This document is a contract modification for Solicitation Number 36C24124B0041, titled "Z1DA--518-21-118 Building 78 Roof Replacement Construction." The modification provides the sign-in log from a site walkthrough conducted on 3/19/2024 and notes that the RFI deadline is 3/27/2024 and the proposal deadline (bid opening) is 4/16/2024 at the Bedford VAMC. Responses to RFIs received by the deadline will be issued in a future amendment, while RFIs submitted after the deadline are at the Contracting Officer's discretion. The solicitation is for a construction project to replace the roof on Building 78, issued by the Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 1.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24124B0041 0008.docx | DOCX document | |
| SF_1409 - 36C24124B0041 - 518-21-118.pdf | ||
| 36C24124B0041 0007.docx | DOCX document | |
| S02 PRE-AWARD CONTRACTOR EVALUATION FORM.pdf | ||
| 36C24124B0041 0006.docx | DOCX document | |
| Bldg 78 Roof - April 1st Site Visit sign in.pdf | ||
| 36C24124B0041 0005.docx | DOCX document | |
| 36C24124B0041 0004.docx | DOCX document | |
| pre-bid site walkthrough sign in.pdf | ||
| 36C24124B0041 0002.docx | DOCX document | |
| Instructions to Bidders - 36C24124B0041 - Building 78 Roof.pdf | ||
| 36C24124B0041 0001.docx | DOCX document | |
| Davis-Bacon Act WD MA20240001 revised 020924.pdf | ||
| 518-21-118 Building 78 Roof Replacement - SPECIFICATIONS - Bid.pdf | ||
| 518-21-118 Building 78 Roof Replacement - Plans BID Set.pdf | ||
| 36C24124B0041_2.docx | DOCX document | |
| 518-21-118 Building 78 Roof Replacement - Scope of Work.docx | DOCX document |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2.
AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A.
MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ________ ___ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDE
R IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is rece ived prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF
AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 518-21-118 Department of Veterans Affairs Network Contracting Office 1 (NCO 1) Contracting Officer (90C) 718 Smyth Road Manchester NH 03104 Department of Veterans Affairs Network Contracting Office 1 (NCO 1) Contract Specialist 200 Springs Road Bedford MA 01730 To all Offerors/Bidders
36C24124B0041 03-12-2024
X x x This amendment is issued to provide the sign-in log from the site walk on 3/19/2024 at 10:00AM.
"pre-bid site walkthrough sign in.pdf" is attached.
RFI and proposal deadlines are unchanged. RFI deadline is schedule for March 27, 2024 at 4:00PM EST. Proposal deadline (bid opening) is scheduled for April 16, 2024 at 11:00AM EST at Bedford VAMC.
Responses to submitted RFIs receive d by the RFI deadline will be issued with a future amendment/s. RFIs submitted after The deadline will be up to the COR's discretion.
Casey Pridham Contracting Officer See attached document: pre-bid site walkthrough sign in.