Exhibit U-Tenant-Improvements-Cost-Summary--TICS--Table--Oct-2024-.pdf

PDF 114 KB Posted

Attached to
X1DZ--Norristown Vet Center Replacement Lease 5, 358 RSF / 3969 ABOA/NUSF
Solicitation number
36C24425R0120
Issued by

About this file

The document is a Tenant Improvements Cost Summary (TICS) template for a GSA lease in Norristown, PA, with a total assignable building area (ABOA) of 3,969 square feet. The template provides a comprehensive breakdown of potential construction and improvement costs across 33 CSI Masterformat divisions, including general requirements, existing conditions, concrete, masonry, metals, wood, thermal protection, openings, finishes, and various building systems like electrical, HVAC, plumbing, and communications.

Currently, all line items in the template are blank with zero dollar amounts, indicating this is a standardized cost tracking document prepared for potential lease improvements. The template includes sections for trade costs, general contractor fees, architectural and engineering fees, and other lessor costs, with notes specifying that the document should include all subcontractor costs and that shell and core work items will be for a "warm lit shell" as defined in a separate lease document.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Version Oct. 2024

For: - ABOA SF= 3,969.00

Agency: - TIA PER ABOA SF= -$

Location: Norristown, PA TOTAL TIA= -$

Common Area Factor: -100.00% RSF= -

Masterformat

CSI

System Elements TI* SHELL**

Div 1 General Requirements -$ -$

Div 2 Existing Conditions -$ -$

Div 3 Concrete -$ -$

Div 4 Masonry -$ -$

Div 5 Metals -$ -$

Div 6 Wood, Plastics, Composites -$ -$

Div 7 Thermal and Moisture Protection -$ -$

Div 8 Openings -$ -$

Div 9 Finishes -$ -$

Div 10 Specialties -$ -$

Div 11 Equipment -$ -$

Div 12 Furnishings -$ -$

Div 13 Special Construction -$ -$

Div 14 Conveying Equipment -$ -$

Div 21 Fire Suppression -$ -$

Div 22 Plumbing -$ -$

Div 23 Heating, Ventilating, and Air Conditioning (HVAC) -$ -$

Div 26.1 Electrical -$ -$

Div 26.2 Lighting -$ -$

Div 27 Communications -$ -$

Div 28.1 Electronic Safety -$ -$

Div 28.2 Electronic Security (TI - Non-BSAC) -$ -$

Div 31 Earthwork -$ -$

Div 32 Exterior Improvements -$ -$

Div 33 Utilities -$ -$ Subtotal -$ -$

General Contractor Fee Percent -$ -$ Subtotal Construction Costs -$ -$

Architectural & Engineering Fees (NIC DID costs) *** Percent -$ -$

Other Lessor Costs Established Under the Lease -$ -$ Subtotal Lessor's Costs: -$ -$

Lessor's Project Management Fee Percent -$

Total Price to Government: GRAND TOTAL -$

Cost per ABOA SF -$ -$

Cost per RSF -$ -$

Notes:

* Include all subcontractors' costs.

Trade Costs

Not subject to Lessor's project management fee.

Shell and core work items within tenant space will include those items for a warm lit shell. Please refer to the SHELL DEFINITIONS tab, and the lease for further information.

TENANT IMPROVEMENTS COST SUMMARY (TICS)

File details come from the government source that posted it. Updated .