Z2DZ--Project Number 653-107, Seismic Retrofit of Building 11, Roseburg VAMC, Oregon
Solicitation number
36C10F26R0082
Issued by

About this file

This is Standard Form 30 (SF-30), an Amendment of Solicitation/Modification of Contract, issued by the Department of Veterans Affairs, Office of Construction and Facilities Management for solicitation 36C10F26R0082.

Amendment 0003, effective August 5, 2026, extends the proposal due date to Thursday, September 10, 2026, at 4:00 p.m. PST. The amendment publishes Request for Information (RFI) responses and updates the corrected scope of work document (36C10F26R0082_2). The solicitation involves all work necessary to complete a seismic retrofit and renovation of a laundry facility, with the project scope defined in accompanying documents including drawings, specifications, references, appendices, and addendums. The work is solicited on a lump-sum basis (JB) for one unit. Offerors must acknowledge receipt of this amendment prior to the extended deadline through one of three methods: completing Items 8 and 15 and returning copies to the issuing office, acknowledging receipt on each copy of the offer submitted, or sending a separate letter or electronic communication referencing the solicitation and amendment numbers. Contracting Officer Michelle Belkot issued the amendment. All terms and conditions of the referenced solicitation remain unchanged and in full force and effect except as specifically modified by this amendment. Offerors are directed to continue monitoring email correspondence for any additional changes to the RFP.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODECODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 2

0003 09-04-2026 653-107

003C4

Department of Veterans Affairs Office of Construction and Facilities Management (00CFM3B) 425 I Street NW Washington DC 20001

101F

Department of Veterans Affairs Office of Construction and Facilities Management 425 I Street NW Washington DC 20001

To all Offerors/Bidders

36C10F26R0082

08-05-2026

X

X X

** HOUR & DATE for Receipt of Offers is EXTENDED to: 09-10-2026 16:00 PDT

X 1

1. Amendment 0003 is issued to publish Request for Information (RFI) responses.

2. Update corrected scope of work, 36C10F26R0082_2

3. Proposal due date is hereby extended to Thursday, September 10, 2026, 4:00 p.m. PST.

All documents and information within this amendment superseded previous versions.

Continue to monitor e-mail correspondence for any and all changes to this RFP.

Michelle Belkot Contracting Officer

ITEM

NUMBE

R

DESCRIPTION OF

SUPPLIES/SERVIC

ES

QUANTIT

Y

UNI

T UNIT PRICE AMOUNT

0001 1.00 JB ______________

All work necessary to complete the entire project as indicated in the scope of work, drawings, specifications and any references, appendices, or addendums.

Contract Period: Base POP Begin:

POP End:

GRAND TOTAL ______________

See attached document: 36C10F26R0082_2.

See attached document: RFI B11 Seismic Retrofit and Renovate Laundry 36C10F26R0082.