Revised G-003 with Bed Count Summary.pdf
PDF 914 KB Posted
- Solicitation number
- 36C24221B0005
About this file
This document outlines a federal contract opportunity for renovations at the Syracuse VA Medical Center. The project provides for a complete renovation of the 8th floor Community Living Center over four phases to ensure continued care for patients. Work includes new interior finishes, asbestos and hazardous materials abatement, demolition and installation of walls, electrical, lighting, ceilings, floors, mechanical equipment, ductwork, plumbing, HVAC and controls. The period of performance is 515 calendar days with submittals due in 90 days, asbestos abatement in 60 days and construction in 365 days. The NAICS code is 236220 and this is a 100% SDVOSB set-aside. Firms must self-perform 15% of work and provide past performance ratings. Payment and performance bonds are required along with a 20% bid bond submitted with the bid. The estimated value is between $2-5 million.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24221B0005 0006.docx | DOCX document | |
| 36C24221B0005 0005_1.docx | DOCX document | |
| RFI 36C24221B0005 Renovate CLC 12-9-20-- 9 Dec 0005.docx | DOCX document | |
| 36C24221B0005 0004_1.docx | DOCX document | |
| 230923 rev Oct 2020 Siemens and JCI no POT.pdf | ||
| 528A7-18-739_Revised Dwg M-701-RFI.pdf | ||
| walk thru sign in sheet.pdf | ||
| RFI 3C24221B0005 Renovate CLC 8 December 2020.docx | DOCX document | |
| 36C24221B0005 0003_2.docx | DOCX document | |
| 36C24221B0005.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DUST CONTROL PLAN NOTES /
DUST CONTROL PLAN HAZARD ASSESSMENT
PRIOR TO INITIATING WORK, CONTRACTOR WILL ASSESS THE SCOPE OF THE CONSTRUCTION ACTIVITIES AND DETERMINE THE POTENTIAL RISK GROUPS INVOLVED BASED ON THE LOCATION OF ACTIVITIES AND EXTENT AND DURATION OF THE WORK. LOW RISK GROUPS ARE CONSIDERED "OFFICE WORKERS", MEDIUM RISK GROUPS ARE CONSIDERED ALL INPATIENT AND OUTPATIENT AREAS NOT IN THE HIGH RISK GROUP. HIGH RISK GROUP DESIGNATION INCLUDES INPATIENT AREAS SUCH AS PEDIATRIC AND ADULT OPERATING/DELIVERY ROOMS, CATH LABS, MYELO SUPPRESSION UNITS, ICUS, DIALYSIS, NURSERIES AS WELL AS CLINIC AREAS (CLINICS ASSOCIATED WITH HEMATOLOGY, ONCOLOGY, PEDIATRIC INFECTION DISEASE, OR TRANSPLANT SERVICES) AND SERVICE AREAS (CENTRAL PROCESSING, STERILE PROCESSING, FOOD PREP & SERVICE AREA AND PHARMACIES. THE VAMC INFECTION CONTROL GROUP WILL CONFIRM AND APPROVE THE DESIGNATION PROVIDED IN THIS SUBMITTED DUST CONTROL PLAN. VAMC IS ALSO RESPONSIBLE FOR ANY AND ALL INFECTION CONTROL MEASURES DETERMINED AND ESTABLISHED BY VAMC POLICY, SUCH AS THE RELOCATION OF HIGH RISK PATIENTS, APPROVING ALTERNATE TRAFFIC PATHS FOR CONSTRUCTION WORKERS OR ESTABLISH ALTERNATE TRAFFIC PATTERNS FOR STAFF, PATIENTS AND VISITORS. THE PLAN SHOULD BE REVISED ACCORDING TO
SPECIFIC VAMC POLICIES OR CHANGING CONDITIONS AT THE SITE AS THEY MAY OCCUR.
A. EXTERNAL DEMOLITION AND CONSTRUCTION ACTIVITIES
• DETERMINE IF THE IMPACTED AREAS OF THE FACILITY CAN OPERATE TEMPORARILY ON RECIRCULATED AIR; IF FEASIBLE
SEAL OFF ADJACENT AIR INTAKES.
• IF THIS IS NOT POSSIBLE OR PRACTICAL, CHECK THE LOW-EFFICIENCY FILTER BANKS FREQUENTLY AND
REPLACE AS NEEDED TO AVOID BUILDUP OF PARTICULATE.
