36C24423B0003 0001 Technical Q and A.docx
DOCX document 97 KB Posted
- Solicitation number
- 36C24423B0003
About this file
This document contains technical questions and answers related to solicitation number 36C24423B0003 for repairing mortar and brick on Building 1 at Project Number 503-19-110. The scope of work includes tuckpointing approximately 756 square feet of parapet wall, repairing undersides of concrete sunshades by patching cracks and painting repaired areas, and installing a new roof system over an existing concrete deck. The roof system shall include a vapor retarder, insulation with an average R-value of 33, cover board, and a 60-mil EPDM membrane. Existing mechanical equipment, conduit, and radio antennas will need to be temporarily disconnected or raised by the general contractor to allow for safe roof installation. Lightning protection will be recertified after completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 002 01 33 23 Shop Dwgs Data and Samples.doc | DOC document | |
| 36C24423B0003.docx | DOCX document | |
| Bid Specifications Repair Mortar and Brick.pdf | ||
| Wage Determination PA20230077 1-13-2023.pdf | ||
| Bid Drawings Replace Mortar and Brick.pdf | ||
| 010000 General Requirements 503-19-110.pdf | ||
| Statement of Work Repair Mortar and Brick.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
03-23-2023
503-19-110 00244 Department of Veterans Affairs Network Contracting Office 4
00244 Department of Veterans Affairs Network Contracting Office 4
To all Offerors/Bidders
36C24423B0003 02-13-2023
X
X
** HOUR & DATE for Receipt of Offers is EXTENDED to:
Repair Mortar and Brick on Bldg. #1 | Project # 503-19-110
This amendment is issued for the Technical Question Responses.
All other Terms and Conditions Remain unchanged.
Melvin Moore Contracting Officer
Repair Mortar and Brick on Bldg. #1 Project # 503-19-110 Questions and Responses Repair Mortar and Brick Invitation for Bids 36C24423B0003
Question 1: Supplemental Contract Requirements, on pages 49-50 of the Solicitation, require COVID 19 vaccinations for contractor employees. At a federal level, these have been overruled. Please confirm requirements.
Response: There is no current requirement for contractor employees to be vaccinated.
Question 2: Are there any additional drawings that show roof drain locations?
Response: A/E does not have any as-built drawings that locate existing items such as roof drains. If VA does not have as-builts to provide contractor, locations shall be verified in the field by the contractor. Specification 01 00 00 requires the Contractor to visit and become familiar with the site.
Question 3: Does lightning protection need to be recertified?
Response: Yes, lightning protection needs to be recertified.
Question 4: Dwg. AE201, details F1 and F7 show the existing abutting the new. Are these areas to be toothed out and bonded as one unit?
Response: No, at each location where the new wall abuts the existing, there will be a vertical control joint with backer rod and sealant similar to F7/AE504.
Question 5: If areas described in (1) are to create a control joint, should “dry-fix” anchors be installed into the existing wall construction beside vertical control joints?
Response: Do no install anchors unless required by the drawings and specifications.
Question 6: On Plan Sheet AE202, there is approximately 756SF of masonry along the parapet wall that is shown to be tuck pointed. However, during the site visit, it appears that portions of the wall is buckled and bowed several inches. Is the VA certain they only want that area tuck pointed?
Response: This condition was not evident in our survey from 2020 nor was it part of the original scope of work. Further deterioration could have occurred in the 2+ year period but we cannot confirm. Prepare cost for additional wall repair work as an additional base bid.
Question 7: On Plan Sheet AS203, it indicates to repair the underside of the concrete sunshades. However, the corresponding detail does not show how the VA wants it repaired. Furthermore, there is no division 3 specification guiding the contractor as well. Please provide guidance, a detail or specification on how the VA wants the designated areas “repaired.”
Response: On Sheet AE203, Keynote 214 can be expanded to include: Patch cracks on underside of concrete overhangs. Remove loose material. Grind or sawcut unsound material to solid concrete. Do not use impact tools. Patch crack with vinyl/cement non-shrink concrete patching compound, damtite bondson concrete patch, or equal manufactured compound designed for exterior installation. Clean and prime substrate in accordance with manufacturer’s instructions and recommendations. Mix and apply per manufacturer’s instructions. Finish patch to smooth finish, flush with adjacent surfaces. Once fully cured, sawcut new approx. ¼” wide by ½” deep control. Install two-part paintable polyurethane sealant in cut joint. After sealant has fully cured, paint patch and disturbed areas to match adjacent color.
Question 8: As a follow up to the underside of the concrete sunshades, it indicates to pain it. Is the intent to paint only the repaired areas? Or does the VA intend to paint the entire shade? T obviously won’t match perfectly due to age.
Response: The entire underside of all sunshades are to be painted after necessary concrete repairs are made.
Question 9: Specifications state an overall average R-value of 33 with a minimum R-value of 10 at any location. Is this correct or do we need a continuous minimum R-value of 30?
Response: The minimum R-value requirement for the entire roof as an average of R-33.
Question 10: What wind speed warranty is required for this project?
Response: Design for wind uplift (per building code) at project site.
Question 11: Clarify the typical new roof system from the concrete deck up including edge metal.
Response: Vapor Retarder, Insulation, cover board, EPDM and existing ballast and roof pavers to be salvaged and replaced. See details for edge metal flashing.
Question 12: Specifications call for a 100-mil EPDM, which is only a 45-mil EPDM membrane laminated to a 55-mil fleece. Is this correct or would they prefer a 115-mil membrane which is a 60-mil sheet laminated to a 55-mil fleece.
Response: Provide products that comply with ASTM D4637/D463M, Type III requirements.
Question 13: Will the lighting protection contractor remove the existing system prior to the new roof install and then reinstall and certify after the new roof is installed? This would leave the building unprotected from lighting for a period of time. Will current lightning protect have to be installed to meet current codes or reinstall as it exists?
Response: The existing lightning protection shall not be disconnected. It should only be locally dis-attached from the existing roof and temporarily relocated as required to re-roof at those specific areas. Once the re-roofing is completed at those localized areas, the existing lightning protection shall be re-attached to the new roof. The re-attached system shall be recertified to ensure it was not disconnected during the re-roofing process.
Question 14: The upper roof has a large amount of mechanical equipment and conduit running continuously on top of the roof. Will any disconnections and or raising of equipment be the responsibility of the roofing contractor? Will there be coordinated shutdowns or shielding of the radio antennas on the high roof to ensure safety of the roofing installers? Who owns the coordination of this work?
Response: The disconnections and or raising of equipment be the responsibility of the General Contractor. Coordinate any required shut downs of equipment with the VA COR for a safe roofing installation. See Specification section 01 00 00, including 1.6, G.
End of Document