This document provides details for a federal solicitation seeking proposals for the Great Lakes National Cemetery Phase 2 expansion project. The solicitation, issued by the Department of Veterans Affairs Office of Construction and Facilities Management, is set aside 100% for Service Disabled Veteran Owned Small Businesses. The purpose of the project is to develop approximately 30 acres of land at the Great Lakes National Cemetery in Holly, Michigan to provide over 29,000 additional gravesites. The project scope includes pre-placed crypts, roads, parking areas, a new committal shelter, landscaping, drainage improvements, and upgrades to electrical, maintenance facilities, and the cemetery's GIS system. Proposals are due by January 6, 2021, with contract award anticipated by March 31, 2021 and notice to proceed by April 19, 2021. The estimated cost range is $20-50 million to be paid as a firm fixed price.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IAS
GREAT LAKES
NATIONAL CEMETERY
PHASE 2 CEMETERY DEVELOPMENT
HOLLY, MICHIGAN
SOLICITATION 36C10F20R0098
PROJECT # 923CM2002
PRE-PROPOSAL CONFERENCE
DECEMBER 1, 2020
1 Office of Construction and Facilities Management
Agenda
Opening Remarks
NCA Mission
Solicitation Summary
Milestones
Project Scope and Overview
Site walkthrough
2 Office of Construction and Facilities Management
Opening Remarks
Introductions
VA Representatives
➢ VA CFM: Jeff Gerbensky, Contracting Officer
➢ VA CFM: Dave Martino, Project Manager
➢ GLNC: Srey Austin, Director
➢ GLNC: John Shilling, Maintenance & Operations Supervisor
3 Office of Construction and Facilities Management
NCA Mission
The National Cemetery Administration honors Veterans and their families with final resting places in national shrines and lasting tributes that commemorate their service and sacrifice to our Nation.
President Abraham Lincoln pledged the nation:
“To care for him who shall have borne the battle and for his widow and his orphan.”
That remains VA’s motto today.
4 Office of Construction and Facilities Management
Solicitation Overview
Solicitation is set aside for Service Disabled Veteran Owned Small Business (SDVOSB) in accordance with 38 U.S.C. 8127(d).
SDVOSB Offerors must be registered in SAM and registered & verified in VIP prior to submission
Annual Representation and Certification https://www.sam.gov/SAM/
Vendor Information Pages (VIP) https://www.vip.vetbiz.va.gov/
5 Office of Construction and Facilities Management
VAAR 809-406-2
Cause for Debarment
(a) In addition to the causes listed in FAR 9.406-2, the SDO may debar contractors, based upon a preponderance of the evidence, for
(1) Misrepresentation of Veteran-owned small business (VOSB) or service- disabled, Veteran-owned small business (SDVOSB) status; or
(2) Any deliberate violation of the limitation on subcontracting clause requirements for acquisitions under subpart 819.70.
(b) The SDO shall debar for a period of not less than five years, pursuant to 38 U.S.C. 8127(g), Enforcement Penalties for Misrepresentation, any business concern that has willfully and intentionally misrepresented the status of that concern as a small business concern owned and controlled by Veterans or as a small business concern owned and controlled by service-disabled Veterans pursuant to this subsection.
(1) “Willful and intentional” misrepresentations, for the purpose of debarment actions taken pursuant to subsection (b), are defined as misrepresentations concerning the status of the concern as a small business concern owned and controlled by Veterans or as a small business concern owned and controlled by service-disabled Veterans resulting in an admission, criminal conviction, civil judgment, or administrative decision related to fraud or other criminal acts.
(2) Debarment of a business concern pursuant to subsection (b) shall include the debarment of all principals in the business concern. Debarment shall be for a period of not less than five years.
https://www.acquisition.gov/content/part-9-contractor-qualifications#i1115334 https://www.va.gov/oal/library/vaar/vaar819.asp#81970
6 Office of Construction and Facilities Management
Service-Disabled
Veteran-Owned Small Business
VA Office of Small and Disadvantaged Business Utilization (OSDBU) Washington, D.C.
➢ http://www4.va.gov/osdbu/
Contact OSDBU for information on
Joint Ventures
Teaming Agreement
Mentor Protégée (See VAAR 819-71)
CVE verification http://www4.va.gov/osdbu/
7 Office of Construction and Facilities Management
Project Cost Range
Between $20,000,000 - $50,000,000
Contract Type: Firm Fixed Price
Evaluation Method: Best Value/Tradeoff
Federal , State, and Local Tax (FAR Clause 52.229-3)
Is the Responsibility of the Contractor, include it in your proposal price
Construction Wage Rate Requirements (Davis Bacon Act) Applies
Buy American Act Applies
8 Office of Construction and Facilities Management
Contract Line Item Numbers (CLINs 001-006)
CLIN 001: Base Bid - All work necessary to construct the base project
CLIN 002: Base Bid - Furnish and deliver pre-placed crypts
CLIN 003: Add Alternate #1 - New Committal Shelter 4
CLIN 004: Add Alternate #2 – Honor Guard Parking
CLIN 005 : Add Alternate #3 – Assembly Area Parking Lot
CLIN 006 : Add Alternate #4 – New Covered Storage Bldg, Maint. Yard
Period of Performance
1004 calendar days after the Notice to Proceed for base bid and any/all add alternate work.
