2020-07-16 Bidder Questions - MR Responses - 2.xlsx
XLSX spreadsheet 27 KB Posted
- Attached to
- Y1DZ--620A4-14-118 Chiller Plant Upgrade
- Solicitation number
- 36C24220B0045
About this file
This document contains a bidder question form and federal contract opportunity notice. The bidder question form relates to project number 620A4-14-118 to upgrade the chiller plant at the Castle Point VA Medical Center campus in Wappingers Falls, New York. It provides responses to contractor questions on specifications, drawings, and scope details.
The federal contract opportunity is a pre-solicitation notice for project number 620A4-14-118 to upgrade the Castle Point VA Medical Center chiller plant. The estimated value is between $1 million to $5 million. The completion period is 1,460 calendar days. The procurement is a 100% set-aside for a Service-Disabled Veteran-Owned Small Business. Contractors must be registered in the VetBiz and SAM databases. A bid bond is required and payment and performance bonds are required upon award. The solicitation will be released on or around June 1, 2020. Questions are due by May 31, 2020 and are to be emailed to the point of contact.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24220B0045_9.docx | DOCX document | |
| HA102-Hazardous Materials Lead Paint Location Plan Ground Floor.pdf | ||
| 36C24220B0045_8.docx | DOCX document | |
| 36C24220B0045_7.docx | DOCX document | |
| 36C24220B0045_6.docx | DOCX document | |
| Sign In.pdf | ||
| 36C24220B0045_5.docx | DOCX document | |
| 36C24220B0045_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bidder Question Form
| UPGRADE CHILLER PLANT |
| VA #620A-14-118 |
| VAHVHCS Castle Point Campus, Wappingers Falls, NY |
BIDDER QUESTION FORM
| # | Question/Comment | Discussion | Miller-Remick Response |
| 6/30/20 | |||
| 1 | There does not appear to be any insulation specification for the condenser water. Please clarify. | Correct. There is no insulation for the condenser water. | |
| 2 | Drawing HA101 references an existing roofing manufacturer warranty from Firestone. Is the warranty still in effect? | yes | |
| 3 | Please provide a roofing specification for the patch and repairs that includes the Firestone product used. | Notes on SD102 (#7), SD103 (#5), SF-102 (#7), and SF-103 (#11) require the contractor to coordinate with the COR and Firestone’s instructions and details “so as not to void any warranty”. In addition, Detail #2 on S-502 also sates for the contractor to “match existing”. | |
| 7/7/20 | |||
| 4 | Bid drawing M-802: Please provide the contact information of the contractor for is at present servicing campus existing Building Automation System (BAS) | Janson control | |
| 5 | Bid drawing E-601 & E-602 (Existing & New Electrical one line diagram): Please provide name plate detail of existing substation 35-US Federal Pacific so as to enable the bidders to obtain quote for the new replacement circuit breakers . Also please clarify whether existing breakers are fixed or draw out type? | Existing breakers and new breakers are draw-out type. Refer to spec section 26 23 00; Part 2.3 for information regarding existing breakers and new breakers. |
The Substation is by FPE, 3000A, 277/480V, 3 Phase 4 Wire with 120V Control. SO No 02-9981, Date: 5-14-81, Dwg No.: 02-9981-1D2.
