852.236-72_Performance of Work by the Contractor - effective 01 Oct 2026.docx
VAAR Clause Oct 1, 2026 DOCX document 16 KB Posted
- Solicitation number
- 36C24227B0008
About this file
This file is a federal contract clause titled "Performance of Work by the Contractor" (852.236-72), effective October 2026, designated as a deviation clause for use in Department of Veterans Affairs construction contracts.
The clause establishes requirements for contractor performance and scheduling transparency. Under the basic provision, contractors must submit a statement concurrently with the contract schedule identifying which portions of work will be performed by the contractor's own forces. The approved schedule serves as the basis for determining work activity values under this clause. Any changes to established activity identifiers or responsibility codes for contractor-performed work require prior written approval from the Contracting Officer. The clause includes an alternate provision (Alternate I) applicable to contracts utilizing a Network Analysis Schedule, requiring contractors to submit responsibility codes for all network activities to be performed by the contractor's forces, with activity costs used to determine the total value of work executed by contractor personnel. This clause applies to the Batavia VAMC Salt Barn construction project (Solicitation 36C24227B0008), a Department of Veterans Affairs Veterans Integrated Service Network 2 project involving demolition of the existing salt barn, site preparation, electrical reconfiguration, earthwork, concrete work, asphalt installation, and roof installation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FAR 52.225-2 Buy American Certification.pdf | ||
| 852.236-80_Subcontracts and Work Coordination - effective 01 Oct 2026.docx | DOCX document | |
| 852.232-70 Payments Under Fixed-Price Construction Contracts Without NAS-CPM- effective 01 Oct 2026.docx | DOCX document | |
| Specifications 22 Total.zip | ZIP file | |
| 36C24227B0008_1.docx | DOCX document | |
| Drawings 5 Total.zip | ZIP file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
852.236-72 Performance of Work by the Contractor.
As prescribed in 836.101-770, insert the following clause:
PERFORMANCE OF WORK BY THE CONTRACTOR (OCT 2026)(DEVIATION)
(a) The Contractor must submit, simultaneously with the schedule required by the specifications of the contract, a statement designating the portions of contract work to be performed with the Contractor’s own forces. The approved schedule must be used in determining the value of a work activity/event, or portions thereof, of the work for the purpose of this article.
(b) Changes to established activity/event identifiers or responsibility codes for Contractor activities must not be made without approval from the Contracting Officer.
(End of clause)
Alternate I (OCT 2026)(DEVIATION)
For requirements which include a Network Analysis Schedule, substitute the following paragraph (a) for paragraph (a) of the basic clause above:
(a) The Contractor must submit, simultaneously with the cost per activity of the construction schedule required by the specifications of the contract, a responsibility code for all activities of the network for which the Contractor’s forces must perform the work. The cost of these activities must be used in determining the portions of the total contract work to be executed by the Contractor’s forces for the purpose of this article.