate response.
The contract requires that the Contractor submit, within ten (10) calendar days of notice to proceed, a realistic schedule showing the order in which the work will be performed under this contract, including but not limited to, manpower and trade. The actual work elements to be accomplished will be shown as required on the reversed side of the form. Develop schedule using MS Project. The chart will be submitted to the Contracting Officer through the COR for approval.
Unless otherwise specified, the number of draft copies and the number of final copies shall be the same.
If for any reason any deliverable cannot be delivered within the scheduled time frame, the contractor is required to explain why in writing to the CO, including a firm commitment of when the work shall be completed. This notice to the CO shall cite the reasons for the delay, and the impact on the overall project. The CO will then review the project scope and issue a response, in accordance with applicable regulations. If deliverable cannot be delivered within the scheduled time frame, compensation may be taken from the contractor.
In the event the contract is modified, changing the work, adding or deleting work, or changing the completion date, a revised schedule will be submitted.
F. CHANGES TO STATEMENT OF WORK
Any changes to the SOW and provided drawings and specifications shall be authorized and approved only through written modifications to the contract by the CO. A copy of each modification will be kept in a project folder along with all other products of the project. Costs incurred by the contractor through the actions of parties other than the CO shall be borne by the contractor.
G. REPORTING REQUIREMENTS
The contractor shall provide the COR with required reporting requirements per the specifications, all daily logs shall be sent to the COR via email by Monday noon from the following week. All weekly payrolls shall be provided and up to date prior to end of month and prior to request for payment. Electronic media is acceptable. All invoices shall be received within 5 days of the first of the month, and is subject to prior COR approval.
H. TRAVEL
None required or expected.
I. GOVERNMENT RESPONSIBILITIES
Refer to specifications for specific government responsibilities and provisions.
J. CONTRACTOR EXPERIENCE REQUIREMENTS
The contractor must inform the VHA COR when personnel are removed from the contract for any reason. If a key person becomes unavailable to complete the contract, proposed substitutions of key personnel shall be made to the COR and CO for VA approval.
K. CONTRACTOR BADGING REQUIREMENTS
It is the responsibility of the contractor to coordinate with the CO and COR for badging all onsite personnel. Contractor personnel must pass a VA required background check and have a VA issued badge prior to beginning any work.
L. CONFIDENTIALITY AND NONDISCLOSURE
Preliminary and final deliverables, and all associated working papers, application source code, and other material deemed relevant by VA which have been generated by the contractor in the performance of this contract, are the exclusive property of the U.S. Government and shall be submitted to the CO at the conclusion of the contract.
The CO will be the sole authorized official to release, verbally or in writing, any data, draft deliverables, final deliverables, or any other written or printed materials pertaining to this contract. No information shall be released by the contractor. Any request for information relating to this contract, presented to the contractor, shall be submitted to the CO for response.
Press releases, marketing material, or any other printed or electronic documentation related to this project, shall not be publicized without the written approval of the CO.
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
(a) Bidding materials consisting of drawings, specifications and contract forms may be obtained by general (prime) contractors interested in submitting bids direct to the Department of Veterans Affairs and by suppliers and subcontractors for their use in preparing sub-bids for general (prime) contractors from the SAM website www.sam.gov under solicitation number 36C24524B0001. By registering at SAM, prime contractors, suppliers and subcontractors will have access to download plans, specifications and amendments.
(b) A Bid Guarantee is required for this solicitation. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000.00. Bid Bond is to be executed on a SF 24. Failure to furnish the required bid guarantee on the proper form and amount, by the time set for the opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.
(c) The bidder to whom award is made will be required to furnish two (2) bonds, a Payment Bond to be executed on the SF 25A and a Performance Bond to be executed on the proper SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of the SF 25 and SF 25A can be obtained upon application to the issuing office.
(d) Disclosure of the magnitude of construction: Between $25,000 and $100,000.
DOCUMENTS REQUIRED WITH BID PACKAGE:
Completed 1442 – pages 1 & 2 Offer Guarantee/Bid Bond Representations and Certifications Price Proposal with Complete Breakdown
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
Instructions, Conditions and Other Statements to Bidders:
(e) Pricing shall be submitted utilizing the Bid Schedule, Continuation of Block 17 of SF-1442. Bidders are urged to type or print pricing legibly.
(f) Offers are to be valid for 120 calendar days for acceptance. Any offers less than 120 calendar days will not be considered and will be rejected as non-responsive.
(g) A formal site visit is scheduled for this solicitation on November 14, 2023, at 2:00 p.m. EST.
(h) Technical Questions: Questions of a technical nature must be provided in writing and shall be submitted by prospective bidders to attention: Aaron Morrison. Questions shall be submitted only via e-mail to: aaron.morrison@va.gov . The subject line must read: 36C24524B0001 Technical Questions. Oral questions of a technical nature are not acceptable due to the possibility of misunderstanding or misinterpretation. All questions must be received no later than 2:00 p.m. EST, November 21, 2023. No telephone request will be honored. Any questions received after this time will NOT be considered and a response will NOT be given. All technical questions and Government responses will be posted on SAM in an amendment to the solicitation.
