Revised G-003 with Bed Count Summary.pdf

PDF 914 KB Posted

Attached to
Z1DA--528A7-18-739 COVID-19: RENOVATE 8TH FLOOR CLC
Solicitation number
36C24221B0005
Issued by

About this file

This document outlines a federal contract opportunity for renovations at the Syracuse VA Medical Center. The project provides for a complete renovation of the 8th floor Community Living Center over four phases to ensure continued care for patients. Work includes new interior finishes, asbestos and hazardous materials abatement, demolition and installation of walls, electrical, lighting, ceilings, floors, mechanical equipment, ductwork, plumbing, HVAC and controls. The period of performance is 515 calendar days with submittals due in 90 days, asbestos abatement in 60 days and construction in 365 days. The NAICS code is 236220 and this is a 100% SDVOSB set-aside. Firms must self-perform 15% of work and provide past performance ratings. Payment and performance bonds are required along with a 20% bid bond submitted with the bid. The estimated value is between $2-5 million.

View the file

Other files

File Type Posted
36C24221B0005 0006.docx DOCX document
36C24221B0005 0005_1.docx DOCX document
RFI 36C24221B0005 Renovate CLC 12-9-20-- 9 Dec 0005.docx DOCX document
36C24221B0005 0004_1.docx DOCX document
230923 rev Oct 2020 Siemens and JCI no POT.pdf PDF
528A7-18-739_Revised Dwg M-701-RFI.pdf PDF
walk thru sign in sheet.pdf PDF
RFI 3C24221B0005 Renovate CLC 8 December 2020.docx DOCX document
36C24221B0005 0003_2.docx DOCX document
36C24221B0005.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DUST CONTROL PLAN NOTES /

DUST CONTROL PLAN HAZARD ASSESSMENT

PRIOR TO INITIATING WORK, CONTRACTOR WILL ASSESS THE SCOPE OF THE CONSTRUCTION ACTIVITIES AND DETERMINE THE POTENTIAL RISK GROUPS INVOLVED BASED ON THE LOCATION OF ACTIVITIES AND EXTENT AND DURATION OF THE WORK. LOW RISK GROUPS ARE CONSIDERED "OFFICE WORKERS", MEDIUM RISK GROUPS ARE CONSIDERED ALL INPATIENT AND OUTPATIENT AREAS NOT IN THE HIGH RISK GROUP. HIGH RISK GROUP DESIGNATION INCLUDES INPATIENT AREAS SUCH AS PEDIATRIC AND ADULT OPERATING/DELIVERY ROOMS, CATH LABS, MYELO SUPPRESSION UNITS, ICUS, DIALYSIS, NURSERIES AS WELL AS CLINIC AREAS (CLINICS ASSOCIATED WITH HEMATOLOGY, ONCOLOGY, PEDIATRIC INFECTION DISEASE, OR TRANSPLANT SERVICES) AND SERVICE AREAS (CENTRAL PROCESSING, STERILE PROCESSING, FOOD PREP & SERVICE AREA AND PHARMACIES. THE VAMC INFECTION CONTROL GROUP WILL CONFIRM AND APPROVE THE DESIGNATION PROVIDED IN THIS SUBMITTED DUST CONTROL PLAN. VAMC IS ALSO RESPONSIBLE FOR ANY AND ALL INFECTION CONTROL MEASURES DETERMINED AND ESTABLISHED BY VAMC POLICY, SUCH AS THE RELOCATION OF HIGH RISK PATIENTS, APPROVING ALTERNATE TRAFFIC PATHS FOR CONSTRUCTION WORKERS OR ESTABLISH ALTERNATE TRAFFIC PATTERNS FOR STAFF, PATIENTS AND VISITORS. THE PLAN SHOULD BE REVISED ACCORDING TO

SPECIFIC VAMC POLICIES OR CHANGING CONDITIONS AT THE SITE AS THEY MAY OCCUR.

A. EXTERNAL DEMOLITION AND CONSTRUCTION ACTIVITIES

• DETERMINE IF THE IMPACTED AREAS OF THE FACILITY CAN OPERATE TEMPORARILY ON RECIRCULATED AIR; IF FEASIBLE

SEAL OFF ADJACENT AIR INTAKES.

• IF THIS IS NOT POSSIBLE OR PRACTICAL, CHECK THE LOW-EFFICIENCY FILTER BANKS FREQUENTLY AND

REPLACE AS NEEDED TO AVOID BUILDUP OF PARTICULATE.

