Attachment 1 Response to RFI 36C24124R0058 Manchester VAMC SATOC IDIQ.pdf
PDF 101 KB Posted
- Attached to
- 5680--Manchester Construction SATOC
- Solicitation number
- 36C24124R0058
About this file
This document appears to be Attachment 1 - Response to RFI 36C24124R0058 for the Manchester VAMC SATOC IDIQ contract. The RFI provides information about the contract requirements, including that the contractor will only be required onsite during active construction, and that space will be available for an office trailer and lay-down area if needed. The average task order value is expected to range from $100,000 to $750,000, with the VA expecting to issue roughly a dozen task orders per year under this SATOC contract vehicle. The related federal contract opportunity is a Request for Proposal (RFP) for a Single Award Task Order Contract (SATOC) at the Manchester VA Medical Center, to be issued by the Department of Veterans Affairs Veterans Health Administration.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1
RFI 36C24124R0058 Manchester VAMC SATOC IDIQ
Does the VA want the contractor representative to be onsite full time Monday-Friday?
Contractor will be required onsite only during active construction.
Is there an office space for the project manager onsite at the VA? If not, will there be an area sufficient to set up an office trailer?
We will have sufficient space to set up a trailer, if needed.
Will the contractor be provided a lay down area for containers to store construction supplies and equipment?
We will have sufficient space for a lay-down area, as needed.
What will be the average dollar value size of each task order?
Dollar values will vary greatly, depending on what the specific project requires, but will generally range from $100k-$750k
How many task orders have been done yearly?
Task order quantity will vary greatly depending on funding, contractor availability, timing, etc. VA expects to try to use SATOC roughly a dozen times a year.