36C24420Q0489-0003003.docx

DOCX document Posted

Attached to
J035--Elevator Maintenance Butler VAMC Federal contract opportunity
Solicitation number
36C24420Q0489
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 4

About this file

36C24420Q0489 0003 Questions and answers.docx

View the file

Other files for this federal contract opportunity

Other files attached to J035--Elevator Maintenance Butler VAMC, newest first.
File Type Posted
36C24420Q0489-0003002.docx DOCX document
36C24420Q0489-0003000.docx DOCX document
36C24420Q0489-0003001.docx DOCX document
36C24420Q0489-0002003.docx DOCX document
36C24420Q0489-0002001.docx DOCX document
36C24420Q0489-0002004.docx DOCX document
36C24420Q0489-0002002.docx DOCX document
36C24420Q0489-0002000.docx DOCX document
36C24420Q0489-0001003.docx DOCX document
36C24420Q0489-0001002.docx DOCX document
36C24420Q0489-0001001.docx DOCX document
36C24420Q0489-0001000.docx DOCX document
36C24420Q0489-002.pdf PDF
36C24420Q0489-000.docx DOCX document
36C24420Q0489-001.docx DOCX document
36C24420Q0489-004.xlsx XLSX spreadsheet
36C24420Q0489-003.docx DOCX document
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers Amend 0003

1. Paragraph 4.3 requires a one-hour response to all service calls but does not specify a standard for arrival time at the facility. A common standard we see in similar statements of work is to require arrival onsite within two hours of receiving the request. If this is acceptable, we propose adding to the end of the statement “….and be on-site within two hours of receiving the initial request.”

The SOW has been amended to reflect a change in the response time.

2. Is the VA currently in possession of its own (i.e., not owned by the current Contractor) schematic wiring diagrams for every elevator? If not, which ones are missing? This information is necessary to assess the cost of obtaining missing schematics.

The Government does not have any schematic drawings of equipment.

3. Paragraphs 4.6, 11.2.1 and 16.5.1 provide three different procedures/locations for check-in. Is that the intent? If not, please clarify the procedure to follow.

This has been corrected on the revised SOW.

4. Paragraph 7.5 states “Any repairs or adjustments necessary to complete a test and return the elevator to service shall be performed by the Contractor at no additional expense to the Medical Center.” Are the repairs and adjustments mentioned here within the scope of Section 2? If so, we suggest adding “subject to the provisions of Section 2.”, If not, please clarify how these additional repairs and adjustments will be covered?

Please see the revised SOW for changes.

5. Paragraph 7.9 states, “The Contractor shall perform necessary inspections and tests as required under ASME 17.1 and ASME 17.2 using a Qualified Elevator Inspector (QEI)." Please confirm that the VA will provide/cover the cost of the 3rd party inspector for these inspections similar to how it covers inspections in Paragraph 7.1.1.