This is a Questions and Answers document addressing inquiries submitted by potential vendors in response to a Request for Quote (RFQ) for smart food locker systems to support the Department of Veterans Affairs' NouRISH (Nutrition, Resources, and Integrated Support for Health) program. The solicitation (36C10X26Q0233) seeks to furnish, deliver, and install food lockers with integrated software, warranty, and maintenance services to VA Community Based Outpatient Clinics and other VA facilities, with a focus on rural and highly rural sites. Key clarifications include: no incumbent vendor exists; the Government will not extend due dates without reasonable justification; answers will be posted within two business days of the questions deadline; evaluation will follow Section E criteria of the RFQ; and future procurement quantities remain to be determined based on operational needs.

Technical and operational requirements clarified in the Q&A include that lockers must maintain both frozen and refrigerated temperatures via single setpoint capability, operate on 220VAC power (120VAC is not acceptable), and include vendor-provided cellular SIM cards for connectivity. Alternative veteran access methods using secure unique codes that change per order are acceptable. The contractor is responsible for site assessment consultation regarding electrical readiness and installation feasibility but is not responsible for site preparation. All lockers will be installed on VA property, which may include leased space, with delivery and site specifications established at the order level. Questions regarding food transport, shared locker usage, donated food redistribution, and site preparation fall outside the procurement scope.

View the file

Other files

File Type Posted
SF30 36C10X26Q0233 0002.docx DOCX document
S02 RFQ Answers Amendment 2 AUG17.xlsx XLSX spreadsheet
S02 - 36C10X26Q0233 Food Lockers Combined Synopsis AMENDED.docx DOCX document
SF30 36C10X26Q0233 0001.docx DOCX document
S02 Attachment A - Questions and Answers.xlsx XLSX spreadsheet
S02 - 36C10X26Q0233 Food Lockers Combined Synopsis.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A

Addressed Via Amendment #Question
#QuestionSolicitation
ReferenceAnswer
1Is there an incumbent?N/ANo Incumbent
2Will the Government consider extending due dates?N/AThe Government will not respond to requests to extend due dates unless there is a reasonable request that includes the circumstances surrounding the request.
3When will responses to questions be posted?N/AThe Government plans to post answers within 2 business days of the Questions Due date.
4Are you differentially evaluating quotes that include the physical refrigerated lockers as well at integrated online ordering software to manage food inventory, facilitate order placement, scheduling, and communication with veteransQuotes will be evaluated IAW Section E of the RFQ.
5How will food be transported, then loaded into the lockers?N/A - Beyond the scope of the requirement.
6Will the lockers be shared among different groups?N/A - Beyond the scope of the requirement.
7Will the lockers need to be capable to receive donated food from approved organizations for redistribution?N/A - Beyond the scope of the requirement.
8How many systems might be procured after a successful pilot?Future acquisiiton are yet to be determined and will be based on need.
9Would it be desireable to have the option to connect to 120VAC (normal household voltage) for power in addition to 220VAC requested? This can open the installations to more locations and perhaps reduce or simplify them.120VAC is not desirable.
10Is the ask for a single solution that can maintain temperature at both frozen or refrigerated temperatures depending on the setpoint?Yes, see salient characteristics.
11With security as a primary concern would alternative methods of Veteran access to food be acceptable, for example using a secure unique code that changes for each order?Yes, this would be an acceptable option if needed.
12Will all the lockers be installed on VA property?Yes, this may also include leased space.
13Will the agency be providing cellular SIM cards or the vendor?The vendor shall provide the SIM card.
14Will the agency be providing electric power ready at the installation?The contractor shall consult with the site point of contact to assess the readiness of the proposed installation site to ensure safety and accessibility, including verification of adequate electrical outlets. Delivery and site specifications will be established at the order level.
15Food lockers generally require site preparation, for example ensuring there is a secure surface for installation, electric power, among other items. Will the prepared site be provided to the bidder and installation team?The Contractor is not responsible for any site prep. Per the RFQ: The contractor shall consult with the site point of contact to assess the readiness of the proposed installation site to ensure safety and accessibility, including verification of adequate electrical outlets. Delivery and site specifications will be established at the order level.