36C24419Q0130_0001.docx
DOCX document 20 KB Posted
- Attached to
- Notice of Award for HVAC Condensing Unit Upgrade (AHU 2 and AHU 3) at VA Butler Healthcare
- Solicitation number
- 36C24419Q0130
About this file
36C24419Q0130 0001 36C24419Q0130 0001.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| -16070.docx | DOCX document | |
| Attachment_6--Line_set_data.pdf | ||
| Attachment_4--Hot_Water_Horizontal_Unit_Heater_1.pdf | ||
| 36C24419Q0130_0002.docx | DOCX document | |
| Attachment_5--Hot_Water_Horizontal_Unit_Heater_2.pdf | ||
| Attachment_1--WD_2015-4235_Rev_9--12-26-2018.pdf | ||
| Attachment_3--Attic_Plan--HVAC_Piping.pdf | ||
| Attachment_2--Revised_Statement_of_Work.docx | DOCX document | |
| P09_Statement_of_Work--FBO_posted--01-04-2019.docx | DOCX document | |
| Attachment_03_WD_2015-4235_Rev_8--07-10-2018.pdf | ||
| Attachment_02_Price_Cost_Schedule.docx | DOCX document | |
| Attachment_01_Statement_of_Work.docx | DOCX document | |
| 36C24419Q0130_1.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 529-19-1-513-0007 36C244 Department of Veterans Affairs Network Contracting Office 4 1010 Delafield Road Pittsburgh
PA
15215-1802 Contract Specialist is Mark Murray mark.murray4@va.gov 36C244 Department of Veterans Affairs Network Contracting Office 4 1010 Delafield Road Pittsburgh
PA
15215-1802 To all Offerors/Bidders
36C24419Q0130 12-17-2018
X X X
04:30 PM ET, 01-11-2019
The purpose of this Amendment is to answer Vendor Questions (Q&A Matrix included), provide a revised Statement of Work, and resolve inconsistency with the Combined Synopsis Solicitation description.
References to Base Plus Four Option Years are removed as well as Attachments 2A, 2b, and 2c.
This is a firm fixed price contract for services specified in the Statement of Work (SOW, attached) and not an option year contract.
As per FAR 52.212-4(s), the schedule of supplies/services (Attachment 2, original solicitation) has precedence and specifies that work shall be performed in accordance with the SOW.
Solicitation 36C24419Q0130 | HVAC Condensing Unit Upgrade Service | VA Butler Healthcare
| # |
| Vendor Question |
| Government Response |
| 1 |
| Do you have a government estimate on this project? |
| Yes, the Independent Government Cost Estimate is for official Government use only. |
| 2 |
| The solicitation talks about Base + 4, I don’t think that is what you meant |
| This is a firm fixed price contract for the services specified in the Statement of Work (SOW) and not an Option Year Contract. |
| 3 |
| Do the existing coil remain? |
| See Revised SOW. |
| 4 |
| Are the existing coils rated for R-410A refrigerant? |
| To Be Published—Separate Amendment |
| 5 |
| Does the existing refrigerant piping remain? |
| See Revised SOW. |
| 6 |
| Is the existing pipe size rated for R-410A capacity? |
| To Be Published—Separate Amendment |
| 7 |
| What is the refrigerant piping distance including 90’s from the AHU to the remote outdoor Condensing Unit? |
| To Be Published—Separate Amendment |
| 8 |
| Is there a drawing showing the piping route? |
| To Be Published—Separate Amendment |
| 9 |
| If refrigerant piping replacement is required will the replacement be able to be accomplished during normal business hours? |
| To Be Published—Separate Amendment |
| 10 |
| The existing AHU's that are in place have evaporator coils that are not compatible with 410A and the existing units are in an attic which would make it very difficult/costly to change them out. |
| See Revised SOW. |
| 11 |
| Can we anticipate if changes will be made to SOW requirements and perhaps suspense date extended? |
| See Amendment and information below this matrix. |
| 12 |
| Page 3 of 19 states that the anticipated period of performance will be Base plus 4 option years, however, the price/cost schedule only shows a base year. Please advise if this is correct and what would be included in the option years. |
| See Response to 2. |
| 13 |
| Page 4 of 19 references attachments 2A, 2B, and 2C (3 documents making up the Schedule of Supplies and Services), however, there was only an “Attachment 02” posted to the FBO website. |
| Attachments 2A,2B, and 2C are revised to Attachment 2 (Price Cost Schedule) as specified on page 19 and attached as separate document. |
| 14 |
| Will the maintenance portion of the contract be negotiated post award? |
| See Response to 2. |
| 15 |
| How often will the maintenance of the system be required e.g. 3 months 6 months? |
| See Response to 2. |
| 16 |
| Are we to issue the pricing of the two AHU only? |
| Yes, in accordance with the Price Cost Schedule and SOW. |
| 17 |
| [Will] there be demo of existing partitions needed to remove the old units? |
| To Be Published—Separate Amendment |
| 18 |
| Please confirm these units are not RTU’s. |
| To Be Published—Separate Amendment |
| 19 |
| Is there any reconfiguring of the exiting returns or supplies [required]? |
| To Be Published—Separate Amendment |
| 20 |
| [Will] there be any MEP Design work [required]? |
| To Be Published—Separate Amendment |
| 21 |
| Are there any as builds available? |
| To Be Published—Separate Amendment |
Responses are due to Mark Murray, mark.murray4@va.gov , NLT Friday, January 11th, 2019, 04:30 PM ET in order to be considered for award.
| Attachment |
| Title |
| Date |
| Number of Pages |
| 1 |
| Revised Statement of Work |
See attached document: P09 Statement of Work--FBO posted--01-04-2019.