(i) Bidders whose bid contains a Teaming Agreement must provide the following information at time of bid:
· Legal name of company that will be teaming with the bidding firm
· Legal address of the company that will be teaming with the bidding firm
· Duns & Bradstreet number of the company that will be teaming with the bidding firm
· Copy of the System Award Management (SAM) document of the company that will be teaming with the bidding firm.
· Bidding firm must submit a narrative identifying exactly how the Teaming Agreement will be written defining each party’s role in the preparation process and clearly defines separate roles for the proposed prime contractor and for the proposed subcontractor and how the proposed bidder intends to totally control contract performance. The teaming subcontractor must not have a role in contract management, particularly, a role where the teaming subcontractor employees are the key personnel. The narrative needs to contain the listing of team members, responsibilities of the team members, duration, and responsibilities of the team lead contractor. All bonds must be in the bidder’s name. Failure to provide complete narrative describe above at time of bid will be considered non-responsive and their bid will be rejected.
Prior to award, should the lowest bidder indicate their bid contains a Teaming Agreement, the bidder has ten (10) calendar days to provide a duly executed Teaming Agreement acceptable to the Contracting Officer once the bidder is notified in writing. Failure to provide a duly executed Teaming Agreement within the required ten (10) calendar day timeframe will result in non-responsive bid and rejection of that bid.
(j) Safety or Environmental Violations and Experience Modification Rate
“All Bidders/Offeror’s shall submit the following information pertaining to their past Safety and Environmental record. The information shall contain, at a minimum, a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.
All Bidders/Offeror’s shall submit information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information shall be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead.
Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state-run worker’s compensation insurance rating bureau.
A Determination of Responsibility will be accomplished for the apparent awardee prior to processing the award. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines above may result in a determination of “Non-Responsibility” for the bidder/offeror. Failure to submit this information may result in a determination of “Non-Responsive” for the bidder/offeror. NOTE: Any information received by the Government that would cause for a negative Determination of Responsibility may make the bidder/offeror ineligible for award.
All bidders shall meet reporting requirements to be in compliance with VETS 4212 as outlined within the solicitation and as prescribed in FAR 52.222-37.
Failure to furnish the required information will be considered as Non-Responsive and will be cause for rejection.
An award will be made with reasonable promptness to the responsible bidder, whose bid, conforming to the invitation for bids, will be most advantageous to the government, considering only bid price and any price related factors included in the invitation. Award shall not be made until all required approvals have been obtained in accordance with FAR 14-103-2.
(k) All respondents must be registered in the System Award Management System (SAM) data base at time of bid submittal. Offerors must be verified in the Department of Veterans Affairs (VA), Center for Veterans Enterprise (CVE) at http://www.vetbiz.gov/ at time of bid offering in accordance with Veterans Affairs Acquisition Regulation (VAAR) Subpart 819.7003(b) . Any offeror not CVE or SAM verified at time of bid submittal will be disqualified and bid will be rejected.
(l) Limitations on Subcontracting - Monitoring and Compliance This solicitation includes (VAAR) 852.219-10, VA Notice of Service-Disabled Veteran-Owned Small Business Set- Aside. Accordingly, any contract resulting from this solicitation will include this clause. The contractor is advised in performing contract administration functions, the CO may use the services of a support contractor(s) retained by VA to assist in assessing the contractor's compliance with the limitations on subcontracting or percentage of work performance requirements specified in the clause. To that end, the support contractor(s) may require access to contractor's offices where the contractor's business records, or other proprietary data are retained and to review such business records regarding the contractor's compliance with this requirement. All support contractors conducting this review on behalf of VA will be required to sign an “Information Protection and Non-Disclosure and Disclosure of Conflicts of Interest Agreement” to ensure the contractor's business records or other proprietary data reviewed or obtained in the course of assisting the CO in assessing the contractor for compliance are protected to ensure information or data is not improperly disclosed or other impropriety occurs. Furthermore, if VA determines any services the support contractor(s) will perform in assessing compliance are advisory and assistance services as defined in FAR 2.101, Definitions, the support contractor(s) must also enter into an agreement with the contractor to protect proprietary information as required by FAR 9.505-4, obtaining access to proprietary information, paragraph (b). The contractor is required to cooperate fully and make available any records as may be required to enable the CO to assess the contractor's compliance with the limitations on subcontracting or percentage of work performance requirement.
(m) Infection Control Requirements.
Prior to issuance of the notice to proceed an approved Infection Control Risk Assessment (ICRA) plan must be submitted and approved. The plan will be strictly enforced to also include the completion of infection control training.
(n) A public bid opening will take place at 2:00 p.m. on Tuesday December 12th , 2023 at the FMS Offices at the east end of Building 8 located at 1540 Spring Valley Drive, Huntington, WV 25704.
(o) VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors
1. Contractor employees are subject to daily screening for COVID-19 and may be denied entry to VA facilities if they fail to pass screening protocols. As part of the screening process contractors may be asked screening questions found on the COVID-19 Screening Tool. Check regularly for updates.
a. Contractor employees who work away from VA locations, but who will have direct contact with VA patients shall self-screen utilizing the COVID-19 Screening Tool, in advance, each day that they will have direct patient contact and in accordance with their person or persons who coordinate COVID-19 workplace safety efforts at covered contractor workplaces. Contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.
