This document contains a question and answer (Q&A) session regarding a federal contract opportunity for a Comprehensive Water Management Program at the Pittsburgh VA Medical Center. The key details are:

The contract will require the contractor to provide a water management program, including oversight of the facility's water system, data tracking, and recommendations for a water management team. No sampling is required, but the contractor will observe sample collection. The contract does not include repair or replacement of existing equipment. The contractor should have experience developing a water management program and staffing recommendations that align with AAMI ST108:2023 standards. The procurement will be a five-year, firm-fixed-price Indefinite Delivery-Indefinite Quantity (IDIQ) contract awarded to one small business contractor. The North American Industry Classification System (NAICS) code is 541380 - Testing Laboratories and Services. The anticipated award date is September 23, 2024.

View the file

Other files

File Type Posted
36C24424Q1010 0001.docx DOCX document
Combined Synopsis - 36C24424Q1010 - Water Management Prog.docx DOCX document
Attachment B - Past Performance Questionnaire.docx DOCX document
Attachment D - Wage Determination.pdf PDF
36C24424Q1010.docx DOCX document
Attachment A - Statement of Work.pdf PDF
Attachment E - Question and Answer.docx DOCX document
Attachment C - Price Schedule.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question and Answer

1. Are you looking for the contractor to conduct regular (daily, monthly, quarterly, etc.) sampling as part of this solicitation, or to oversee the collection of these samples by facility personnel?

No sampling is required. However observation of collection would be included in survey of of the SPS water system as referenced in 2.1 in the SOW. The contractor will provide a database for the facility to log and track testing results as referenced in 3.19.5

2. Following the initial survey, should existing equipment be found in need of repair or replacement to comply with AAMI ST108 standards, will this work fall under this contract?

No, when issues with equipment or parts of the water system are identified it will be the responsibility of the facility to fix or address these issues.

3. AAMI (Association for the Advancement of Medical Instrumentation) recently published a new standard that establishes the quality of water used to process reusable medical devices. Is one output of the Comprehensive Water Management Program to provide direction on the requirements for water quality necessary to effectively process medical devices intended for patient use?

Yes, please refer to 3.6 of the SOW

4. Are there any VA-specific guidelines or preferences for determining control limits, or should we rely solely on industry standards like AAMI ST108:2023?

AAMI ST108:2023 are the guidelines for the determining control limits.

5. Is the VA Pittsburgh Healthcare System (VAPHS) currently experiencing consequences of using water that is of inadequate quality during the cleaning and sterilization of medical devices?

No, SPS has a contingency in place if water quality is inadequate by AAMI-ST108 guidelines.

6. Can we successfully propose services in addition to the NAISC code specified - 541380 - Testing Laboratories and Services? This is the NAICS Code that will be applied to this RFQ, no other is necessary.

7. Can the VA provide more details on the expected composition of the Water Management Team (WMT)? Are there specific roles or departments that must be represented/interviewed?

The contractor will provide a recommendation for the composition of the Water Management Team and suggest role to be filled by those suggested parties, refer to SOW section 3.1. The contractor should have experience with this type of work and the requirement for a facility Water Management Team. The facility will review the contractors suggestions for WMT involvement and roles and decide if those roles and actions are appropriate for our facility.

8. Concerning the technical capability requirements in the proposal instructions, can the VA clarify if certifications or specific qualifications are required for the "certified analyst" mentioned? What other certifications will be required from the contractor personnel?

Certified Water Technologist (CWT)

9. In section 3.18, the SOW mentions a 90-day work plan development, and 1 year program facilitation timeline. Can the VA provide more details on the expected activities, milestones and deliverables within these timeframes?

This timeline will be created by the contractor based off the deliverables listed in 3.0 in the SOW. The contractor will utilize the deliverables and plan a 90 implantation to present to the SPS Chief. This WMP include implementation on continued support for the remainder of the contract year, refer to SOW section 3.19 for continued support references.

1.