About this file

This document is a combined synopsis/solicitation for commercial services related to the tri-annual testing and maintenance of the electrical power distribution system at the VA Connecticut Healthcare System West Haven and Newington campuses. The VA is seeking services for all labor, transportation, parts, and expertise necessary to provide this testing in accordance with NETA standards. The work will need to be executed primarily outside of regular business hours to avoid disrupting hospital operations. The period of performance is 30 days from award. The contract is set aside for service-disabled veteran-owned small businesses (SDVOSB). Key qualifications include being an NETA-certified electrical contractor with experience in healthcare facility electrical systems maintenance and testing. Proposals are due by August 16, 2024 and will be evaluated on price, capabilities, and veteran-owned small business status.

View the file

Other files

File Type Posted
P01_Arc Flash Hazard Analysis Newington.pdf PDF
P01_Arc Flash Evaluation Report Newington.pdf PDF
Item List.pdf PDF
P01_Drawings Newington.pdf PDF
P01_Arc Flash Evaluation Report West Haven.pdf PDF
36C24124Q0631_2.docx DOCX document
P01_Drawings West Haven.pdf PDF
36C24124Q0631_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6-1

6. ARC FLASH HAZARD ANALYSIS

6.1. Introduction

An arc flash risk assessment determines arc flash hazards, arising from incident energy released by an arcing fault, at specified devices in the electrical distribution system. Of critical interest are locations where maintenance personnel will likely perform work on energized equipment such as switchgear, switchboards, panelboards, industrial control enclosures, and panelboards. NFPA 70E, 2018, 130.5(D) requires arc flash labels containing the nominal system voltage, arc flash boundary, available incident energy, and corresponding working distance for all such equipment.

The analysis performed per NFPA 70E, 2018, determines the Flash Protection

Boundary and the personal protective equipment (PPE) to be used within arc flash boundaries higher than 1.2 cal./cm2.

This study has been completed based on the IEEE 1584-2018 standard. This guide utilizes similar parameters as IEEE 1584-2002, with the addition of the bus bar configurations and box enclosure dimensions.

6.2. Arc Flash Calculations

Calculations have been made per IEEE 1584, 2018 with a clear fault threshold of

80%, a maximum arcing duration of 2.0 seconds, and the inclusion of induction motors for 5 cycles.

6.3. Arc Flash Hazard Analysis

The Arc Flash Risk Assessment has been performed per NFPA 70E with the worst-case results across all scenarios reported. Equipment with a calculated incident energy of 12.0 cal./cm2 or higher is highlighted in the Arc Flash Reports. TMM recommends that all existing arc flash hazard labels be removed and only labels that are provided with this study be installed.

The following operating scenarios have been evaluated for arc flash risk assessment with the worst-case results being reported:

Scenario 0 (NML): MV-N-SWGR-1 is powered by UTIL-FDR-626. MV-52-L1 and tie-breaker MV-N-SWGR-1-TIE are closed, and MV-52-L2 is open.

Scenario 1 (UTIL-FDR-627): MV-N-SWGR-1 is powered by UTIL-FDR-627.

MV-52-L2 and tie-breaker MV-N-SWGR-1-TIE are closed, and MV-52-L1 is open.

Scenario 2 (MV GENS/UTIL-626): Medium voltage generators CG1 and CG2 are in service, operating in parallel with UTIL-FDR-626. MV-52-L1 and tie-breaker

MV-N-SWGR-1-TIE are closed, and MV-52-L2 is open.

Scenario 3 (LV-GENS/UTIL-FDR-627): MV-N-SWGR-1 is powered by UTIL-

FDR-627. MV-52-L2 and tie-breaker MV-N-SWGR-1-TIE are closed, and MV-

52-L1 is open. All LV generators are online powering the EES system.

6-2

The calculated incident energy exceeds 40 cal./cm2 at the locations listed below.

Energized work should be performed at these locations under permit only.

