This document contains an asbestos reinspection report for Building 321 and details of a related federal contract opportunity for construction of a central emergency power distribution project.

The asbestos reinspection report provides an overview of Building 321, describes assumed asbestos containing materials including flange gaskets and roofing, and assesses the condition and hazard potential of the identified materials. The report was conducted by environmental consultants Aerosol Monitoring & Analysis for the VA Maryland Health Care System.

The related federal contract opportunity is solicitation number 36C24522R0034 for project 512A5-18-302 to construct a central emergency power distribution system at the Perry Point VA campus. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration VISN 5. No further details are provided on response dates, pricing terms, set asides, incumbents or award dates.

View the file

Other files for this federal contract opportunity

Other files attached to 6115--Perry Point | CONSTRUCT CENTRAL EMERGENCY POWER DISTRIBUTION Project #512A5-18-302, newest first.
File Type Posted
36C24522R0034 0007.docx DOCX document
01 74 19 - CONSTRUCTION WASTE MANAGEMENT.pdf PDF
2022.05.27.REVISED ELECTRICAL SITE DWGS.pdf PDF
01 57 19 - TEMPORARY ENVIRONMENTAL CONTROLS.pdf PDF
26 23 13 - GENERATOR PARALLELING CONTROLS.pdf PDF
512A5-18-302_PRE-BID RFIS RESPONSES 05312022.pdf PDF
01 00 00 -GENERAL REQUIREMENTS REV 052622.pdf PDF
01 45 29 - TESTING LABORATORY SERVICES.pdf PDF
Building 315_Lead Sampling.pdf PDF
Capacitor bank Nameplate Information.pdf PDF
36C24522R0034 0006.docx DOCX document
Building 315_Asbestos Sampling.pdf PDF
36C24522R0034 0005.docx DOCX document
36C24522R0034 0004.docx DOCX document
36C24522R0034 0004.docx DOCX document
S04. Sign in Sheet for Site Visit 5.4.2022.pdf PDF
36C24522R0034 0003.docx DOCX document
Evaluation Factors Central Power.pdf PDF
36C24522R0034 0002_1.docx DOCX document
512A5-18-302_Final Bid Specifications - Copy.pdf PDF
512A5-18-302_Final Bid Drawings - Copy.pdf PDF
36C24522R0034 0001.docx DOCX document
36C24522R0034_1.docx DOCX document
36C24522R0034.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Environmental Consultants

1331 Ashton Road P.O. Box 646 Hanover, MD 21076 410-684-3327 FAX: 410-684-3384 www.amaconsulting.com

June 23, 2016

Mr. Robert Johnson Industrial Hygienist VA Maryland Health Care System Boiler Plant Road, Bldg. 101, Room 34 Perry Point, Md 21902

RE: Building 321 Asbestos Reinspection Report; AMA Project #: 15246

Mr. Johnson:

Aerosol Monitoring & Analysis, Inc. (AMA) representatives, Mr. Rob Schoennagel and Mr. Patrick LaShier conducted an on-site asbestos re-inspection of Building 321 for the purpose of verifying the existing information regarding asbestos containing materials (ACM) within the building, assessing conditions of ACMs, and placing warning labels.

Building Description

Building 321 is a Chiller plant. It was constructed in 1980 and has not had any major renovations. Little change has occurred since the previous inspection within this building.

General Summary

AMA performed condition assessments of known ACMs, as well as labeling ACM materials within Building 321.

EPA Inspector(s) – Andrew Washington (I/MP 15013511. Exp. 7/23/16) Robert Schoennagel (I/MP 15002091, exp. 3/30/16) Patrick LaShier (I 15024311, exp. 10/30/16)

Based upon previous inspections, the following ACMs exist within Building 321:

Flange gaskets (assumed), Cal-Mag insulation (assumed), and Roofing (assumed).

Hazard Assessment

ACMs were evaluated following the guidelines established by the Asbestos Hazard Emergency Response Act (AHERA).

