This document contains responses to questions regarding a federal solicitation to replace HVAC systems and renovate halls and walls at two buildings at a Department of Veterans Affairs medical center. The solicitation seeks bids to remove and replace flooring, demolish and remove trailers beneath floors, upgrade electrical service, paint building exteriors, replace deteriorated doors and skirting, and install infection control barriers. Bidders should price repairing rotten areas identified during construction. Staging and dumpster locations will be determined upon award. The award date was not provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24523B0006 0007.docx | DOCX document | |
| S06 Building 1415 Report.pdf | ||
| 36C24523B0006 0006.docx | DOCX document | |
| S06 answer pre bid RFI 36C245-23-B-0006- REPLACE BLDG 14 15 HVAC AND HALLS AND WALLS - PROJ 517-16-135 - Responses (002).pdf | ||
| 36C24523B0006 0005.docx | DOCX document | |
| S06 answers to pre-bid questions 36C245-23-B-0006- REPLACE BLDG 14 15 HVAC AND HALLS AND WALLS - PROJ 517-16-135 - .pdf | ||
| 36C24523B0006 0004.docx | DOCX document | |
| 36C24523B0006 0003.docx | DOCX document | |
| S04 Pre Bid Agenda Replace Bldg 14 15.pdf | ||
| S04 Pre Bid attendance Bldg 14 15.pdf | ||
| 36C24523B0006 0002.docx | DOCX document | |
| 36C24523B0006 0001.docx | DOCX document | |
| S02 Drawings .pdf | ||
| S02 SOW Replace Building 14n15 HVAC and Halls and Walls .docx | DOCX document | |
| 36C24523B0006.docx | DOCX document | |
| S02 Wage Determination.pdf | ||
| S02 14-15 HVAC Combined Specs.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
05 RFI Replace Building 14 / 15 - Responses
Date: August 11, 2023
590 Means St. NW Suite 200 Atlanta, GA 30318 404.214.9774
1. The only painting referenced on the drawings is on the exterior of the building. Question: Can you confirm that there is no interior painting on this project? That is correct.
2. Drawing G002 General Hazardous Abatement Notes #1 states an asbestos and lead based survey report is available for contractor use. No asbestos containing materials were observed during this survey. No lead-based paint was observed during this survey. Question: Can this survey report be provided? Yes, we can provide that to you.
3. Drawing G002 General Project Notes B states the contractor will be responsible for acquiring
I.D. badges for each member of his workforce. Valid forms of I.D. are required to receive badges. Coordinate with COR per new directive.
• Question: What does the badging process consist of (i.e., paperwork, fingerprinting, scheduling, cost, timeframe to completion for access to facility, etc.)? Badging requests are reviewed and assigned typically within 10 business days (depending on volume). See attached slides from Security presentation showing badging process flow diagram.
4. Drawing G002 Architectural General Notes F states coordinate contractor dumpster location with government. Dumpster location to be identified prior to bidding. Question: Where will the dumpster area be for this project? Staging to be provided in the vicinity of the project area. Final staging area to be determined upon contract award.
• Question: Where will the staging area be for this project? Staging to be provided in the vicinity of the project area. Final staging area to be determined upon contract award.
5. Drawing AD101 Demolition Plan Key Notes #1 states Remove all floor finishes and base in areas where indicated. At the walk thru it was noted that there were rooms that were marked to do nothing with the flooring but the same flooring type of flooring was in rooms that were identified with Note #1. There were also rooms identified with note #1 that had new flooring installed (not matching the blue tile) It was discussed at the walk thru that a new demo drawing would be provided identifying what rooms the flooring is to be removed and replaced.
• Question: What is the intent of the new flooring install (is the VAMC looking to have the same flooring throughout? See revised AD101-rv and A601-rv.
• Question: Can an updated demolition plan and finish plan be provided for the flooring? Yes.
AD101-rv and A601-rv.
• Question: Will additional RFIs be entertained regarding these new documents once posted?
Yes, but limited to revised sheets only.
