Clean and Test Substations Switchgear at the Phildelphia VAMC. Federal contract opportunity
Solicitation number
36C24418Q0066
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 4

About this file

36C24418Q0066 00003 36C24418Q0066 00003.docx

View the file

Other files for this federal contract opportunity

Other files attached to Clean and Test Substations Switchgear at the Phildelphia VAMC., newest first.
File Type Posted
-13120.docx DOCX document
36C24418Q0066-00006000.docx DOCX document
36C24418Q0066-00005001.jpg JPG image
36C24418Q0066-00005003.jpg JPG image
36C24418Q0066-00005000.docx DOCX document
36C24418Q0066-00005004.jpg JPG image
36C24418Q0066-00005002.jpg JPG image
36C24418Q0066-00004000.docx DOCX document
36C24418Q0066-00002000.docx DOCX document
36C24418Q0066-00001000.docx DOCX document
36C24418Q0066-001.pdf PDF
36C24418Q0066-002.pdf PDF
36C24418Q0066-003.pdf PDF
36C24418Q0066-000.docx DOCX document
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C244-18-Q-0066 Amendment A00003

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE

OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

BY

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 00003 12-13-2017 None 00244 Department of Veterans Affairs Network Contracting Office 4 1700 South Lincoln Avenue Lebanon, PA 17042

00244 Department of Veterans Affairs Network Contracting Office 4 1700 South Lincoln Avenue Lebanon, PA 17042

To all Offerors/Bidders

36C24418Q0066 11-22-2017

X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to:

Friday, 01/12/2018 4:00 PM EST

See Attached Continuation Page

Julieanne M. Bartlett Contracting Officer

1. Amendment A00003 is hereby incorporated into RFQ number 36C244-18-Q-0066 and shall become part of any resultant Purchase Order. This amendment contains the following information:

a. Contractor Questions and Government Answers

b. An extension to the due date of this RFQ.

2. The following are Contractor Questions and Government Answers received:

Question 1: Can you please provide additional detail regarding the Medium Voltage Circuit Breaker specifications, Are they vacuum breakers?

Answer 1: Yes, the breakers in building 6 are type VR Vacuum Circuit Breakers. In building 16, 6 and 8, there are medium voltage fused disconnect switches.

Question 2: Please verify our assumption that all of the molded case circuit breakers have trip units that would allow for secondary injection. Will any of these units require primary injection testing?

Answer 2: I believe most of them do. There may be one or two that don’t.

Question 3: Typically, 3-phase XFMR’s under 500kVA and 1-phase xfmr’s under 100KVA do not require PF/Excitation unless specifically called out for. Do the 112.5kVA XFMR’s require power factor/excitation tests?

Answer 3: We do not need to do the power factor/excitation test.

Question 4: Typically, 3-phase XFMR’s under 500kVA and 1-phase xfmr’s under 100KVA do not require PF/Excitation unless specifically called out for. Do the 112.5kVA XFMR’s require power factor/excitation tests?

Answer 4: This information is not readily available, although it could have been obtained at the site visit that was made available to all interested vendors. In the past, contracted vendors have shown up with multiple types of test sets. The Government will provide additional clarification to this question in another amendment.

Question 5: Will the equipment requiring IR testing have appropriate loads to allow us to detect hot spots, or would this be under normal operating conditions? If additional loads are required, are required to supply load banks?

Answer 5: The system is an emergency system and has no load on it. It would be hard to transfer normal loads to the emergency system for an extended period of time. Vendors should bring in a load bank for the system. Vendors would need to provide a 1000 or 1500 KW load bank. .

3. The due date for this RFQ is extended as follows:

The last day to ask any questions is Friday, January, 5, 2018, at 2:00 PM EST.

All quotes must be received by FRIDAY, January 12, 2018 at 4:00 PM to be considered for award.

File details come from the government source that posted it.