• SEAL WINDOWS AND REDUCE WHEREVER POSSIBLE OTHER SOURCES OF OUTSIDE AIR INTRUSION (OPEN DOORS IN STAIRWELLS AND CORRIDORS) ESPECIALLY IN PROTECTIVE ENVIRONMENT (PE) AREAS.
B. INTERNAL DEMOLITION AND CONSTRUCTION ACTIVITIES DUST AND DEBRIS CONTROL
• BARRIER SYSTEMS: THE AREA SHOULD BE ISOLATED, AS THE PROJECT REQUIRES. SMALL, SHORT DURATION PROJECTS GENERATING MINIMAL DUST MAY USE FIRE-RATED PLASTIC SHEETING, BUT SHOULD BE SEALED AT FULL CEILING HEIGHT WITH AT LEAST 2-FOOT OVERLAPPING FLAPS FOR ACCESS TO ENTRY. PROJECTS THAT PRODUCE MODERATE TO HIGH LEVELS OF DUST REQUIRE RIGID, DUST-PROOF, AND FIRE-RATED BARRIER WALLS (E.G., DRYWALL) WITH CAULKED SEAMS FOR A TIGHT SEAL EXTENDING FLOOR TO CEILING. SEAL OFF AND BLOCK RETURN AIR VENTS IF RIGID BARRIERS ARE USED FOR CONTAINMENT. LARGE DUST PROJECTS NEED AN ENTRY VESTIBULE FOR CLOTHING CHANGES AND TOOL STORAGE AND TIGHT SEALS SHOULD BE MAINTAINED AT THE FULL PERIMETER OF WALLS AND WALL PENETRATIONS. AN INTERIM PLASTIC DUST BARRIER (MINIMUM 4-MIL) MAY BE REQUIRED TO PROTECT THE AREA WHILE THE RIGID IMPERVIOUS BARRIER IS BEING CONSTRUCTED. ANY DUST SHALL BE IMMEDIATELY CLEANED IF TRACKED OUTSIDE OF THE CONSTRUCTION BARRIER. UPON COMPLETION OF THE CONSTRUCTION PROJECT DUST BARRIERS SHALL BE REMOVED CAREFULLY TO MINIMIZE SPREADING OF DUST AND THE CONTRACTOR SHALL HAVE TEMPORARY DUST PROTECTION IN PLACE BEFORE REMOVAL OF A PERMANENT BARRIER. CONTRACTOR PERSONNEL SHALL MONITOR AND PERFORM BARRIER MAINTENANCE AND BE EDUCATED TO NOTICE SIMPLE CLUES SUCH AS ACCUMULATIONS OF VISIBLE DUST EVIDENCED BY FOOTPRINTS, OPENED DOORS/WINDOWS EVIDENCED BY
PRESENCE OF INSECTS AND FLIES, WET CEILING TILE, ETC.
• TRAFFIC CONTROL; DESIGNATED ENTRY AND EXIT PROCEDURES SHALL BE DEFINED. EGRESS PATHS SHOULD BE FREE OF DEBRIS; DESIGNATED ELEVATORS SHOULD BE USED DURING SCHEDULED TIMES; AND ONLY AUTHORIZED PERSONNEL SHOULD BE ALLOWED TO ENTER THE CONSTRUCTION ZONE. SIGNAGE SHOULD
DIRECT PEDESTRIAN TRAFFIC AWAY FROM THE CONSTRUCTION AREA AND MATERIALS.
• DEMOLITION DEBRIS: DEBRIS SHOULD BE REMOVED IN CARTS WITH TIGHTLY FITTED COVERS, USING DESIGNATED TRAFFIC ROUTES. EFFORTS SHOULD BE MADE TO MINIMIZE USE OF ELEVATORS WITH AN EMPHASIS ON TRANSPORT DURING THE LOWEST PERIOD OF ACTIVITY. DEBRIS SHOULD BE REMOVED DAILY AND AT TIMES SPECIFIED BY THE VAMC. IF CHUTES ARE USED TO DIRECT DEBRIS OUTSIDE, HIGH EFFICIENCY PARTICULATE AIR (HEPA) FILTERED NEGATIVE AIR MACHINES SHOULD BE USED, AND THE CHUTE OPENING SHOULD BE SEALED WHEN NOT IN USE. FILTERS SHOULD BE BAGGED AND SEALED BEFORE BEING TRANSPORTED OUT OF THE CONSTRUCTION AREA. THE CONTRACTOR SHALL NOT HAUL DEBRIS THROUGH
PATIENT-CARE AREAS WITH PRIOR APPROVAL OF THE VAMC.