6. Drawing AD101 Demolition Plan Key Notes #1 states Remove all floor finishes and base in areas where indicated. Corridor C01 only shows a Note #1 on phase 2.
• Question: Does Corridor CO1 get new flooring in the entire corridor? Will address on revised
AD101 Sheet.
7. On Drawing A601 it shows the VCT is to match what is currently used in the conference room (room 124).
• Question: What is the basis of design of the blue tile that is 12 X 12?
Manufacturer: Armstrong Flooring Collection: The Standard Excelon Imperial
Order samples of the following (Shadow Blue 51807, Lunar Blue 51932 and Blue Gray 51903) and match to the blue VCT tile that is currently used in B14/B15. Once you have received the samples, please see which comes the closest to the color of the existing tile.
8. Drawing A401 Detail 5 shows a skirting detail with a 2’ footer that comes out of the ground 6” and is 1’ wide.
• Question: Does this footer detail go around the entire perimeter of the building? No, it occurs only where the brick veneer occurs, it does not occur on the rear. See A401 for elevations.
9. Drawing A401 shows to paint the exterior of the building. At the walk thru it was discovered that there were visible rotten areas in multiple location. The extent of the rotten areas (underneath) could not be determined.
• Question: For bidding purposes can you please advise on how to proceed with pricing the rotten areas as the drawings do not call for any repairs? Pricing should be for painting as indicated. However, rotten areas identified as needing replaced during construction shall be evaluated with VA and addressed at that time.
10. A401 shows to paint the existing doors on the rear elevation. At the walk thru it was discovered that these doors are rotted out (one door had a large portion missing the other door and frame was damaged and not secured to the structure).
• Question: For bidding purposes can you please advise on how to proceed with pricing the rotten areas as the drawings do not call for any repairs? Pricing should be for painting as indicated. However, rotten areas identified as needing replaced during construction shall be evaluated with VA and addressed at that time.
• Question: If these rotted doors are to be replaced as part of this project, can a door, frame, and hardware specification and schedule be provided? Rotten doors, frames and hardware identified as needing replaced during construction shall be evaluated with VA and addressed at that time.
11. Drawing A401 shows vents in the skirting of the trailers?
• Question: Are new vents to be provided? If so, what is the basis of design? Salvage and re-use existing vents.
12. Drawing A601 General Floor Plan Note #1 states Remove mesh, reinsulate with 6” batt insulation and replace mesh.
• Question: Where does this occur as the note #1 does not show up on the floor plan anywhere?
This is a General Note Not A Key Note. It covers the full footprint under the floor. Will revise the note for clarity.
13. Drawing A601 Room Finish Schedule Remarks #1 states only infill area of ceiling where diffusers were removed with tiles that match the existing. See sheet A101 for reference.
• Question: What is the basis of design on the existing ceiling tile? CertainTeed Baroque (Serene
Plus) 2’ x 2’ x 5/8” White is the typical tile used across the facility.
• Question: Can a cut sheet be provided? Not Applicable.
14. Drawing A601 Finish Plan General Note E states install and match new SVT on top of existing
SVT in the same manner as the new flooring work that has already been completed. The wording is confusing as if we are to install the new flooring on top of existing without removing the existing first. Drawing AD101 note #1 stated remove all floor finishes and wall bases in areas where indicated.
• Question: Can you please clarify what the intent is where it states install and match new SVT on top of existing SVT? Disregard that comment.
• Question: Can you identify on the floor plan where this is supposed to take place? See previous answer.
15. Drawing A601 Finish Plan General Note F states in areas where new SVT has already been installed cut border / accent pattern out of first layer (new SVT1) and install SVT2 in its place.
• Question: Can you identify on the floor plan where this is supposed to take place? Will address on updated re-issued sheet when provided by July 5, 2023.
16. Drawing MD101 General Note C states demolish and remove all wheels, axles, hitches, and other building-structure irrelevant remnants of the trailers beneath the floor.