| 7/10/20 | ||
| 6 | I have a question regarding the HVAC specs and drawings for Chilled Water piping materials. The drawing M501 #3.4 says the chilled water piping about 6” can only be welded joints. But the spec 23 21 13 says the chilled water piping 2” and above can either be welded or grooved. Which of these is correct? | Chilled water piping 6" and above, shall be welded only. |
| 7 | Spec 23 07 11, Part 1.1, Paragraph A, Item 2 calls for reinsulation of HVAC piping, duct, etc. after abatement of asbestos. There are no pipe abatement specs given. Also, there is no pipe, equipment or duct insulation asbestos abatement scope shown on the drawings. Please clarify what the spec refers to. If there is insulation asbestos abatement please provide a clear scope and quantities. | There was no asbestos pipe and/or equipment insulation referenced in our report. Therefore, there shouldn’t be any planned abatement of pipe and/or equipment insulation at this time. |
| 8 | Insulation specs 230711-1 specifically call for re-insulation after Asbestos abatement. No drawings indicate removal of insulation due to asbestos abatement. Please confirm that this does not apply. | There was no asbestos pipe and/or equipment insulation referenced in my report. Therefore, there shouldn’t be any planned abatement of pipe and/or equipment insulation at this time. |
| 9 | Specifications are not clear on whether jacketing is used on Chiller plant indoors. Was there Aluminum or PVC Jacketing on piping to be demolished? | Provide color coated PVC jacketing per ASME A13.1 for chilled water piping. No known Aluminum or PVC Jacketing on piping to be demolished. |
| 10 | Is this a tax-exempt project? | yes | |
| 11 | If tax-exempt, will the VA be issuing a tax-exempt certificate for use by the Prime Contractor and subs? | CO will provided the required document to the winning bidder | |
| 12 | There are no specifics on the drawings regarding lead paint abatement, i.e. locations, quantities, etc. Please provide specifics such as locations of abatement, quantities of abatement, etc. | Drawing HA102 has been provided to inform the contractor of presence and known locations of lead paint within project boundary. Intent is not to abate areas of lead paint. All work requiring grinding, cutting, etc., to be performed in a safe manner per the contractor’s means and methods and the guidelines set forth by the Occupational Safety and Health Administration for lead: • Step 1: Determine if the Job Involves Lead-Based Paint. • Step 2: Set It Up Safely. • Step 3: Protect Yourself. • Step 4: Minimize the Dust. • Step 5: Leave the Work Area Clean. • Step 6: Control the Waste. • Step 7: Verify Work Completion with the Cleaning. | |
| 13 | Drawing S-001 calls for structural steel inspection, then continues to specify visual inspection of all welds, 10% of primary connection fillet welds get mag particle, and 100% get UT. There are different and more stringent specs called out in 01 45 29 for testing requirements. Which will be used to govern testing of concrete and steel? | More stringent requirements between dwgs and specs shall be followed. | |
| 14 | If steel is to be UT inspected, should it be inspected before galvanization and at the shop? Field UT of galvanized steel is not recommended. | Shop or field UT testing is acceptable. | |
| 15 | Spec section 23 05 11 uses the terms “Coordination/Shop Drawings”, but our understand of these two are very different. We interpret Coordination Drawings as those BIM or CAD drawings issued to ensure no interference/clashes between systems, whereas Shop Drawings are from the OEM. Please advise which drawings the VA is expecting. | Coordination drawings are submittal drawings (CAD or BIM) to be reviewed to assure disciplines have been coordinated and maintenance/access has been shown. Shop drawings (i.e. fabrication, erection drawings) are submittal drawings (CAD or BIM) to be reviewed to assure construction standards are being met. Both are required per the specs. | |
| 16 | If Coordination Drawings are required, the Level of Development (LOD) must be specified so the deliverables are known. | Refer to spec section 23 05 11, Part 1.4.J. | |
| 17 | If Coordination Drawings are required, what trades are expected to show up on these? | Refer to spec section 23 05 11, Part 1.4.J. | |
| 18 | Where will contractors be allocated space for laydown and onsite pipe fabrication? | Coordinate with spec section 01 00 00. | Contractors allocated space will be around the chiller building with no blocking to any entry or way road. |
| 19 | Steel demo on SD103 is unclear as to what remains. It appears everything is demoed except the existing W8x31 column. Please confirm. | As noted on SD103, all ex steel dunnage framing & bracing and existing pipe dunnage posts shall be selectively demolished. Existing steel wide flange dunnage post/column shall remain. | |