The fundamental principle of the hazard assessment methodology described here is that the tendency for ACM to release fibers is directly related to the degree that the material has been disturbed or has deteriorated. One of the best measures of past and current disturbance and/or deterioration is the condition of the ACM. ACM in poor condition reflects past and perhaps ongoing disturbance/deterioration, and most likely past and perhaps ongoing release of fibers into the air. The likelihood of future disturbance can be gauged by the location of the material with respect to: (1) potential contact by building occupants, (2) sources of vibration and (3) sources of air erosion and water damage.

All of these factors can be used to determine the relative hazard ACM in each functional space poses to building occupants. The hazard rating can then be used to rank ACM in each functional space for priority of abatement and to help design an Operations and Maintenance Program which will minimize exposure until the ACM is eventually removed. AMA conducted a hazard assessment of the identified and assumed asbestos containing building materials (ACBM) following the protocol established under the Asbestos Hazard Emergency Response Act (AHERA) regulation, 40 CFR 763, Subpart E. Although non-friable materials are not included in the AHERA rules assessment, AMA included such materials in order to provide the client with an assessment of the risks of the identified/assumed ACBM in their current condition. The materials are classified in the attached Table II by material description, type (asbestos/content by percentage), location, extent, accessibility, and condition of material and current damage. Assessment sheets for each friable homogeneous material were also provided.

Classifying Material with Respect to Condition

“Significantly damaged” ACM is characterized by large areas of material delaminated or showing adhesive failure and/or a surface with water stains, gouges, or mars over at least one tenth of the surface if the damage is evenly distributed (one quarter if the damage is localized.)

“Damaged” ACM is characterized by a surface that is crumbled, water-stained, gouged, marred or otherwise abraded over less than one tenth of the surface if the damage is evenly distributed (one quarter if the damage is localized.)

Good condition refers to a material state where no visible damage or deterioration is evident.

Classifying Material with Respect to Potential for Disturbance

The same factors used in damage assessment are used in evaluating potential for disturbance: (1) potential contact from building occupants, (2) vibration and (3) air flow.

Potential for contact may be considered high if the material is in a public area (e.g., hallway) and accessible to building occupants. The potential may be moderate if the material is in a room or office and accessible to the occupants. Low potential for contact would be characterized by a material that is not within reach of any building occupant.

Factors such as the presence of loud motors or engines near an ACM or close proximity of an airport or major highway to the building could result in a high vibration impact. Moderate vibration influence could be characterized by non-obtrusive motors or engines (e.g. operating ductwork) or occasional loud noises (e.g. vehicle loading dock, generators) The absence of any of the above factors would lead to a low potential of vibration influence.

Potential for air erosion may be classified as high if the material is located in an area with a high velocity air stream, such as a fan room, or moderate if a noticeable movement of air is present (e.g. ventilator air stream.) Potential for air erosion would be considered low if no detectable air movement is detected in the area.

Refer to the attached Asbestos Containing Material Data Table for detailed information regarding the presence quantity, location, condition and assessment of the ACBM at the building.

If you have any questions regarding this summary or the attached data spreadsheet, please contact me at our office.

Sincerely, Andrew Washington, CIH Project Manager

Attachments

Assessment Sheets

VAMHCS FRIABLE HOMOGENEOUS AREA-ASSESSMENT

Building: 321 Date 1-19-16

Inspector Robert Schoennagel HA# 1

Material Type: Assumed Cal Mag pipe insulation Location: West side, under metal jacketing

Area: Exterior Sq. Ft. Ln. Ft. 350 LF

(COMMENTS, % Damage) No damage to any fittings

HAZARD ASSESSMENT FACTORS

DAMAGE FACTORS

Physical

Significant Moderate None x

Water

Extensive

Light

Deterioration

Heavy

Light

DISTURBANCE FACTORS

Proximity to Repair Items

<1 ft. x 1 to 5 ft.

>5ft., Accessible

Within reach x Barely Unreachable

Texture

Rough Pitted Moderate Smooth x

Adjacent Rooms

Common Area x Offices Mech. Rm.