• Question: For bidding purposes can pictures or a list of these items be provided as they are not called out in the drawings? See attached “PDF Question 16 – Response”
17. Drawing MD101 Demolition Key Notes #6 states demolish exhaust grill, duct, and rooftop exhaust fan. Roof curb shall remain for re-use.
• Question: Will Roof Patching be required for this work? No Roof Patching required.
• Question: If so, what type of roof is on the trailers? Not Applicable.
• Question: Is there a current active warranty on the roof? No active roof warranty.
18. Drawing E-002 new work riser diagram shows a new transformer and service drop. After speaking with AEP, they stated costs charged to the general contractor vary on a case-by-case scenario. To further determine what the costs would be for this project AEP would require specific project information such as a ticket number, federal ID number, or other project identifying information that is not available to the contractor at this time.
• Question: Can information be provided to bidders to be able to communicate with AEP and get a realistic cost for this scope of work? AEP has provided VA an estimate to complete their work to upgrade the electric service from single phase to three phase.
• Question: If not, what is the cost to the contractor for this scope or does the government want bidders to carry an allowance for this work? Please include $20,000 to cover cost of AEP work to be completed.
• Question: If an allowance is to be carried, for bidding purposes, what is the dollar value?
$20,000
• Question: What is the lead time for the transformer by AEP? Transformer lead times to be provided by AEP upon request to complete the three phase upgrade. AEP indicates lead times are dependent upon current mark demand at time of upgrade request. However, lead times are expected to be extensive as per AEP.
• Question: What is the base of the transformer (i.e., concrete, plastic, etc.) and is it to be provided by the general contractor? Please include estimate to install conduit from utility pole to CT Cabinet. Conduit shall be quantity 3, 4” diameter for use by AEP to complete service drop.
19. Drawing E-002 shows demolishing the CT cabinet and MDP panel. At the walk thru it was discovered that these cabinets are mounted to a wood frame that appears to be supporting the back corner of the rear deck.
• Question: Does the wood frame get demolished and replaced? It remains.
• Question: If the frame does get replaced what is to be done to support the rear deck? Not
Applicable.
20. Question: Does the breakroom need to stay accessible while work is going on in phase 1?
Yes
21. Question: Does project require any afterhours or weekend work? Yes
22. Specification section 01-00-00-1.3 Statement of Bid Items mentions fire protection systems. There is nothing shown on the drawings identifying fire protection systems work to be performed.
• Question: Can the fire protection system scope be identified for this project? There is no Fire Protection (sprinklers) within the scope.
23. Specification section 01-00-00-1.5.D.7 states All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
• Question: Does the VAMC provide access to the EDMS or would a platform like ProCore be sufficient? ProCore is acceptable.
24. Specification section 01-35-26-1.12-A states that ICRA classification is III for this project.
Specification section 01-35-26-1.12-B-2.a states “Class III & IV (where dust control is the only hazard, and an agreement is reached with the Resident Engineer and Medical Center) - Airtight plastic barrier that extends from the floor to ceiling. Seams must be sealed with duct tape to prevent dust and debris from escaping
• Question: Is a plastic barrier acceptable for this project? Barriers shall be rigid, plastic barriers shall not be acceptable.
• Question: What is the layout of the ICRA plan in regards to the phasing plan? ICRA shall be installed along phasing lines. ICRA shall be coordinated with COR upon project award.
• Question: Is negative air required on this project? Yes.
25. Specification section 01-33-23-1.6.E states “Provide electronic documents over 5MB through an electronic FTP file sharing system. Confirm that the electronic FTP file sharing system can be accessed from the VA computer network. The Contractor is responsible for setting up, providing, and maintaining the electronic FTP file sharing system for the construction contract period of performance.
• Question: Will ProCore be sufficient to meet this requirement? Yes.
26. There is no specification for the cast in place concrete for the footer.
• Question: Can a specification to include a concrete design mix on the footer be provided? Yes.
Please see the attached Quikrete Specifications Sheet.
27. There is no specification for the Z-brick skirting.
• Question: Can a specification be provided for this item? We have reached out to the manufacturer awaiting an answer.