| 20 | Who is the existing roof contractor providing warranty on roof? | Firestone | |
| 21 | Please confirm only steel fabricators holding AISC certifications are approved for steel supply on this project. | Refer to specification section 051200-1.4 for required steel fabricators and installers qualifications/certifications. | |
| 22 | Section 09 91 00 indicates galvanized steel and mechanical insulation get painted, but later in the section gives contradictory language. Please confirm the painting scope. | Galvanined steel not to be painted. Condenser water piping to be painted per ASME13.1. Floor is to be painted (color per VA). Housekeeping pads are to be painted "safety" yellow. Existing painted steel I-beams to be touched up at locations of demolished and new pipe/equipment supports to match existing color. | |
| 23 | Is the GC expected to directly contract with the third party CIH or can this come from the abatement contractors’ staff? | The project monitoring firm and air monitoring firms/laboratories must be independent of the asbestos abatement contractor per industrial Code rule section 56-4.3. | |
| 24 | What are the Covid 19 requirements for working within the plant? | PPE , social distancing and gate screening. | |
| 25 | How many and at what locations are Cooling Tower spring isolators required? | Please see sheet note 7 on drawing MQ102. | |
| 26 | Can the VA provide the contact info for the current water treatment vendor? | Chardon Labs | |
| 27 | The spec state 280-day POP whereas the solicitation states 360 days. Please confirm. | 360 days | |
| 28 | Please confirm the VA retains the temp chiller currently onsite and its rental costs during construction are not part of this contract. | Confirmed. | |
| 29 | Will the VA provide space for an office trailer throughout construction? | Coordinate with spec section 01 00 00. | See response to #18. |
| 30 | If yes to the above, should contractors’ meter their utility usage? | Coordinate with spec section 01 00 00. | yes |
| 31 | Does the VA anticipate off hours work will be required for any portions of this project? | Coordinate with spec section 01 00 00. Electrical off-hour work to be performed per drawing E-001, E-101 and EP101. | Electrical off-hour work to be performed per drawing E-001, E-101 and EP101. System Shutdowns/outage coordination may require off hours work. |
| 32 | If yes to the above, what scope of work will require off hours? | Coordinate with spec section 01 00 00. | See response to #31. |
| 33 | Can crane picks take place during normal hours? | Coordinate with spec section 01 00 00. | yes |
| 34 | What seismic design category is applicable to this project? | Refer to Drawing S-001, Design Data. | |
| 35 | Spec 23 25 00 states for the GC to provide water treatment and monitoring for 12 months, 6 return to site visits, etc. following commissioning of system. Please confirm if the VA plans to use their existing water treatment contractor for this scope or if the prime contractor is expected to provide this coverage. | VA chemical contractor will be responsible for that task | |
| 36 | If part of this contract, please provide the water treatment contracting contact info. | See response to #26. | |
| 37 | Confirm if the Superintendent and Project Manager are both required to be onsite full time, each day construction activities are commencing. | Coordinate with spec section 01 00 00. | only Superintendent is required to be on site on any preformed workday. |
| 38 | If full time onsite, are both expected to be onsite from Day 1 to the very last day (Final Handover)? | Coordinate with spec section 01 00 00. | See response to #37. |
| 39 | Confirm if the PM can provide QC Manager roles or does this require an additional person, making the total required onsite persons from the GC’s staff three different employees. | If required, roles for contractor's QC Manager is found within spec section 01 45 00 Quality Control which was not provided per VA direction. | the PM can provide QC roles. |
| 40 | Please show a detail of the “pipe port” the drawings explain where the chilled water lines to the temp chiller enter and exit through the window. We do not understand the plate/panel the drawings are trying to explain. | Refer to structural dwg SF102 for more information. | |
| 41 | Is the chemical feed scope by others or part of this contract? | the VA contractor is responsible to provide chemicals, chemical tanks, feed pumps, feed lines to the GC supplied manifold systems & associated apparatus (i.e. not limited to coupon rack , isolation valve , ..etc.) | |
| 42 | Confirm water treatment contract covers chemical feed. | See response to #41. | |
| 43 | If no to above, please provide chemical feed contractor info. | N/A | |
| 44 | Drawing M601, Chiller #3, 10” CHS line shows a backflow preventer (“RPZ BFP”) after the flow meter and before the balance valve with arrows pointing the return line and into dead air space? Is this correct? | This is not correct and is not part of the chiller piping connections. This can be omitted. | |
