36C24219B0014-002.doc

DOC document 539 KB Posted

Attached to
Animal Research Shock Tube Site Support 526-17-504
Solicitation number
36C24219B0014
Issued by

About this file

36C24219B0014 526-17-504 Animal Research Shock Tube - Statement of Work 07-06-2018.doc

View the file

Other files

File Type Posted
36C24219B0014-P00003002.pdf PDF
36C24219B0014-P00003001.pdf PDF
36C24219B0014-P00003000.docx DOCX document
36C24219B0014-P00003003.pdf PDF
36C24219B0014-P00002000.docx DOCX document
36C24219B0014-P00001000.docx DOCX document
36C24219B0014-003.pdf PDF
36C24219B0014-001.docx DOCX document
36C24219B0014-004.pdf PDF
36C24219B0014-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Veterans Affairs Animal Research Shock Tube Site Support James J. Peters Bronx VA Medical Center Project #526-17-504

Statement of Work Project #: 526-17-504 Reference #: 526-18-4-5019-0074 COR: David Ng The Contractor must furnish all labor, materials, tools and supervision to complete the following:

Animal Research Shock Tube Site Support (1st floor, Building 105):

The renovation of an approximately 650 S.F. space on the 1st floor of the Research Building (Building 105) of the James J. Peters VA Medical Center to create an Animal Research Shock Tube lab, which includes but is not limited to demolition of the existing area indicated on the drawings and construction of the lab.

The new work will comprise of general carpentry, modifications of the electrical, plumbing, fire protection, HVAC, telecommunication, and security systems, installation of millwork and/or casework, and interior finish work.

The area is approximately 650 square feet and the following rooms will be included in the renovation:

1F-29A and 1F-23 Anteroom and smoke barrier wall will be constructed along the perimeter of the project before any construction work commences. All proper infection control and life safety measure will be provided and coordinated with Infection Control and Safety Officer.

Work is expected to be completed within 120 calendar days from NTP.