• EXTERIOR WINDOWS: WINDOWS SHOULD BE SEALED TO MINIMIZE INFILTRATION FROM ANY ADJACENT
EXCAVATION DEBRIS.
• CEILINGS THAT ARE REMOVED/MODIFIED TO ALLOW CONSTRUCTION OF ICRA BARRIERS SHOULD BE
REINSTALLED TO PRE-CONSTRUCTION CONDITIONS.
VENTILATION AND ENVIRONMENTAL CONTROLS
• AIR SYSTEM FLOW: DETERMINE WHETHER THE CONSTRUCTION AREA USES FRESH/OUTSIDE OR
RECIRCULATED AIR; FILTERS SHOULD BE ADDED OR RETURN VENTS COVERED AS NEEDED WITH FILTER
MATERIAL OR PLASTIC. AIR MUST FLOW FROM CLEAN TO DIRTY AREAS.
• NEGATIVE AIR PRESSURE: THE AIR WITHIN THE CONSTRUCTION AREA MUST BE NEGATIVE WITH RESPECT TO SURROUNDING AREAS AND WITH NO DISRUPTION OF AIR SYSTEMS OF ADJACENT AREAS. USE OF THE NEGATIVE AIR PRESSURE SYSTEM WITHIN THE ENCLOSURE TO REMOVE DUST SHOULD PASS AIR THROUGH AN INDUSTRIAL GRADE, PORTABLE HEPA FILTER CAPABLE OF FILTRATION RATES OF 300-800 CUBIC FEET PER MINUTE (FT3//MIN), OR EXHAUST AIR DIRECTLY TO THE OUTSIDE IF APPROVED BY VAMC. IF EXHAUST MUST BE TIED INTO A RE-CIRCULATED AIR SYSTEM, A PRE-FILTER AND HEPA FILTER SHOULD BE USED BEFORE
EXHAUST TO PREVENT CONTAMINATION OF THE DUCTS.
• ADJACENT AREAS: THE STATUS OF SEALED PENETRATIONS AND INTACT CEILING SHOULD BE VERIFIED DAILY.
• AIR EXCHANGE RATES AND PRESSURE RELATIONSHIPS: VAMC AND/OR CONTRACTOR WILL VERIFY AND MAINTAIN PROPER RATES IN CRITICAL AREAS NEAR CONSTRUCTION ACTIVITY AND ENSURE AIR IS NOT BEING RE-CIRCULATED WITHOUT FILTRATION FROM THE CONSTRUCTION AREA ELSEWHERE. VAMC WILL MAKE DETERMINATION ON PROVIDING FOR THE ACCOUNTABILITY AND FREQUENCY OF TESTING AIR PRESSURE
THROUGHOUT THE PROJECT.
• MANOMETERS SHOULD BE LOCATED ON ICRA PARTITION DOOR AND ON THE NON-CONSTRUCTION SIDE OF THE
PARTITION.
CONTAMINATION
• WORKSITE CLOTHING: CONTRACTOR PERSONNEL CLOTHING SHOULD BE FREE OF LOOSE SOIL AND DEBRIS BEFORE LEAVING THE CONSTRUCTION AREA. IF PROTECTIVE APPAREL IS NOT WORK (E.G. COVERALLS, FOOTGEAR AND HEADGEAR) A HEPA-FILTERED VACUUM SHOULD BE USED TO REMOVE DUST FROM CLOTHING BEFORE LEAVING THE BARRICADE. IF PROTECTIVE APPAREL IS UTILIZED THE CONTRACTOR SHALL CONSTRUCT A SPACE OR ANTEROOM FOR CHANGING CLOTHING AND STORING EQUIPMENT (DESIGNATED AREA). ALL EQUIPMENT, TOOLS, TOOL CARTS, MATERIALS, ETC. TRANSPORTED THROUGH OCCUPIED AREAS SHALL BE MADE FREE FROM DUST AND MOISTURE BY VACUUMING AND WET WIPING BEFORE THEIR REMOVAL
FROM THE CONSTRUCTION ZONE OR WORK AREA.