• SEAL WINDOWS AND REDUCE WHEREVER POSSIBLE OTHER SOURCES OF OUTSIDE AIR INTRUSION (OPEN DOORS IN STAIRWELLS AND CORRIDORS) ESPECIALLY IN PROTECTIVE ENVIRONMENT (PE) AREAS.

B. INTERNAL DEMOLITION AND CONSTRUCTION ACTIVITIES DUST AND DEBRIS CONTROL

• BARRIER SYSTEMS: THE AREA SHOULD BE ISOLATED, AS THE PROJECT REQUIRES. SMALL, SHORT DURATION PROJECTS GENERATING MINIMAL DUST MAY USE FIRE-RATED PLASTIC SHEETING, BUT SHOULD BE SEALED AT FULL CEILING HEIGHT WITH AT LEAST 2-FOOT OVERLAPPING FLAPS FOR ACCESS TO ENTRY. PROJECTS THAT PRODUCE MODERATE TO HIGH LEVELS OF DUST REQUIRE RIGID, DUST-PROOF, AND FIRE-RATED BARRIER WALLS (E.G., DRYWALL) WITH CAULKED SEAMS FOR A TIGHT SEAL EXTENDING FLOOR TO CEILING. SEAL OFF AND BLOCK RETURN AIR VENTS IF RIGID BARRIERS ARE USED FOR CONTAINMENT. LARGE DUST PROJECTS NEED AN ENTRY VESTIBULE FOR CLOTHING CHANGES AND TOOL STORAGE AND TIGHT SEALS SHOULD BE MAINTAINED AT THE FULL PERIMETER OF WALLS AND WALL PENETRATIONS. AN INTERIM PLASTIC DUST BARRIER (MINIMUM 4-MIL) MAY BE REQUIRED TO PROTECT THE AREA WHILE THE RIGID IMPERVIOUS BARRIER IS BEING CONSTRUCTED. ANY DUST SHALL BE IMMEDIATELY CLEANED IF TRACKED OUTSIDE OF THE CONSTRUCTION BARRIER. UPON COMPLETION OF THE CONSTRUCTION PROJECT DUST BARRIERS SHALL BE REMOVED CAREFULLY TO MINIMIZE SPREADING OF DUST AND THE CONTRACTOR SHALL HAVE TEMPORARY DUST PROTECTION IN PLACE BEFORE REMOVAL OF A PERMANENT BARRIER. CONTRACTOR PERSONNEL SHALL MONITOR AND PERFORM BARRIER MAINTENANCE AND BE EDUCATED TO NOTICE SIMPLE CLUES SUCH AS ACCUMULATIONS OF VISIBLE DUST EVIDENCED BY FOOTPRINTS, OPENED DOORS/WINDOWS EVIDENCED BY

PRESENCE OF INSECTS AND FLIES, WET CEILING TILE, ETC.

• TRAFFIC CONTROL; DESIGNATED ENTRY AND EXIT PROCEDURES SHALL BE DEFINED. EGRESS PATHS SHOULD BE FREE OF DEBRIS; DESIGNATED ELEVATORS SHOULD BE USED DURING SCHEDULED TIMES; AND ONLY AUTHORIZED PERSONNEL SHOULD BE ALLOWED TO ENTER THE CONSTRUCTION ZONE. SIGNAGE SHOULD

DIRECT PEDESTRIAN TRAFFIC AWAY FROM THE CONSTRUCTION AREA AND MATERIALS.

• DEMOLITION DEBRIS: DEBRIS SHOULD BE REMOVED IN CARTS WITH TIGHTLY FITTED COVERS, USING DESIGNATED TRAFFIC ROUTES. EFFORTS SHOULD BE MADE TO MINIMIZE USE OF ELEVATORS WITH AN EMPHASIS ON TRANSPORT DURING THE LOWEST PERIOD OF ACTIVITY. DEBRIS SHOULD BE REMOVED DAILY AND AT TIMES SPECIFIED BY THE VAMC. IF CHUTES ARE USED TO DIRECT DEBRIS OUTSIDE, HIGH EFFICIENCY PARTICULATE AIR (HEPA) FILTERED NEGATIVE AIR MACHINES SHOULD BE USED, AND THE CHUTE OPENING SHOULD BE SEALED WHEN NOT IN USE. FILTERS SHOULD BE BAGGED AND SEALED BEFORE BEING TRANSPORTED OUT OF THE CONSTRUCTION AREA. THE CONTRACTOR SHALL NOT HAUL DEBRIS THROUGH

PATIENT-CARE AREAS WITH PRIOR APPROVAL OF THE VAMC.