Elevators

AIR FLOW FACTORS

Barriers

Permanent Enclosed x Encapsulated None

Ventilation

Yes No x If yes, Intake Exhaust

Air Movement

High

Low x

Air Conduits

Air Plenum Air Shaft Elevator Shaft

VA Maryland Health Care System 3 Year Re-Inspection Documentation

Building #: 321 Homogenous Area #: 1 Date: 1-19-16_____ Description: Assumed Cal Mag pipe insulation Inspector: Robert Schoennagel

Physical Assessment (check all that apply) Damaged or significantly damaged TSI ACM Damaged friable surfacing ACM Significantly damaged friable surfacing ACM Damaged or significantly damaged friable miscellaneous ACM x ACBM with potential for damage ACBM with potential for significant damage Any remaining friable ACBM or friable suspected ACBM No asbestos detected

Classification of Hazard Potential (circle one)

Hazard Rank ACM Condition ACM Disturbance Potential

7 Significantly Damaged Any 6 Damaged Potential for Significant Damage 5 Damaged Potential for Damage 4 Damaged Low Potential for Damage 3 Good Significant Potential for Damage 2 Good Potential for Damage 1 Good Low Potential for Damage

Inspector Signature: Robert Schoennagel Date:1-19-16

Condition if Changed: No

2011 Inspection Note: Good ______

Current Inspection Comments: Good

Recommended Response Action (circle applicable actions) O&M Remove / Enclose / Encapsulate Evacuate / Restrict

ACM Data Table

Department of Veterans Affairs Perry Point - Building 321

Asbestos Containing Material Data Table

ACM Data Table - 1

Campus/Site Area Designation Building Number

Floor Room

Number Category

(AHERA Class) Material Type Location Quantity

Unit of Measure

Condition Comments Asbestos Content Access Hazard Ranking

Response Action

Drawing Number

Photo Number

Perry Point 01 321 1st Central

Chiller Plant Miscellaneous

White pipe seam sealant on fiberglass pipes

Throughout 1,200 Linear feet On pipe seams and end caps 6" -

2' OD Lines No Asbestos High N/A H-3211 N/A

Perry Point 01 321 1st Central

Chiller Plant Miscellaneous Drywall and joint compound Southwest side 1,200 Square feet

Associated with offices, bathroom areas and breakroom

No Asbestos High N/A H-3211 N/A

Perry Point 01 321 1st Central

Chiller Plant Miscellaneous Interior Door caulk East and west walls 2 Doors 2 @ 4' X 7' No Asbestos High N/A H-3211 N/A

Perry Point 01 321 1st Central

Chiller Plant Miscellaneous Assumed flange gaskets Throughout 150 Gaskets Good Assumed ACM Low 2 O&M H-3211 N/A

Perry Point 01 321 1st Central

Chiller Plant Miscellaneous White baseboard mastic Northwest Office Area 40 Linear feet No Asbestos High N/A H-3211 N/A

Perry Point 01 321 1st Central

Chiller Plant Miscellaneous Tan baseboard mastic

Bathroom Storage Room and Bathroom

70 Linear feet No Asbestos High N/A H-3211 N/A

Perry Point 01 321 1st Central

Chiller Plant Miscellaneous

Tan floor expansion joint material

At floor near Chiller 140 Linear feet No Asbestos High N/A H-3211 N/A

Perry Point 01 321 1st Central

Chiller Plant Miscellaneous Window Caulk East and west walls 22 Window 22 @ 3.5' X 6' No Asbestos Low N/A H-3211 N/A

Perry Point 02 321 1st Storage Miscellaneous 12" X 12" White with tan streaks floor tile Throughout floor 36 Square feet No Asbestos High N/A H-3211 N/A

Perry Point 02 321 1st Storage Miscellaneous Tan floor tile mastic Throughout floor 36 Square feet <1% Chrysotile by TEM High N/A H-3211 N/A

Perry Point 02 321 1st Storage Miscellaneous Drywall joint compound Throughout walls 260 Square feet No Asbestos High N/A H-3211 N/A Perry Point 02 321 1st Storage Miscellaneous Tan baseboard mastic Throughout walls 23 Linear feet No Asbestos High N/A H-3211 N/A

Perry Point 03 321 1st Bathroom Miscellaneous 12" X 12" White with tan streaks floor tile Throughout floor 60 Square feet No Asbestos High N/A H-3211 N/A