28. At the walk thru it was discussed that an alternate location for the power service was a possibility to minimize the transfer of power downtime (see attached screenshot). The newly proposed location would be closer to the electrical closet and would allow for easier access and installation of the new service. Additionally, the relocation would assist with the issues mentioned in question #19.
• Question: Would this relocation be acceptable to the VAMC? Please bid according to provided contract documents.
29. At the walk thru it was noted that every downspout location, the area directly behind it to include the fascia was rotted.
• Question: Can you please advise on how to proceed with this area as the drawings do not call for any repairs for the gutters, except to add one downspout to be added to one particular area? Pricing should be as indicated on drawings. However, gutters and downspouts identified as needing repaired/replaced during construction shall be evaluated with VA and addressed at that time.
30. Drawing A401 detail 5 shows a skirting detail that call for a prefinished brick panel, the brick siding finish legend lists basis of design is Z-Brick Mesa Beige. According to the manufacturer, Z-Brick is not offered in a prefinished brick panel only as a loose brick.
• Question: What is the government’s intent in providing a panel of this type? To come close to matching the brick palette color of the Beckley Campus and a product that is economically feasible.
• Question: Mesa Beige has been discontinued. Can you advise on what color is to be utilized?
Contacted the Manufacturer Mesa Beige is still in use.
31. At the walk thru it was discovered that the front left corner of building #15 is obstructed by an overgrown tree/bush (see attached picture).
• Question: Can you please advise what is to be done with this tree/bush to gain access to this area of the building? Remove the tree.
Request for Information
440 Martin Luther King Jr. Blvd. Macon, GA 31201
P: 478.743.8415 F: 478.743.8239
Attention:
Requested By: Will Zinnerman
Company Name:
Date: 06/22/2023 Address:
Request #: Pre-Bid RFI 01 City, State, Zip:
Project #: 8106 Telephone #:
Project Name: TMM VA Beckley Replace B14 & B15 HVAC
Subject:
Including Drawing # and/or Specification #
Drawing MD101 General Note C states demolish and remove all wheels, axles, hitches, and other building-structure irrelevant remnants of the trailers beneath the floor.
Request:
For bidding purposes can pictures or a list of these items be provided as they are not called out in the drawings?
Response:
By:
Title: Date:
Document1 Page 1
Items to be removed are generally listed in the note. Attached photos are the best available information available. Bidders must visit the site if they want more information.
Richard Funk PE
06/26/2023
Request for Information
Document1 Page 2
PRODUCT DESCRIPTION
QUIKRETE Concrete Mix is a pre-blended mixture of cement and aggregates for general structural uses, requiring only the addition of water
PRODUCT USE
QUIKRETE Concrete Mix is designed for pouring concrete 2 in (50 mm) thick or more and building or repairing anything out of concrete, including:
• Foundation walls and footings
• Sidewalks, curbs, steps, ramps and walkways
• Appliance and equipment platforms
• Pipe and post footings
• Floor slabs and patios
• Pools, fish ponds, stepping stones
• Splashblocks and bird baths
• Riprap & slope protection
• Driveway repairs
SIZES
QUIKRETE Concrete Mix is available in the following bag sizes:
• 40 lb (18.1 kg)
• 50 lb (22.6 kg)
• 60 lb (27.2 kg)
• 80 lb (36.2 kg)
• 90 lb (40.8 kg) (regional availability)
YIELD
• A 40 lb (18.1 kg) bag yields approximately 0.30 ft3 (8.5 L)
• A 50 lb (22.6 kg) bag yields approximately 0.375 ft3 (10.6 L)
• A 60 lb (27.2 kg) bag yields approximately 0.45 ft3 (12.7 L)
• An 80 lb (36.2 kg) bag yields approximately 0.60 ft3 (17 L)
• A 90 lb (40.8 kg) bag yields approximately 0.675 ft3 (19.1 L)
TECHNICAL DATA
APPLICABLE STANDARDS
• ASTM C39 Standard Test Method for Compressive Strength of
Cylindrical Concrete Specimens
• ASTM C138 Standard Test Method for Density (Unit Weight), Yield, and
Air Content (Gravimetric) of Concrete
• ASTM C143 Standard Test Method for Slump of Hydraulic-Cement
Concrete
• ASTM C387 Standard Specification for Packaged, Dry, Combined
Materials for Concrete and High Strength Mortar
PHYSICAL/CHEMICAL
Typical results obtained for QUIKRETE Concrete Mix, when tested in accordance with the referenced ASTM test methods, are shown in Table 1.