• EXTERIOR WINDOWS: WINDOWS SHOULD BE SEALED TO MINIMIZE INFILTRATION FROM ANY ADJACENT

EXCAVATION DEBRIS.

• CEILINGS THAT ARE REMOVED/MODIFIED TO ALLOW CONSTRUCTION OF ICRA BARRIERS SHOULD BE

REINSTALLED TO PRE-CONSTRUCTION CONDITIONS.

VENTILATION AND ENVIRONMENTAL CONTROLS

• AIR SYSTEM FLOW: DETERMINE WHETHER THE CONSTRUCTION AREA USES FRESH/OUTSIDE OR

RECIRCULATED AIR; FILTERS SHOULD BE ADDED OR RETURN VENTS COVERED AS NEEDED WITH FILTER

MATERIAL OR PLASTIC. AIR MUST FLOW FROM CLEAN TO DIRTY AREAS.

• NEGATIVE AIR PRESSURE: THE AIR WITHIN THE CONSTRUCTION AREA MUST BE NEGATIVE WITH RESPECT TO SURROUNDING AREAS AND WITH NO DISRUPTION OF AIR SYSTEMS OF ADJACENT AREAS. USE OF THE NEGATIVE AIR PRESSURE SYSTEM WITHIN THE ENCLOSURE TO REMOVE DUST SHOULD PASS AIR THROUGH AN INDUSTRIAL GRADE, PORTABLE HEPA FILTER CAPABLE OF FILTRATION RATES OF 300-800 CUBIC FEET PER MINUTE (FT3//MIN), OR EXHAUST AIR DIRECTLY TO THE OUTSIDE IF APPROVED BY VAMC. IF EXHAUST MUST BE TIED INTO A RE-CIRCULATED AIR SYSTEM, A PRE-FILTER AND HEPA FILTER SHOULD BE USED BEFORE

EXHAUST TO PREVENT CONTAMINATION OF THE DUCTS.

• ADJACENT AREAS: THE STATUS OF SEALED PENETRATIONS AND INTACT CEILING SHOULD BE VERIFIED DAILY.

• AIR EXCHANGE RATES AND PRESSURE RELATIONSHIPS: VAMC AND/OR CONTRACTOR WILL VERIFY AND MAINTAIN PROPER RATES IN CRITICAL AREAS NEAR CONSTRUCTION ACTIVITY AND ENSURE AIR IS NOT BEING RE-CIRCULATED WITHOUT FILTRATION FROM THE CONSTRUCTION AREA ELSEWHERE. VAMC WILL MAKE DETERMINATION ON PROVIDING FOR THE ACCOUNTABILITY AND FREQUENCY OF TESTING AIR PRESSURE

THROUGHOUT THE PROJECT.

• MANOMETERS SHOULD BE LOCATED ON ICRA PARTITION DOOR AND ON THE NON-CONSTRUCTION SIDE OF THE

PARTITION.

CONTAMINATION

• WORKSITE CLOTHING: CONTRACTOR PERSONNEL CLOTHING SHOULD BE FREE OF LOOSE SOIL AND DEBRIS BEFORE LEAVING THE CONSTRUCTION AREA. IF PROTECTIVE APPAREL IS NOT WORK (E.G. COVERALLS, FOOTGEAR AND HEADGEAR) A HEPA-FILTERED VACUUM SHOULD BE USED TO REMOVE DUST FROM CLOTHING BEFORE LEAVING THE BARRICADE. IF PROTECTIVE APPAREL IS UTILIZED THE CONTRACTOR SHALL CONSTRUCT A SPACE OR ANTEROOM FOR CHANGING CLOTHING AND STORING EQUIPMENT (DESIGNATED AREA). ALL EQUIPMENT, TOOLS, TOOL CARTS, MATERIALS, ETC. TRANSPORTED THROUGH OCCUPIED AREAS SHALL BE MADE FREE FROM DUST AND MOISTURE BY VACUUMING AND WET WIPING BEFORE THEIR REMOVAL

FROM THE CONSTRUCTION ZONE OR WORK AREA.