9 Office of Construction and Facilities Management
Bid Bond/Bid Guarantee (SF 24)
See Solicitation pages 7 & 21
Bond amount 20% of the offer price but shall not exceed $3,000,000
Volume II, TAB 2, of your emailed proposal must contain a legible, scanned copy of your Executed Bid Guarantee (SF-24). Please shade any raised seals with pencil lead to make them legible before you scan the bond.
An original, hard copy, executed Bid Guarantee (on form SF-24) must be mailed to the Contracting Officer within 5 business days of the proposal due date/time. See page Solicitation pg 7
Make sure your bond is in compliance with Far Part 28
Performance & Payment Bonds (SF 25) Required
Penal sum = 100% of award amount
Required of awardee within 10 calendar days of award.
10 Office of Construction and Facilities Management
Early Turnover (ETO) Work
Completion and turn over to the Owner earlier than the final project completion date. See Spec Section 01 00 01-General Requirements
Time period for completion of the ETO work is a specified number of days following the "Notice to Proceed" for the overall project
ETO work identified in plans/specs
ETO 1: To be completed within 180 days of Notice to Proceed.
ETO 2: To be completed within 400 days of Notice to Proceed
ETO 3: To be completed within 400 days of Notice to Proceed
11 Office of Construction and Facilities Management
Liquidated Damages
$1,292.00 for each calendar day of delay
Insurance
See Solicitation pages 52 & 53
Certificate of Insurance required prior to commencing work
Worker’s compensation and employers liability
General Liability
Automobile Liability
12 Office of Construction and Facilities Management
Pre-Proposal Inquiries (PPI)/Requests for Information (RFI’S)
Use Solicitation PPI Form (Attachment 4)
Questions Due: December 11, 2020, at 12:00 PM CT
Email to:
Jeffrey.gerbensky@va.gov, and
David.martino@va.gov
The subject line to read “Great Lakes National Cemetery Phase 2 Development RFP #:
36C10F20R0098”
Answers posted on or about: December 18, 2020 mailto:Jeffrey.gerbensky@va.gov mailto:David.martino@va.gov
13 Office of Construction and Facilities Management
Submission Instructions
Volume I – Technical Proposal (limit 67 pages)
➢ Title Page (see Solicitation page 13)
➢ Tab 1 – Past Performance
➢Project Summaries
➢PPQ & CPARS Reports
➢ Tab 2 – Relevant Experience
➢Relevant Projects
➢Key Personnel
➢ Tab 3 – Technical Approach
➢ Tab 4 – Construction/Project Management
➢Project Org Chart & Narrative
➢Capacity to Perform Work
➢Quality Control Plan
➢Safety Plan
➢Schedule
14 Office of Construction and Facilities Management
Submission Instructions
Volume II – Price Proposal (limit 30 pages)
➢ Title Page (see Solicitation page 13)
➢ Tab 1 –
➢Executed Solicitation, Offer and Award Form (SF1442) (pages 1-2).
Offeror shall complete Blocks 14-20C.
➢Completed Offer Schedule (page 3).
➢Solicitation Amendments – complete boxes 15A-C (SF 30) for each amendment issued & include a copy in your proposal.
➢ Tab 2 –
➢Scanned, legible, copy of Executed Bid Guarantee (SF-24)
➢ Tab 3 –
➢Printed copy “Representations and Certifications” as submitted on https://www.sam.gov/SAM/
15 Office of Construction and Facilities Management
Submission Instructions
Proposal Submission Instructions
➢ Email:
• Submit one (1) copy of the Technical Proposal (Volume I), & one (1) copy of their Price Proposal (Volume II).
➢Emailed proposals shall be sent to the Contracting Officer at jeffrey.gerbensky@va.gov by the due date & time shown in Box 13a of solicitation form SF 1442 (or as subsequently amended).
➢40 mb max file size limit
➢ If the file size is greater than 40MB, separate document into multiple files and label files logically & sequentially, for example Volume 1-part 1, Volume 1-part 2, etc.
➢Adobe PDF is the only file format that will be accepted.
➢ Ignore any solicitation references to Vendor Portal – they are an error and will be corrected via amendment.
mailto:jeffrey.gerbensky@va.gov
16 Office of Construction and Facilities Management
Milestones
1 Solicitation Issued November 20, 2020
2 Proposal Due Date January 6, 2020, 12:00PM CT
3 Contract Award (TENTATIVE) March 31, 2021
4 Notice To Proceed (TENTATIVE) April 19, 2021
17 Office of Construction and Facilities Management
Project Scope/Overview
VA Office of Construction &
Facilities Management
Dave Martino, Project Manager
18 Office of Construction and Facilities Management
Site Walkthrough
December 2, 2020
10am – 1pm CT
Cemetery Administration Bldg
4200 Belford Rd
Holly, MI 48442
(248) 328-0386
Site Walkthrough
19 Office of Construction and Facilities Management
QUESTIONS???
No technical questions will be answered today or during the pre-proposal site visit.
Submit all technical Requests for Information in writing per the solicitation.
Questions