• CONTRACTOR CLEANING: THE CONSTRUCTION ZONE SHOULD BE MAINTAINED IN A CLEAN MANNER BY CONTRACTORS AND SWEPT OR HEPA-VACUUMED DAILY FOR MORE FREQUENTLY AS NEEDED TO MINIMIZE DUST. ADJACENT AREAS THAT MAY BE IMPACTED BY THE CONSTRUCTION SHOULD BE DAMP MOPPED DAILY OR MORE FREQUENTLY AS NEEDED. WALK-OFF MATS WITH TACKY OR ADHESIVE SURFACES SHOULD BE
UTILIZED TO MINIMIZE TRACKING OF HEAVY DIRT AND DUST FROM CONSTRUCTION AREAS.
STEP #1: SELECT ACTIVITY TYPE BELOW:
CONSTRUCTION ACTIVITY TYPES:
TYPE A
INSPECTION AND NON-INVASIVE ACTIVITIES
INCLUDES, BUT NOT LIMITED TO:
• REMOVAL OF CEILING TILES FOR VISUAL INSPECTION LIMITED TO 1 TILE PER 50
SQUARE FEET.
• PAINTING (BUT NOT SANDING)
• WALL COVERING
• ELECTRICAL TRIM WORK
• MINOR PLUMBING
• ACTIVITIES WHICH DO NOT GENERATE DUST OR REQUIRE CUTTING OF WALLS
OR ACCESS TO CEILINGS OTHER THAN FOR VISUAL INSPECTION
TYPE B
SMALL SCALE, SHORT DURATION (less than 1 day) ACTIVITIES WHICH CREATE
MINIMAL DUST
INCLUDES, BUT NOT LIMITED TO:
• INSTALLATION OF TELEPHONE AND COMPUTER CABLING
• ACCESS TO CHASE SPACES
• CUTTING OF WALLS OR CEILING WHERE DUST MIGRATION CAN BE CONTROLLED
TYPE C
WORK THAT GENERATES A MODERATE TO HIGH LEVEL OF DUST OR REQUIRES
DEMOLITION OR REMOVAL OF ANY FIXED BUILDING COMPONENTS OR
ASSEMBLIES
INCLUDES, BUT NOT LIMITED TO:
• SANDING OF WALLS FOR PAINTING OR WALL COVERING
• REMOVAL OF FLOOR COVERING, CEILING TILES AND CASEWORK
• NEW WALL CONSTRUCTION
• MINOR DUCT WORK OR ELECTRICAL WORK ABOVE CEILINGS
• MAJOR CABLING ACTIVITIES
• ANY ACTIVITY WHICH CANNOT BE COMPLETED WITHIN A SINGLE WORK SHIFT
TYPE D
MAJOR DEMOLITION AND CONSTRUCTION PROJECTS
INCLUDES, BUT NOT LIMITED TO:
• ACTIVITIES THAT REQUIRE CONSECUTIVE WORK SHIFTS.
• REQUIRES HEAVY DEMOLITION OR REMOVAL OF A COMPLETE CABLING
SYSTEM.
• NEW CONSTRUCTION
IS IT LIKELY THE CONTRACTOR'S STAFF WILL BE PLACED AT RISK FOR INFECTION
WITH TUBERCULOSIS? YES / NO
IS IT LIKELY THERE WILL BE PHYSICAL DISRUPTION OF THE WATER
SYSTEM/LINES DURING ACTIVITY? YES / NO
STEP #2: SELECT RISK GROUP BELOW AND MARK BOTTOM OF COLUMN
A) INFECTION CONTROL RISK GROUPS
GROUP 1 - LOW: OFFICE AREAS
GROUP 2 - MEDIUM: CARDIOLOGY, ECHOCARDIOGRAPHY, ENDOSCOPY, NUCLEAR
MEDICINE, PHYSICAL THERAPY, RADIOLOGY/MRI, RESPIRATORY THERAPY
GROUP 3 - HIGH RISK: CCU, EMERGENCY ROOM, LABORATORIES, OUTPATIENT
SURGERY, PHARMACY, POST ANESTHESIA CARE UNIT, SURGICAL UNITS
GROUP 4 - HIGHEST RISK: ANY AREA CARING FOR IMMUNOCOMPROMISED
PATIENTS, CARDIAC CATH LAB, CENTRAL SUPPLY, INTENSIVE CARE UNITS,
MEDICAL UNITS, NEGATIVE AIRFLOW ROOMS, ONCOLOGY, OPERATING ROOMS
STEP #3: DETERMINE CLASS OF PRECAUTIONS USING MATRIX BELOW:
CONSTRUCTION ACTIVITY / INFECTION CONTROL MATRIX TO DETERMINE CLASS
** ICN MUST BE CONSULTED WHEN THE ASSESSMENT INDICATES THAT CLASS II,
III, IV PRECAUTIONS ARE REQUIRED.