01-FDR-BKR-#1-SSB1-2B (Rm. SG110)

01-FDR-BKR-#4-SSB1-2A (Rm. SG110)

01-LC1B-A (Rm. New Elec.) (01-LC1B-AM-MB LineSide)

01-LC1B-B (Rm. New Elec.) (01-LC1B-BM-MB LineSide)

01-LC7-MSB4 (Rm. SG109A) (01-LC7-MSB4-MB LineSide)

01-TR-FDR-BKR-#1-SSB1-2B-SEC (Rm. SG110)

01-TR-FDR-BKR-#4-SSB1-2A-SEC (Rm. SG110)

02-LC2A (Rm. G145A) (02-LC2A-MB LineSide)

02-LC2B (Rm. G145A) (02-LC2B-MB LineSide)

02-TR-NLDP-1A-SEC (Rm. G136)

16-LC3-B (Rm. 102) (16-LC3-B-MB LineSide)

16-LC3-D (Rm. 102) (16-LC3-D-MB LineSide)

MV-T-B16-TLC3-B-SEC (Rm. 102)

MV-T-B1-LC7-MSB4-SEC (Ext. Bld. 1 PET)

MV-T-LCB-A-SEC (Rm. New Elec.)

MV-T-LCB-B-SEC (Rm. New Elec.)

MV-T-PET-MDP-SEC (Ext. Bld. 1 PET)

MV-TR-01-SSB1-2A-SEC (Rm. SG110)

MV-TR-01-SSB1-2B-SEC (Rm. SG110)

MV-TR-01-SSB1-4A-SEC (Rm. SG110)

MV-TR-01-SSB1-4B-SEC (Rm. SG110)

MV-TR-02-LC2A-SEC (Rm. G145A)

MV-TR-02-LC2B-SEC (Rm. G145A)

MV-TR-02-SS2B-6A-SEC (Rm. G-136)

MV-TR-02-SS2B-6B-SEC (Rm. G-136)

MV-TR-N-USS-1-A-SEC (Rm. 19 202)

MV-TR-N-USS-1-B-SEC (Rm. 19 202)

Arc Flash labels will be provided in the VAMC’s copy of the final submittal for installation by the electrical maintenance staff. WARNING labels are provided for equipment with a calculated incident energy less than 40 cal./cm2 and DANGER labels are provided for underrated equipment and all equipment with a calculated incident energy equal to or exceeding 40 cal./cm2.

Sample labels are presented below:

6-3

6.4. Personal Protective Equipment (PPE)

The table below, excerpted from NFPA 2018, 2018, delineates the clothing and PPE required for the indicated levels of incident energy:

6-4

Table 130.5(G) Selection of Arc-Rated Clothing and Other PPE When the

Incident Energy Analysis Method Is Used

Incident energy exposures equal to 1.2 cal/cm2 up to 12 cal/cm2

Arc-rated clothing with an arc rating equal to or greater than the estimated incident energy a

Long-sleeve shirt and pants or coverall or arc flash suit (SR)

Arc-rated face shield and arc-rated balaclava or arc flash suit hood (SR) b

Arc-rated outerwear (e.g., jacket, parka, rainwear, hard hat liner) (AN)

Heavy-duty leather gloves, arc-rated gloves, or rubber insulating gloves with leather protectors (SR) c

Hard hat

Safety glasses or safety goggles (SR)

Hearing protection

Leather footwear

Incident energy exposures greater than 12 cal/cm2

Arc-rated clothing with an arc rating equal to or greater than the estimated incident energy a

Long-sleeve shirt and pants or coverall or arc flash suit (SR)

Arc-rated arc flash suit hood

Arc-rated outerwear (e.g., jacket, parka, rainwear, hard hat liner) (AN)

Arc-rated gloves or rubber insulating gloves with leather protectors (SR) c

Hard hat

Safety glasses or safety goggles (SR)

Hearing protection

Leather footwear

SR: Selection of one in group is required.

AN: As needed.

a Arc ratings can be for a single layer, such as an arc-rated shirt and pants or a coverall, or for an arc flash suit or a multi-layer system if tested as a combination consisting of an arc-rated shirt and pants, coverall, and arc flash suit.

b Face shields with a wrap-around guarding to protect the face, chin, forehead, ears, and neck area are required by 130.7(C)(10)(c). Where the back of the head is inside the arc flash boundary, a balaclava or an arc flash hood shall be required for full head and neck protection.

c Rubber insulating gloves with leather protectors provide arc flash protection in addition to shock protection. Higher class rubber insulating gloves with leather protectors, due to their increased material thickness, provide increased arc flash protection.

File details come from the government source that posted it. Updated .