TABLE 1 TYPICAL PHYSICAL PROPERTIES
Slump, ASTM C143
2 in to 3 in (50 mm to 75 mm) Unit Weight, ASTM C138
Approximately 140 lb/ft3 (2242.5 kg/m3) Compressive Strength, ASTM C39
Age PSI (MPa) 7 days 2500 (17.2)
28 days 4000 (27.5)
INSTALLATION
SURFACE PREPARATION
Stake out the planned area and remove sod or soil to the desired depth.
Nail and stake forms securely in place. Tamp and compact the sub-base until firm.
MIXING
QUIKRETE Concrete Mix can be mechanically mixed in a barrel type concrete mixer or a mortar mixer. Choose the mixer size most appropriate for the size of the job to be done. Allow at least 1 ft3 (28.3 L) of mixer capacity for each 80 lb (36.2 kg) bag of QUIKRETE Concrete Mix to be mixed at one time. For each 80 lb (36.2 kg) bag of QUIKRETE Concrete Mix to be mixed, add approximately 6 pt (2.8 L) of fresh water to the mixer.
Turn on the mixer and begin adding the concrete to the mixer. If the material becomes too difficult to mix, add additional water until a workable mix is obtained. If a slump cone is available, adjust water to achieve a 2 in to 3 in (50 mm to 75 mm) slump.
QUIKRETE Concrete Mix may also be mixed by hand. Empty concrete bags into a suitable mixing container. For each 80 lb (36.2 kg) bag of mix, add approximately 6 pt (2.8 L) of clean water. Work the mix with a shovel, rake or hoe and add water as needed until a stiff, moldable consistency is achieved. Be sure there are no dry pockets of material. Do not leave standing puddles of water.
Final water content should be approximately 6 pt to 9 pt (2.8 L to 4.3 L) of water per 80 lb (36.2 kg) bag of concrete. For other bag sizes, use Table 2 to determine water content.
CONCRETE MIX
PRODUCT NO. 1101-40, -50, -60, -80, -90 03 31 00 Structural Concrete
DIVISION 3
TABLE 2 MIXING WATER FOR QUIKRETE CONCRETE MIX
Package Size lb (kg) Starting Water Content pt (L)
Maximum Expected Water Content pt (L)
40 (18.1) 3 (1.4) 4-1/2 (2.1) 50 (22.6) 3-1/2 (1.7) 5-1/2 (2.6) 60 (27.2) 4 (1.9) 7 (3.3) 80 (36.2) 6 (2.8) 9 (4.3) 90 (40.8) 7 (3.3) 10 (4.7)
APPLICATION
Method for Pouring a Slab Start by dampening the sub-grade before concrete is placed. Do not leave standing puddles of water. Shovel or place concrete into the form; fill to the full depth of the form. Fill the repair area completely working continuously from one end to the other. Avoid partial depth fills which could lead to cold joints. After concrete has been compacted and spread to completely fill the forms without air pockets, strike off and float immediately. To strike off, use a straight board (screed), moving the edge back and forth with a saw-like motion to smooth the surface. Use a darby or bull float to float the surface;
this will level any ridges and fills voids left by the straight edge. Cut the concrete away from the forms by running an edging tool or trowel along the forms to compact the slab edges. Cut 1 in (25 mm) deep control joints into the slab every 6 ft to 8 ft (1.8 m to 2.4 m) using a grooving tool. Allow concrete to stiffen slightly, waiting until all water has evaporated from the surface before troweling or applying a broom finish.