• CONTRACTOR CLEANING: THE CONSTRUCTION ZONE SHOULD BE MAINTAINED IN A CLEAN MANNER BY CONTRACTORS AND SWEPT OR HEPA-VACUUMED DAILY FOR MORE FREQUENTLY AS NEEDED TO MINIMIZE DUST. ADJACENT AREAS THAT MAY BE IMPACTED BY THE CONSTRUCTION SHOULD BE DAMP MOPPED DAILY OR MORE FREQUENTLY AS NEEDED. WALK-OFF MATS WITH TACKY OR ADHESIVE SURFACES SHOULD BE

UTILIZED TO MINIMIZE TRACKING OF HEAVY DIRT AND DUST FROM CONSTRUCTION AREAS.

STEP #1: SELECT ACTIVITY TYPE BELOW:

CONSTRUCTION ACTIVITY TYPES:

TYPE A

INSPECTION AND NON-INVASIVE ACTIVITIES

INCLUDES, BUT NOT LIMITED TO:

• REMOVAL OF CEILING TILES FOR VISUAL INSPECTION LIMITED TO 1 TILE PER 50

SQUARE FEET.

• PAINTING (BUT NOT SANDING)

• WALL COVERING

• ELECTRICAL TRIM WORK

• MINOR PLUMBING

• ACTIVITIES WHICH DO NOT GENERATE DUST OR REQUIRE CUTTING OF WALLS

OR ACCESS TO CEILINGS OTHER THAN FOR VISUAL INSPECTION

TYPE B

SMALL SCALE, SHORT DURATION (less than 1 day) ACTIVITIES WHICH CREATE

MINIMAL DUST

INCLUDES, BUT NOT LIMITED TO:

• INSTALLATION OF TELEPHONE AND COMPUTER CABLING

• ACCESS TO CHASE SPACES

• CUTTING OF WALLS OR CEILING WHERE DUST MIGRATION CAN BE CONTROLLED

TYPE C

WORK THAT GENERATES A MODERATE TO HIGH LEVEL OF DUST OR REQUIRES

DEMOLITION OR REMOVAL OF ANY FIXED BUILDING COMPONENTS OR

ASSEMBLIES

INCLUDES, BUT NOT LIMITED TO:

• SANDING OF WALLS FOR PAINTING OR WALL COVERING

• REMOVAL OF FLOOR COVERING, CEILING TILES AND CASEWORK

• NEW WALL CONSTRUCTION

• MINOR DUCT WORK OR ELECTRICAL WORK ABOVE CEILINGS

• MAJOR CABLING ACTIVITIES

• ANY ACTIVITY WHICH CANNOT BE COMPLETED WITHIN A SINGLE WORK SHIFT

TYPE D

MAJOR DEMOLITION AND CONSTRUCTION PROJECTS

INCLUDES, BUT NOT LIMITED TO:

• ACTIVITIES THAT REQUIRE CONSECUTIVE WORK SHIFTS.

• REQUIRES HEAVY DEMOLITION OR REMOVAL OF A COMPLETE CABLING

SYSTEM.

• NEW CONSTRUCTION

IS IT LIKELY THE CONTRACTOR'S STAFF WILL BE PLACED AT RISK FOR INFECTION

WITH TUBERCULOSIS? YES / NO

IS IT LIKELY THERE WILL BE PHYSICAL DISRUPTION OF THE WATER

SYSTEM/LINES DURING ACTIVITY? YES / NO

STEP #2: SELECT RISK GROUP BELOW AND MARK BOTTOM OF COLUMN

A) INFECTION CONTROL RISK GROUPS

GROUP 1 - LOW: OFFICE AREAS

GROUP 2 - MEDIUM: CARDIOLOGY, ECHOCARDIOGRAPHY, ENDOSCOPY, NUCLEAR

MEDICINE, PHYSICAL THERAPY, RADIOLOGY/MRI, RESPIRATORY THERAPY

GROUP 3 - HIGH RISK: CCU, EMERGENCY ROOM, LABORATORIES, OUTPATIENT

SURGERY, PHARMACY, POST ANESTHESIA CARE UNIT, SURGICAL UNITS

GROUP 4 - HIGHEST RISK: ANY AREA CARING FOR IMMUNOCOMPROMISED

PATIENTS, CARDIAC CATH LAB, CENTRAL SUPPLY, INTENSIVE CARE UNITS,

MEDICAL UNITS, NEGATIVE AIRFLOW ROOMS, ONCOLOGY, OPERATING ROOMS

STEP #3: DETERMINE CLASS OF PRECAUTIONS USING MATRIX BELOW:

CONSTRUCTION ACTIVITY / INFECTION CONTROL MATRIX TO DETERMINE CLASS

** ICN MUST BE CONSULTED WHEN THE ASSESSMENT INDICATES THAT CLASS II,

III, IV PRECAUTIONS ARE REQUIRED.