2. Contractor must immediately notify their COR or Contracting Officer if contract performance is jeopardized due to contractor employees being denied entry into VA Facilities.
BIDDERS ARE REQUIRED TO COMPLETE AND SUBMIT THE FOLLOWING STATEMENT
(p) Contractor Certification: The Contractor certifies that the Contractor shall comply with any and all legal provisions contained in the Immigration and Nationality Act of 1952, As Amended; its related laws and regulations that are enforced by Homeland Security, Immigration and Customs Enforcement and the U.S Department of Labor as these may relate to non-immigrant foreign nationals working under contract or subcontract for the Contractor while providing services to Department of Veterans Affairs patient referrals;
While performing services for the Department of Veterans Affairs, the Contractor shall not knowingly employ, contract or subcontract with an illegal alien; foreign national non-immigrant who is in violation their status, as a result of their failure to maintain or comply with the terms and conditions of their admission into the United States. Additionally, the Contractor is required to comply with all “E-Verify” requirements consistent with “Executive Order 12989” and any related pertinent Amendments, as well as applicable Federal Acquisition Regulations.
If the Contractor fails to comply with any requirements outlined in the preceding paragraphs or its Agency regulations, the Department of Veterans Affairs may, at its discretion, require that the foreign national who failed to maintain their legal status in the United States or otherwise failed to comply with the requirements of the laws administered by Homeland Security, Immigration and Customs Enforcement and the U.S Department of Labor, shall be prohibited from working at the Contractor’s place of business that services Department of Veterans Affairs patient referrals; or other place where the Contractor provides services to veterans who have been referred by the Department of Veterans Affairs; and shall form the basis for termination of this contract for breach.
The Contractor agrees to obtain a similar certification from its subcontractors.
Signature: ____________________________________________ Date: ____________________________________________ Typed Name and Title: ___________________________________ Company Name: ______________________________________
This certification concerns a matter within the jurisdiction of an agency of the United States and the making of a false, fictitious, or fraudulent certification may render the maker subject to prosecution under 18 U.S.C. 1001.
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price, Requirements contract resulting from this solicitation.
(End of Provision)
2.2 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| % |
| 6.9 % |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is
(End of Provision)
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.4 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for— 11/14/2023 at 2pm
(c) Participants will meet at— FMS Building 8 at the Huntington VAMC (End of Provision)
2.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT |
| OCT 2018 |
| 52.204-16 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING |
| AUG 2020 |
| 52.204-22 |
| ALTERNATIVE LINE ITEM PROPOSAL |
| JAN 2017 |
| 52.214-3 |
| AMENDMENTS TO INVITATIONS FOR BIDS |
| DEC 2016 |
| 52.214-4 |
| FALSE STATEMENTS IN BIDS |
| APR 1984 |
| 52.214-5 |
| SUBMISSION OF BIDS |
| DEC 2016 |
| 52.214-6 |
| EXPLANATION TO PROSPECTIVE BIDDERS |
| APR 1984 |
| 52.214-7 |
| LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS |
| NOV 1999 |
| 52.214-18 |
| PREPARATION OF BIDS—CONSTRUCTION |
| APR 1984 |
| 52.214-19 |
| CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION |
| AUG 1996 |
| 52.214-34 |
| SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE |
| APR 1991 |
| 52.214-35 |
| SUBMISSION OF OFFERS IN U.S. CURRENCY |
| APR 1991 |
2.6 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY NOTICE (FEB 2023)
(a) Any offeror responding to this solicitation must comply with established VA Information and Communication Technology (ICT) (formerly Electronic and Information (EIT)) accessibility standards. Information about Section 508 is available at http://www.section508.va.gov/.
(b) The Section 508 accessibility standards applicable to this solicitation are stated in the clause at 852.239–75, Information and Communication Technology Accessibility. In order to facilitate the Government’s determination whether proposed ICT supplies meet applicable Section 508 accessibility standards, offerors must submit appropriate VA Section 508 Checklists, in accordance with the checklist completion instructions. The purpose of the checklists is to assist VA acquisition and program officials in determining whether proposed ICT supplies, or information, documentation and services conform to applicable Section 508 accessibility standards. The checklists allow offerors or developers to self-evaluate their supplies and document—in detail—whether they conform to a specific Section 508 accessibility standard, and any underway remediation efforts addressing conformance issues.
(c) Respondents to this solicitation must identify any exception to Section 508 requirements. If an offeror claims its supplies or services meet applicable Section 508 accessibility standards, and it is later determined by the Government, i.e., after award of a contract or order, that supplies or services delivered do not conform to the described accessibility standards, remediation of the supplies or services to the level of conformance specified in the contract will be the responsibility of the Contractor at its expense.
(End of Provision)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $45 Million.
(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition—
(i) Is set aside for small business and has a value above the simplified acquisition threshold;
(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or
(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(x) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.
(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).
(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial products or commercial services.
(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.
(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)
(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing…
This is the start of the file's text. The full file is on GovTribe.