Note - For best results, do not overwork the material.
Method for Setting Fence Posts Start by digging the post hole about 3 times the diameter of the post. Hole depth should be 1/3 the overall post height. Place 6 in (150 mm) of dry concrete mix in the bottom of the hole. Position the post, checking that it is level and plumb. Mix QUIKRETE Concrete Mix with water prior to placement into the hole. When standing water has evaporated from the concrete, smooth the surface. Taper it away from the post so rain will flow in that direction. Wait 24 hours before post is subjected to any strain. For load-bearing applications, follow local building codes for proper footing specifications.
Finishing Any standard concrete finishing technique is acceptable for use with QUIKRETE Concrete Mix. Concrete can be hand troweled, power-troweled, broom finished or finished with other specialty finishes.
CURING
General Curing is one of the most important steps in concrete construction. Proper curing increases the strength and durability of concrete, and a poor curing job can ruin an otherwise well-done project. Proper water content and temperature are essential for good curing. In near freezing temperatures the hydration process slows considerably. When the weather is too hot, dry, or windy, water is lost by evaporation from the concrete, which will hinder the hydration reaction, which may result in finishing difficulties and shrinkage cracking. The ideal circumstances for curing are ample moisture and moderate temperature and wind conditions. Curing should be started as soon as possible and should continue for a period of 5 days in warm weather at 70 ºF (21 ºC) or higher or 7 days in colder weather at 50 ºF to 70 ºF (10 ºC to 21 ºC).
Specific Curing Methods QUIKRETE Acrylic Concrete Cure & Seal – Satin Finish (No. 8730) provides the easiest and most convenient method of curing. Apply by spray, brush or roller soon after the final finishing operation when the surface is hard. The surface may be damp, but not wet, when applying curing compound. Complete coverage is essential. Other methods of providing proper curing include covering the surface with wet burlap, plastic sheeting, or waterproof paper to prevent moisture loss; keeping the surface wet with a lawn sprinkler is also acceptable. If burlap is used, it should be free of chemicals that could weaken or discolor the concrete.
New burlap should be washed before use. Place it when the concrete is hard enough to withstand surface damage and sprinkle it periodically to keep the concrete surface continuously moist. Water curing with lawn sprinklers, nozzles or soaking hoses must be continuous to prevent interruption of the curing process. Curing with plastic sheets is convenient.
They must be laid flat, thoroughly sealed at joints and anchored carefully along edges.
PRECAUTIONS
• Curing compounds should not be applied if rain or temperatures below
50 ºF (10 ºC) are expected within 24 hours
• Curing with plastic or burlap can cause patchy discoloration in colored concrete. For colored concrete, wet curing or the use of QUIKRETE®
Acrylic Concrete Cure & Seal – Satin Finish (No. 8730) is recommended
• Do not use curing compounds during late fall on surfaces where de-icers will be used to melt ice and snow. Using curing compounds at that time may prevent proper air drying of the concrete, which is necessary to enhance its resistance to damage caused by de-icers
• Protect concrete from freezing during the first 48 hours. Plastic sheeting and insulation blankets should be used if temperatures are expected to fall below 32 ºF (0 ºC)
SAFETY
IMPORTANT: Read Safety Data Sheet carefully before using. WEAR IMPERVIOUS GLOVES, such as nitrile, mask, and eye protection.
DANGER: Causes severe skin burns and serious eye damage.
Prolonged or repeated inhalation of dust may cause lung damage or cancer.
Keep out of reach of children
WARRANTY
NOTICE: Obtain the applicable LIMITED WARRANTY at www.quikrete.com/product-warranty or send a written request to The Quikrete Companies, LLC, Five Concourse Parkway, Atlanta, GA 30328, USA. Manufactured by or under the authority of The Quikrete Companies, LLC. © 2022 Quikrete International, Inc.
* Refer to www.quikrete.com for the most current technical data and SDS
Revised October 2022 http://www.quikrete.com/product-warranty http://www.quikrete.com/
| Request for Information |
| Request for Information |