INFECTION CONTROL RISK ASSESSMENT FOR CONSTRUCTION

(TO BE COMPLETED BY CONTRACTOR & SIGNED BY INFECTION CONTROL VA PERSONNEL)

STEP #4: COMPLETE THE INFECTION CONTROL CONSTRUCTION PERMIT:

CLASS I - DURING CONSTRUCTION PROJECT

1. EXECUTE WORK BY METHOD TO MINIMIZE RAISING DUST FROM CONSTRUCTION

OPERATIONS

2. IMMEDIATELY REPLACE A CEILING TILE DISPLACED FOR VISUAL INSPECTION

CLASS II - DURING CONSTRUCTION PROJECT

1. PROVIDE ACTIVE MEANS TO PREVENT AIRBORNE DUST FROM DISPERSING INTO

ATMOSPHERE.

2. WATER MIST WORK SURFACES TO CONTROL DUST WHILE CUTTING

3. SEAL UNUSED DOORS WITH DUCT TAPE

4. BLOCK OFF AND SEAL AIR VENTS.

5. PLACE DUST MAT AT ENTRANCE AND EXIT OF WORK AREA.

6. REMOVE OR ISOLATE HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.

CLASS III - DURING CONSTRUCTION PROJECT

1. REMOVE OR ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT

CONTAMINATION OF DUCT SYSTEM.

2. COMPLETE ALL CRITICAL BARRIERS, I.E. SHEETROCK, PLYWOOD, PLASTIC, TO SEAL AREA

FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE METHOD (CART WITH PLASTIC

COVERING & SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR VACUUMING

PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS.

3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORKSITE UTILIZING HEPA-EQUIPPED AIR

FILTRATION UNITS.

4. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORTATION IN TIGHTLY COVERED

CONTAINERS.

5. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS SOLID LID IS

USED.

CLASS IV- DURING CONSTRUCTION PROJECT

1. ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT

CONTAMINATION OF DUCT SYSTEM.

2. COMPLETE ALL CRITICAL BARRIERS, I.E., SHEETROCK, PLYWOOD, PLASTIC, TO SEAL AREA

FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE METHOD (CART WITH PLASTIC

COVERING & SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR VACUUMING

PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS.

3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORKSITE UTILIZING HEPA-EQUIPPED AIR

FILTRATION UNITS.

4. SEAL HOLES, PIPES, CONDUITS AND PUNCTURES APPROPRIATELY.

5. CONSTRUCT ANTEROOM AND REQUIRE ALL PERSONNEL TO PASS THROUGH THIS ROOM

SO THEY CAN BE VACUUMED USING A HEPA VACUUM CLEANER BEFORE LEAVING WORK SITE;

OR THE CAN WEAR CLOTH OR PAPER COVERALLS THAT ARE REMOVED EACH TIME THEY

LEAVE THE WORK SITE.

6. ALL PERSONNEL ENTERING THE WORK SITE ARE REQUIRED TO WEAR SHOE COVERS.

SHOE COVERS MUST BE CHANGED EACH TIME THE WORKER EXITS THE WORK AREA.

7. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT IS INSPECTED

BY SAFETY MANAGEMENT & INFECTION CONTROL & THOROUGHLY CLEANED BY

ENVIRONMENTAL MANAGEMENT.

CLASS I - UPON COMPLETION OF PROJECTS

1. CLEAN WORK UPON COMPLETION OF TASK

CLASS II - UPON COMPLETION OF PROJECTS

1. WIPE WORK SURFACES WITH DISINFECTANT.

2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED

CONTAINERS.