Perry Point 03 321 1st Bathroom Miscellaneous Tan floor tile mastic Throughout floor 60 Square feet <1% Chrysotile by TEM High N/A H-3211 N/A

Perry Point 03 321 1st Bathroom Miscellaneous Drywall joint compound Throughout walls 850 Square feet No Asbestos High N/A H-3211 N/A

Perry Point 04 321 1st Breakroom Miscellaneous 12" X 12" White with tan streaks floor tile Throughout floor 450 Square feet No Asbestos High N/A H-3211 N/A

Perry Point 04 321 1st Breakroom Miscellaneous Tan floor tile mastic Throughout floor 450 Square feet <1% Chrysotile by TEM High N/A H-3211 N/A

Perry Point 04 321 1st Breakroom Miscellaneous Drywall and joint compound Throughout walls 1,000 Square feet No Asbestos High N/A H-3211 N/A Perry Point 04 321 1st Breakroom Miscellaneous White sink mastic South wall 2 @ 2' X 1' Sink No Asbestos High N/A H-3211 N/A Perry Point 04 321 1st Breakroom Miscellaneous Brown door caulk East wall 1 @ 4' X 7' Door No Asbestos High N/A H-3211 N/A Perry Point 04 321 1st Breakroom Miscellaneous Tan baseboard mastic Throughout walls 80 Linear feet No Asbestos High N/A H-3211 N/A

Perry Point 05 321 1st Office Miscellaneous 12" x 12" White with Gray floor tile Throughout floor 150 Square feet No Asbestos High N/A H-3211 N/A

Perry Point 05 321 1st Office Miscellaneous Tan floor tile mastic Throughout floor 150 Square feet <1% Chrysotile by TEM High N/A H-3211 N/A

Perry Point 05 321 1st Office Miscellaneous Drywall joint compound Throughout walls and ceiling 1,000 Square feet No Asbestos High N/A H-3211 N/A

Perry Point 05 321 1st Office Miscellaneous White baseboard mastic Throughout walls and ceiling 80 Linear feet No Asbestos High N/A H-3211 N/A

Perry Point 06 321 1st Control Room Miscellaneous 12" x 12" White with tan streaks floor tile Throughout floor 200 Square feet No Asbestos High N/A H-3211 N/A

Perry Point 06 321 1st Control Room Miscellaneous Tan floor tile mastic Throughout floor 200 Square feet <1% Chrysotile by TEM High N/A H-3211 N/A

Perry Point 06 321 1st Control Room Miscellaneous White baseboard mastic North, south and west walls 50 Linear feet No Asbestos High N/A H-3211 N/A

Perry Point 06 321 1st Control Room Miscellaneous Brown baseboard mastic North, south and west walls 50 Linear feet No Asbestos High N/A H-3211 N/A

Perry Point 07 321 1st Corridor Miscellaneous White pipe seam sealant Throughout above drop ceiling 50 Linear feet No Asbestos Low N/A H-3211 N/A

Perry Point 07 321 1st Corridor Surfacing Plaster North wall 15 Square feet Above drop ceiling No Asbestos Low N/A H-3211 N/A Perry Point 07 321 1st Corridor Miscellaneous Red fire stop North wall 1 Square feet No Asbestos Low N/A H-3211 N/A Perry Point 07 321 1st Corridor Miscellaneous Gray fire stop North wall 1 Square feet No Asbestos Low N/A H-3211 N/A Perry Point 07 321 1st Corridor Miscellaneous Brown window caulk West wall 1 @ 5' X 8' Window No Asbestos High N/A H-3211 N/A

Perry Point 08 321 1st Generator Building

Miscellaneous Gray wall caulk Throughout walls and ceiling 500 Square feet Interior walls No Asbestos High N/A H-3211 N/A

Perry Point N/A 321 1st Exterior TSI Assumed calmag West side 350 Linear feet Good Under Metal Jacketing Presumed ACM Low 2 O&M H-3211 N/A Perry Point N/A 321 1st Exterior Miscellaneous Roofing Throughout Roof 5,000 Square feet Good Assumed ACM Low 2 O&M H-3211 N/A