INFECTION CONTROL RISK ASSESSMENT FOR CONSTRUCTION
(TO BE COMPLETED BY CONTRACTOR & SIGNED BY INFECTION CONTROL VA PERSONNEL)
STEP #4: COMPLETE THE INFECTION CONTROL CONSTRUCTION PERMIT:
CLASS I - DURING CONSTRUCTION PROJECT
1. EXECUTE WORK BY METHOD TO MINIMIZE RAISING DUST FROM CONSTRUCTION
OPERATIONS
2. IMMEDIATELY REPLACE A CEILING TILE DISPLACED FOR VISUAL INSPECTION
CLASS II - DURING CONSTRUCTION PROJECT
1. PROVIDE ACTIVE MEANS TO PREVENT AIRBORNE DUST FROM DISPERSING INTO
ATMOSPHERE.
2. WATER MIST WORK SURFACES TO CONTROL DUST WHILE CUTTING
3. SEAL UNUSED DOORS WITH DUCT TAPE
4. BLOCK OFF AND SEAL AIR VENTS.
5. PLACE DUST MAT AT ENTRANCE AND EXIT OF WORK AREA.
6. REMOVE OR ISOLATE HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.
CLASS III - DURING CONSTRUCTION PROJECT
1. REMOVE OR ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT
CONTAMINATION OF DUCT SYSTEM.
2. COMPLETE ALL CRITICAL BARRIERS, I.E. SHEETROCK, PLYWOOD, PLASTIC, TO SEAL AREA
FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE METHOD (CART WITH PLASTIC
COVERING & SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR VACUUMING
PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS.
3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORKSITE UTILIZING HEPA-EQUIPPED AIR
FILTRATION UNITS.
4. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORTATION IN TIGHTLY COVERED
CONTAINERS.
5. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS SOLID LID IS
USED.
CLASS IV- DURING CONSTRUCTION PROJECT
1. ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT
CONTAMINATION OF DUCT SYSTEM.
2. COMPLETE ALL CRITICAL BARRIERS, I.E., SHEETROCK, PLYWOOD, PLASTIC, TO SEAL AREA
FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE METHOD (CART WITH PLASTIC
COVERING & SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR VACUUMING
PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS.
3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORKSITE UTILIZING HEPA-EQUIPPED AIR
FILTRATION UNITS.
4. SEAL HOLES, PIPES, CONDUITS AND PUNCTURES APPROPRIATELY.
5. CONSTRUCT ANTEROOM AND REQUIRE ALL PERSONNEL TO PASS THROUGH THIS ROOM
SO THEY CAN BE VACUUMED USING A HEPA VACUUM CLEANER BEFORE LEAVING WORK SITE;
OR THE CAN WEAR CLOTH OR PAPER COVERALLS THAT ARE REMOVED EACH TIME THEY
LEAVE THE WORK SITE.
6. ALL PERSONNEL ENTERING THE WORK SITE ARE REQUIRED TO WEAR SHOE COVERS.
SHOE COVERS MUST BE CHANGED EACH TIME THE WORKER EXITS THE WORK AREA.
7. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT IS INSPECTED
BY SAFETY MANAGEMENT & INFECTION CONTROL & THOROUGHLY CLEANED BY
ENVIRONMENTAL MANAGEMENT.
CLASS I - UPON COMPLETION OF PROJECTS
1. CLEAN WORK UPON COMPLETION OF TASK
CLASS II - UPON COMPLETION OF PROJECTS
1. WIPE WORK SURFACES WITH DISINFECTANT.
2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED
CONTAINERS.