3. WET MOP &/OR VACUUM BEFORE LEAVING WORK AREA.

4. REMOVE ISOLATION OF HVAC SYSTEM IN AREA WHERE WORK IS BEING PERFORMED.

CLASS III - UPON COMPLETION OF PROJECTS

1. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT IS INSPECTED

BY SAFETY MANAGEMENT & INFECTION CONTROL & THOROUGHLY CLEANED BY

ENVIRONMENTAL MANAGEMENT.

2. REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE SPREADING OF DIRT & DEBRIS

ASSOCIATED WITH CONSTRUCTION.

3. VACUUM WORK AREA WITH HEPA-FILTERED VACUUMS.

4. WET MOP WITH DISINFECTANT.

5. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.

CLASS IV - UPON COMPLETION OF PROJECTS

1. REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE SPREADING OF DIRT & DEBRIS

ASSOCIATED WITH CONSTRUCTION.

2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED

CONTAINERS.

3. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS SOLID LID.

4. VACUUM WORK AREA WITH HEPA-FILTERED VACUUMS.

5. WET MOP WITH DISINFECTANT.

6. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.

CONTRACTOR'S SIGNATURE AND DATE

INFECTION CONTROL PERSONNEL SIGNATURE AND DATE

PHASING DIAGRAM W/ EXISTING PLAN

NOT TO SCALE

PHASING DIAGRAM W/ NEW CONSTRUCTION PLAN

NOT TO SCALE

PHASE 1

PHASE 1

PHASE 2

PHASE 3A/3B

PHASE 4 - TO TAKE PLACE OFF OF MAIN VISITING HOURS

ICRA BARRIER LOCATION, REFERENCE DETAIL 1/G-003

GENERAL NOTE: TWO MEANS OF EGRESS AND

EGRESS SIGNAGE TO THOSE MEANS MUST BE

MAINTAINED DURING EACH PHASE OF

CONSTRUCTION.

ALL PHASES TO BE COORDINATED WITH FACILITY

MANAGEMENT FOR APPROVAL OF CONTROLS, (ICRA,

SIGNAGE, ETC.)

PHASE 1

PHASE 1

PHASE 2

PHASE 3A/B

PHASE 4 - TO TAKE PLACE OFF OF MAIN VISITING HOURS

ICRA BARRIER LOCATION, REFERENCE DETAIL 1/G-003

RISK LEVEL TYPE 'A' TYPE 'B' TYPE 'C' TYPE 'D'

GROUP 1 I II II III / IV

GROUP 2 I II II IV

GROUP 3 I II III / IV

GROUP 4 II III / IV

CONSTRUCTION TYPE: D RISK GROUP: MEDIUM RISK ASSESSMENT: IV

III / IV

IV

IV

PROJECTED UTILITY OUTAGES IMPACTING INFECTION CONTROL

ELECTRICAL:

YES

POTABLE WATER:

YES

HVAC:

YES

MEDICAL VACUUM:

YES

SEWER:

YES

MTL STUD FR - REF SCHED FOR SIZE,

SPACING & WIDTH AS SPEC

U.N.O. (2) LAYER 5/8" TYPE "X" GYP BD

EACH SIDE - 2 HR RATED, UL 419

UNDERSIDE OF STRUCTURE

BASE

PLAN

HEAD

SCHED CEILING, REF RCP

STEEL TRACK, FASTEN 2'-0" OC MAX

ACOUSTIC SEALANT BOTH SIDES. FIRE RATED

SEALANT BOTH SIDES WHERE REQUIRED BY UL 419.

STEEL TRACK, FASTEN 2'-0" OC MAX

ICRA GENERAL NOTES:

1. FOR EXISTING PARTITIONS USED AS ICRA BARRIERS, THE CONTRACTOR SHALL COMPLETE THE

FOLLOWING:

