Question and Answers IFB 36C24224B0048 9-30-2024.docx
DOCX document 15 KB Posted
- Attached to
- Y1DA--Project Number: 561A4-21-101 Replace RF Unit Site Prep - Rm. 48 Lyons VAMC Federal contract opportunity
- Solicitation number
- 36C24224B0048
About this file
This document contains Questions and Answers related to Invitation for Bid (IFB) 36C24224B0048, which is for the Y1DA--Project Number: 561A4-21-101 "Replace RF Unit Site Prep - Rm. 48 Lyons VAMC" project.
The IFB includes the following scope of work: (1) General Construction, including demolition, new walls, floors, ceilings, finishes, and other alterations; (2) Mechanical work, including HVAC demolition and replacement; (3) Plumbing work, including demolition and replacement of steam, domestic, and medical gas systems; (4) Fire Protection work, including sprinkler head demolition and replacement; and (5) Electrical work, including demolition and replacement of power and lighting systems. The solicitation does not include any alternates. The contractor is not responsible for rigging and placing the RF equipment, as that will be handled by the RF equipment provider.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sign in Pre-Bid Site visit S05.pdf | ||
| 36C24224B0048 0001.docx | DOCX document | |
| Construction SOW 561A4-21-101 Replace RF Unit Site Prep - Rm 48 02.docx | DOCX document | |
| Wages.pdf | ||
| 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING-CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (DEVIATION).pdf | ||
| 561A4-21-101 Replace RF Unit Site Prep - Rm 48 Construction Drawings.pdf | ||
| 561A4-21-101 Replace RF Unit Site Prep - Rm 48 Specifications.pdf | ||
| 36C24224B0048_1.docx | DOCX document | |
| FAR 52.225-2 BUY AMERICAN CERTIFICATE.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers IFB 36C24224B0048 9-30-2024
1. Specification General requirement spaces 01-00 00-1 paragraph 1.3 The statement of work is for an entirely different Project (SPS), please send us the correct spec section.
Replace existing specification section 01 00 01 section 1.3 with the following:
0. STATEMENT OF BID ITEM(S)
0. ITEM I, GENERAL CONSTRUCTION: Work includes all labor, material, equipment and supervision to perform the required general construction work on this project including but not limited to; demolition of existing architectural items, new walls, new floor, new ceilings, new finishes, temporary facilities and any other addition/demolition alterations necessary for a complete and operable system.
0. Refer to section 1.6 phasing below and drawing GI-003 for ICRA Requirements.
0. ITEM II, MECHANICAL: Work includes all labor, material, equipment and supervision to perform the required mechanical construction work on this project including but not limited to; demolition of existing HVAC and steam systems, new ductwork, new diffusers and grills, new controls, pre and post air balancing of existing HVAC system and any other addition/demolition alterations necessary for a complete and operable system.
0. ITEM III, PLUMBING: Work includes all labor, material, equipment and supervision to perform the required plumbing construction work on this project including but not limited to;, demolition of steam/steam condensate/domestic/sanitary/venting/medical gas, new steam/steam condensate/domestic/sanitary/venting/medical gas, new plumbing fixtures and any other addition/demolition alterations necessary for a complete and operable system.
0. ITEM IV, FIRE PROTECTION: Work includes all labor, material, equipment and supervision to perform the required fire protection construction work on this project including but not limited to; demolition or relocation of existing sprinkler heads, new sprinkler heads, new fire protection piping and any other addition/demolition alterations necessary for a complete and operable system.
0. ITEM IV, ELECTRICAL: Work includes all labor, material, equipment and supervision to perform the required electrical construction work on this project including but not limited to; demolition of existing power and lighting systems, new power circuits, new RF power from basement, new lighting fixtures, and any other addition/demolition alterations necessary for a complete and operable system.
0. ALTERNATES: None
2. it is unclear who is responsible for rigging and placing the RF equipment in Place, if the contractor is responsible, please clarify how the equipment will be rigged.
Rigging of the RF equipment is not part of this contract and is the responsibility of the RF equipment provider.