3. WET MOP &/OR VACUUM BEFORE LEAVING WORK AREA.
4. REMOVE ISOLATION OF HVAC SYSTEM IN AREA WHERE WORK IS BEING PERFORMED.
CLASS III - UPON COMPLETION OF PROJECTS
1. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT IS INSPECTED
BY SAFETY MANAGEMENT & INFECTION CONTROL & THOROUGHLY CLEANED BY
ENVIRONMENTAL MANAGEMENT.
2. REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE SPREADING OF DIRT & DEBRIS
ASSOCIATED WITH CONSTRUCTION.
3. VACUUM WORK AREA WITH HEPA-FILTERED VACUUMS.
4. WET MOP WITH DISINFECTANT.
5. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.
CLASS IV - UPON COMPLETION OF PROJECTS
1. REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE SPREADING OF DIRT & DEBRIS
ASSOCIATED WITH CONSTRUCTION.
2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED
CONTAINERS.
3. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS SOLID LID.
4. VACUUM WORK AREA WITH HEPA-FILTERED VACUUMS.
5. WET MOP WITH DISINFECTANT.
6. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.
CONTRACTOR'S SIGNATURE AND DATE
INFECTION CONTROL PERSONNEL SIGNATURE AND DATE
PHASING DIAGRAM W/ EXISTING PLAN
NOT TO SCALE
PHASING DIAGRAM W/ NEW CONSTRUCTION PLAN
NOT TO SCALE
PHASE 1
PHASE 1
PHASE 2
PHASE 3A/3B
PHASE 4 - TO TAKE PLACE OFF OF MAIN VISITING HOURS
ICRA BARRIER LOCATION, REFERENCE DETAIL 1/G-003
GENERAL NOTE: TWO MEANS OF EGRESS AND
EGRESS SIGNAGE TO THOSE MEANS MUST BE
MAINTAINED DURING EACH PHASE OF
CONSTRUCTION.
ALL PHASES TO BE COORDINATED WITH FACILITY
MANAGEMENT FOR APPROVAL OF CONTROLS, (ICRA,
SIGNAGE, ETC.)
PHASE 1
PHASE 1
PHASE 2
PHASE 3A/B
PHASE 4 - TO TAKE PLACE OFF OF MAIN VISITING HOURS
ICRA BARRIER LOCATION, REFERENCE DETAIL 1/G-003
RISK LEVEL TYPE 'A' TYPE 'B' TYPE 'C' TYPE 'D'
GROUP 1 I II II III / IV
GROUP 2 I II II IV
GROUP 3 I II III / IV
GROUP 4 II III / IV
CONSTRUCTION TYPE: D RISK GROUP: MEDIUM RISK ASSESSMENT: IV
III / IV
IV
IV
PROJECTED UTILITY OUTAGES IMPACTING INFECTION CONTROL
ELECTRICAL:
YES
POTABLE WATER:
YES
HVAC:
YES
MEDICAL VACUUM:
YES
SEWER:
YES
MTL STUD FR - REF SCHED FOR SIZE,
SPACING & WIDTH AS SPEC
U.N.O. (2) LAYER 5/8" TYPE "X" GYP BD
EACH SIDE - 2 HR RATED, UL 419
UNDERSIDE OF STRUCTURE
BASE
PLAN
HEAD
SCHED CEILING, REF RCP
STEEL TRACK, FASTEN 2'-0" OC MAX
ACOUSTIC SEALANT BOTH SIDES. FIRE RATED
SEALANT BOTH SIDES WHERE REQUIRED BY UL 419.