• MODIFY EXISTING PARTITION TO TWO-HOUR RATED ICRA BARRIER

• EXTEND PARTITION TO FLOOR DECK WITH 5/8" GYP BD ON EACH SIDE, REF TYP DTL 1/G-002

• FINISH WALL PARTITION AS DIRECTED BY UL RATING REQUIREMENTS

• INFILL EXISTING OPENINGS WITH 5/8" GYP BD ON EACH SIDE

• PROVIDE FIRESTOPPING AT ALL EXISTING PENETRATIONS

2. PROVIDE 90 MINUTE RATED DOOR TO ACCESS CONSTRUCTION AREA AT ALL NEW AND

EXISTING ICRA BARRIERS

3. THE CONTRACTOR SHALL NOT BLOCK SPRINKLER PROTECTION ON THE VA-OCCUPIED SIDE OF

ANY ICRA BARRIER

AREA OF DISRUPTION - GENERAL NOTES

EXISTING LEVEL BELOW 8TH FLOOR CLC IS HOME TO MULTIPLE DIFFERENT OCCUPANCIES. COORDINATE WITH VA AND COR TO PLAN OUT AREA OF DISRUPTION DURING EACH PHASE OF CONSTRUCTION WHEN CONTRACTOR IS REQUIRED TO WORK FROM LEVEL BELOW. ALL CONSTRUCTION IS TO COMPLY WITH VA STANDARDS PER EACH TYPE OF OCCUPANCY. LISTED BELOW:

• 7A (BELOW 8A) IS ADMINISTRATION OFFICES : CONSTRUCTION TO BE DONE AFTER HOURS AND NO MORE

THAN ONE ROOM AT A TIME.

• 7B (BELOW 8B) IS PATIENT CARE AREA W/ PATIENTS RESIDING AT ALL HOURS : ICRA ENCLOSURES REQUIRED ON OUTSIDE OF DOORS TO ROOMS DURING CONSTRUCTION. USE NEGATIVE AIR PRESSURE AS NEEDED.

CONSTRUCTION TO BE DONE DURING NORMAL HOSPITAL HOURS.

• 7C (BELOW 8C) IS PATIENT CARE AREA WITH CONTROLLED ACCESS. VA COR WILL GRANT ACCESS DAILY, MAX TWO PERSON WORK CREW. ICRA ENCLOSURES ON INSIDE OF DOOR TO ROOMS DURING

CONSTRUCTION. TOOLS, BELONGINGS, CONSTRUCTION MATERIAL ETC. NOT TO BE LEFT UNATTENDED. ALL WORK RELATED BELONGINGS TO BE REMOVED BEFORE END OF SHIFT. CONSTRUCTION TO BE DONE

DURING NORMAL HOSPITAL HOURS AND NO MORE THAN ONE ROOM AT A TIME.

ALL ROOMS LOCATED ON THE 7TH FLOOR IN THE AREA OF DISRUPTION TO RECEIVE LOCK CHANGE FOR THE DURATION OF

CONSTRUCTION. COORDINATE WITH COR.

ALL ROOMS REQUIRE VA PERSONNEL TO REMOVE EXISTING EQUIPMENT BEFORE CONSTRUCTION. COORDINATE WITH COR.

ALL ROOMS TO BE CLEANED BY GENERAL CONTRACTOR AT END OF SHIFT.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseArchitect/Engineer of Record StampConsultant

321 4 5 6 7 8 9 10

Sprinkler Status

AE Works, LTD.

209 Sandusky Street Pittsburgh, PA 15212 Phone: 412-287-7333 www.ae-works.com G-003

PHASING PLAN & ICRA

INFORMATION

SYRACUSE VAMC 8TH

FLOOR CLC RENOVATION

800 Irving Ave, Syracuse VA, New York 13210

528A7-18-739

MAY 22, 2020 RS ZS

BID DOCUMENTS

1 PARTITION - TYPICAL ICRA BARRIER

# Revisions Date

COMBINED NEW PHASE 1

PHASE 2

PHASE 3A

PHASE 3B

PHASE 4

PHASE2

PHASE 3A

PHASE 3B

PHASE 1 COMBINED

THIS SEGMENT OF CONSTRUCTION BARRIER TO REMAIN

IN PLACE UNTIL PROJECT IS COMPLETE. DURING PHASE 3A AND 3B

CONTRACTOR REQUIRED TO PROVIDE APPLICABLE

PATIENT ACCESS AT ALL TIMES.

COMBINED NEW PHASE 1

PHASE 2

PHASE 3A

PHASE 3B

PHASE 4

COMBINED PHASE 1

PHASE 2

PHASE 3A

PHASE 3B

THIS SEGMENT OF CONSTRUCTION BARRIER TO REMAIN IN PLACE UNTIL

PROJECT IS COMPLETED. DURING PHASE 3A AND 3B, CONTRACTOR

REQUIRED TO PROVIDE APPLICABLE PATIENT ACCESS AT ALL TIMES

File details come from the government source that posted it. Updated .