| 45 | If above is correct, please provide clarification on this. | See response to #44. | |
| 46 | Electrical drawings show two temp chillers, but the mechanical drawings only show one is connected. Please clarify scope of supply. | (2) Temporary chillers required and furnished by the VA. All final connections to the temporary chillers to be made by the VA (Keynote #5, Sheet E-101). Mechanical contractor to provide interior piping to exterior of the wall as shown on M-101 (Keynote #5). All connections exterior to the building to be by VA. | |
| 47 | Drawing M501, Detail 3 shows the chiller connections and one of the balancing valves is indicated as a butterfly control valve. Confirm the upstream sides get the control valve and downstream sides get a balancing valve. | Correct, the upstream side gets the control valve, and the downstream side gets the balancing valve. | |
| 48 | Can a Cooling Tower connection detail be provided? | Please see dwgs MP102, M-301, M-303, M-304, and M-602 for Cooling Tower connections. | |
| 49 | Are globe valves required on the Cooling Tower drains (as shown on M-602)? | No, ball or butterfly valve can be used. | |
| 7/14/20 | |||
| 50 | The mechanical details do not show a triple duty valve on the pump discharge, but the hydronic piping specs call for one at 23 21 13, 2.1, G,1. Please clarify. From experience, these are several thousand dollars and there are nine of them. All nine will cost several tens of thousands of dollars. | Triple duty valves not required or recommended. | |
| 51 | Confirm the HVAC Water Treatment is by others and NOT part of this contract (conductivity/PH controller, chemical feed pumps, coupon rack, etc.). | See response to #41. |
| 52 | Reference: Contract Specification Section 02 82 13.21 Roof Asbestos Abatement (Note: Documents Contain two such sections the first is 4 pages long). Subject: Extent of Contractor Responsibilities Not Clear – Asbestos Abatement Monitoring, Testing & Inspection. Question: The specifications for the Roof Asbestos Abatement are confusing regarding the extent professional monitoring, testing and inspection required of the bidder as the specification seems to imply that the owner and the contractor are required to perform similar services (refer to sect 02 82 13.21 para 2.3 and elsewhere). Please clarify. | The contractor has a responsibility to monitor his own employees’ exposure to hazardous materials under 29 CFR 1910.120. The contractor’s supervisor can perform the air sampling if he has been trained to do so. The IH technician (hired by the VA) shall be responsible for monitoring the project to protect the health and safety of the employees and patients of the VA. The IH technician will be responsible to make sure the contractor is performing his duties per local, state and federal regulations. | |
| 53 | Reference: Contract Drawings SD 101, 102, Etc. and Specification Section 02 83 33.13 – Lead Paint Abatement. Subject: Extent of Lead Paint Abatement Undefined. Question: The Contract Drawings note that “Existing Building has the presence of Lead Paint. Refer to the Specifications.” Since the specification’s do not delineate the location or quantities of lead paint, the scope of this work is undefined. Please Clarify. | See response to #12. | |
| 54 | Reference: Contract Drawings SD102, SD 103 and S 50. Subject: Existing Roofing System Undefined. Question: The Contract Drawings note that Contractor required patch, flash and seal the existing roofing where openings are closed or penetrations patched to “match the existing roofing material”, which is noted as a Firestone product. Please advise the existing type of Firestone roofing system, i.e. BUR, SBS, EPDM or PVC and approximate year installed. | Notes on SD102 (#7), SD103 (#5), SF-102 (#7), and SF-103 (#11) require the contractor to coordinate with the COR and Firestone’s instructions and details “so as not to void any warranty”. In addition, Detail #2 on S-502 also states for the contractor to “match existing”. | |
| 55 | Reference: General Requirements – Section 01 00 00 Paragraph 1.85 Electrical Work Permit A. Subject: State or Local Licensed Electrician. Question: Subparagraph A. of the above referenced document reads as follows: The Contractor is responsible for | ||
| ensuring that a Licensed Journeyman Electrician by a State or Local jurisdiction is present during any and all electrical work activities during this project. New York State does not regulate electricians but requires local jurisdictions to issue their own electrical licenses. Since the project lies within the jurisdiction of Duchess County, please confirm that the electrical work can be overseen by firm that has an electrical license issued by Duchess County. | yes , it can be performed by licensed Duchess County. |