STEEL TRACK, FASTEN 2'-0" OC MAX
ICRA GENERAL NOTES:
1. FOR EXISTING PARTITIONS USED AS ICRA BARRIERS, THE CONTRACTOR SHALL COMPLETE THE
FOLLOWING:
• MODIFY EXISTING PARTITION TO TWO-HOUR RATED ICRA BARRIER
• EXTEND PARTITION TO FLOOR DECK WITH 5/8" GYP BD ON EACH SIDE, REF TYP DTL 1/G-002
• FINISH WALL PARTITION AS DIRECTED BY UL RATING REQUIREMENTS
• INFILL EXISTING OPENINGS WITH 5/8" GYP BD ON EACH SIDE
• PROVIDE FIRESTOPPING AT ALL EXISTING PENETRATIONS
2. PROVIDE 90 MINUTE RATED DOOR TO ACCESS CONSTRUCTION AREA AT ALL NEW AND
EXISTING ICRA BARRIERS
3. THE CONTRACTOR SHALL NOT BLOCK SPRINKLER PROTECTION ON THE VA-OCCUPIED SIDE OF
ANY ICRA BARRIER
AREA OF DISRUPTION - GENERAL NOTES
EXISTING LEVEL BELOW 8TH FLOOR CLC IS HOME TO MULTIPLE DIFFERENT OCCUPANCIES. COORDINATE WITH VA AND COR TO PLAN OUT AREA OF DISRUPTION DURING EACH PHASE OF CONSTRUCTION WHEN CONTRACTOR IS REQUIRED TO WORK FROM LEVEL BELOW. ALL CONSTRUCTION IS TO COMPLY WITH VA STANDARDS PER EACH TYPE OF OCCUPANCY. LISTED BELOW:
• 7A (BELOW 8A) IS ADMINISTRATION OFFICES : CONSTRUCTION TO BE DONE AFTER HOURS AND NO MORE
THAN ONE ROOM AT A TIME.
• 7B (BELOW 8B) IS PATIENT CARE AREA W/ PATIENTS RESIDING AT ALL HOURS : ICRA ENCLOSURES REQUIRED ON OUTSIDE OF DOORS TO ROOMS DURING CONSTRUCTION. USE NEGATIVE AIR PRESSURE AS NEEDED.
CONSTRUCTION TO BE DONE DURING NORMAL HOSPITAL HOURS.
• 7C (BELOW 8C) IS PATIENT CARE AREA WITH CONTROLLED ACCESS. VA COR WILL GRANT ACCESS DAILY, MAX TWO PERSON WORK CREW. ICRA ENCLOSURES ON INSIDE OF DOOR TO ROOMS DURING
CONSTRUCTION. TOOLS, BELONGINGS, CONSTRUCTION MATERIAL ETC. NOT TO BE LEFT UNATTENDED. ALL WORK RELATED BELONGINGS TO BE REMOVED BEFORE END OF SHIFT. CONSTRUCTION TO BE DONE
DURING NORMAL HOSPITAL HOURS AND NO MORE THAN ONE ROOM AT A TIME.
ALL ROOMS LOCATED ON THE 7TH FLOOR IN THE AREA OF DISRUPTION TO RECEIVE LOCK CHANGE FOR THE DURATION OF
CONSTRUCTION. COORDINATE WITH COR.
ALL ROOMS REQUIRE VA PERSONNEL TO REMOVE EXISTING EQUIPMENT BEFORE CONSTRUCTION. COORDINATE WITH COR.
ALL ROOMS TO BE CLEANED BY GENERAL CONTRACTOR AT END OF SHIFT.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
Sprinkler Status
AE Works, LTD.
209 Sandusky Street Pittsburgh, PA 15212 Phone: 412-287-7333 www.ae-works.com G-003
PHASING PLAN & ICRA
INFORMATION
SYRACUSE VAMC 8TH
FLOOR CLC RENOVATION
800 Irving Ave, Syracuse VA, New York 13210
528A7-18-739
MAY 22, 2020 RS ZS
BID DOCUMENTS
1 PARTITION - TYPICAL ICRA BARRIER
# Revisions Date
COMBINED NEW PHASE 1
PHASE 2
PHASE 3A
PHASE 3B
PHASE 4
PHASE2
PHASE 3A
PHASE 3B
PHASE 1 COMBINED
THIS SEGMENT OF CONSTRUCTION BARRIER TO REMAIN
IN PLACE UNTIL PROJECT IS COMPLETE. DURING PHASE 3A AND 3B
CONTRACTOR REQUIRED TO PROVIDE APPLICABLE
PATIENT ACCESS AT ALL TIMES.
COMBINED NEW PHASE 1
PHASE 2
PHASE 3A
PHASE 3B
PHASE 4
COMBINED PHASE 1
PHASE 2
PHASE 3A
PHASE 3B
THIS SEGMENT OF CONSTRUCTION BARRIER TO REMAIN IN PLACE UNTIL
PROJECT IS COMPLETED. DURING PHASE 3A AND 3B, CONTRACTOR
REQUIRED TO PROVIDE APPLICABLE PATIENT ACCESS AT ALL TIMES
File details come from the government source that posted it. Updated .