This document is a combined synopsis/solicitation for a VA Enterprise Learning Management Solution (VA ELMS) under Solicitation Number 36C10B24R0004. The Department of Veterans Affairs is seeking a Commercial off-the-Shelf (COTS) Software as a Service (SaaS) solution hosted in a FedRAMP authorized cloud environment at the moderate impact level. The solution will provide a comprehensive learning management system to support the VA's enterprise-wide talent development and learning management activities.
The solicitation is for a 12-month base period with four 12-month option periods and five optional tasks for license expansions. Proposals are due by July 1, 2024. The solicitation is set-aside for small businesses under NAICS code 541519 with a $34 million size standard. Key requirements include project management, enterprise architecture, system design and implementation, system hosting, licensing, maintenance, production support, system integration, and data governance. The VA is the sole customer and primary stakeholders include all VA staff who access training as well as various VA offices and administrations.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C10B24R0004
PAGE 1 OF
1. REQUISITION NO.
2. CONTRACT NO.
3. AWARD/EFFECTIVE DATE
4. ORDER NO.
5. SOLICITATION NUMBER
6. SOLICITATION ISSUE DATE
a. NAME
b. TELEPHONE NO. (No Collect Calls)
8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY
CODE
10. THIS ACQUISITION IS
UNRESTRICTED OR
SET ASIDE:
% FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ
IFB
RFP
15. DELIVER TO
CODE
16. ADMINISTERED BY
CODE
17a. CONTRACTOR/OFFEROR
CODE
FACILITY CODE
18a. PAYMENT WILL BE MADE BY
CODE
TELEPHONE NO.
UEI:
EFT:
PHONE:
FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19.
20.
21.
22.
23.
24.
ITEM NO.
SCHEDULE OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________
29. AWARD OF CONTRACT: REF. ___________________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DATED ________________________________. YOUR OFFER ON SOLICITATION
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
(REV. NOV 2021)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
F363113-24-0000085
36C10B24R0004 06-24-2024 Kawana Tyler-Simms 848-377-5135
See Block 20
36C10B Department of Veterans Affairs Technology Acquisition Center 23 Christopher Way Eatontown NJ 07724
X
541519 $34 Million
N/A
See Delivery Schedule
36C10B Department of Veterans Affairs Technology Acquisition Center
23 Christopher Way Eatontown NJ 07724
36C10A Department of Veterans Affairs Technology Acquisition Center Financial Services Center PO Box 149971 Austin TX 78714-8971
Title: VA Enterprise Learning Management Solution Type of Contract: Firm Fixed Price Period of Performance: 12-month base, with four 12-month option periods and five optional tasks.
BLOCK 8: INITIAL SOLICITATION INSTRUCTIONS (For PHASE ONE):
At this time ONLY PHASE ONE Proposal Submissions will be accepted, due date is July 1, 2024, at 11:00 EST. PHASE ONE submission shall be in accordance with Section E.14 Proposal Submission Instructions. Additionally, Offeror’s shall include the following additional information with Phase One submission:
- Offeror Company Name/Address
- Offeror POC information
- Contractor’s Unique Entity ID (SAM) Please refer to Sections E.13 Basis for Award and E.14 Proposal Submission Instructions for further information.
See CONTINUATION Page
Table of Contents
| SECTION B - CONTINUATION OF SF 1449 BLOCKS | 4 |
| B.1 GOVERNING LAW | 4 |
| B.2 SOFTWARE LICENSE, MAINTENANCE AND TECHNICAL SUPPORT | 5 |
| B.3 CONTRACT ADMINISTRATION DATA | 7 |
| B.4 PRICE SCHEDULE | 9 |
| B.5 PERFORMANCE WORK STATEMENT | 57 |
| SECTION C - CONTRACT CLAUSES | 162 |
| C.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 162 |
| C.2 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021) | 163 |
| C.3 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (MAY 2024) | 164 |
| C.4 52.217-7 OPTION FOR INCREASED QUANTITY—SEPARATELY PRICED LINE ITEM (MAR 1989) | 173 |
| C.5 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000) | 173 |
| C.6 52.227-19 COMMERCIAL COMPUTER SOFTWARE LICENSE (DEC 2007) | 174 |
| C.7 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022) | 175 |
| C.8 VAAR 852.204-71 INFORMATION AND INFORMATION SYSTEMS SECURITY (FEB 2023) | 175 |
| C.9 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION) | 183 |
| C.10 MANDATORY WRITTEN DISCLOSURES | 185 |
| C.11 VAAR 852.237-75 KEY PERSONNEL (OCT 2019) | 185 |
| C.12 VAAR 852.211-76 LIQUIDATED DAMAGES – REIMBURSEMENT FOR DATA BREACH COSTS (FEB 2023) ALTERNATE I (FEB 2023) | 186 |
| C.13 VAAR 852.239-76 INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY (FEB 2023) | 187 |
| SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS | 189 |
| SECTION E - SOLICITATION PROVISIONS | 190 |
| E.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 190 |
| E.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 191 |
| E.3 52.204-29 FEDERAL ACQUISITON SUPPLY CHAIN SECURITY ACT ORDERS-REPRESENTATION AND DISCLOSURES (DEC 2023) | 193 |
| E.4 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 195 |
| E.5 52.209-11 REPRESENTATION BY CORPORATIONS REGARDING DELINQUENT TAX LIABILITY OR A FELONY CONVICTION UNDER ANY FEDERAL LAW (FEB 2016) | 196 |
| E.6 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (MAY 2024) | 197 |
| E.7 52.216-1 TYPE OF CONTRACT (APR 1984) | 214 |
| E.8 52.233-2 SERVICE OF PROTEST (SEP 2006) | 214 |
| E.9 52.204-20 PREDECESSOR OF OFFEROR (AUG 2020) | 214 |
| E.10 52.209-5 CERTIFICATION REGARDING RESPONSIBILITY MATTERS (AUG 2020) | 215 |
| E.11 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023) | 217 |
| E.12 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008) | 217 |
| E.13 BASIS FOR AWARD | 218 |
| E.14 PROPOSAL SUBMISSION INSTRUCTIONS | 223 |
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 GOVERNING LAW
Federal law and regulations, including the Federal Acquisition Regulations (FAR), shall govern this Contract/Order. Commercial license agreements may be made a part of this Contract/Order but only if both parties expressly make them an addendum hereto. If the commercial license agreement is not made an addendum, it shall not apply, govern, be a part of or have any effect whatsoever on the Contract/Order; this includes, but is not limited to, any agreement embedded in the computer software (clickwrap), any agreement that is otherwise delivered with or provided to the Government with the commercial computer software or documentation (shrinkwrap), or any other license agreement otherwise referred to in any document. If a commercial license agreement is made an addendum, only those provisions addressing data rights regarding the Government’s use, duplication and disclosure of data (e.g., restricted computer software) are included and made a part of this Contract/Order, and only to the extent that those provisions are not duplicative or inconsistent with Federal law, Federal regulation, the incorporated FAR clauses and the provisions of this Contract/Order; those provisions in the commercial license agreement that do not address data rights regarding the Government’s use, duplication and disclosure of data shall not be included or made a part of the Contract/Order. Federal law and regulation including, without limitation, the Contract Disputes Act (41 U.S.C. § 7101 et seq.), the Anti-Deficiency Act (31 U.S.C. § 1341 et seq.), the Competition in Contracting Act (41 U.S.C. § 3301 et seq.), the Prompt Payment Act (31 U.S.C. §3901 et seq.), Contracts for Data Processing or Maintenance (38 USC § 5725), and FAR clauses 52.212-4, 52.227-14, 52.227-19 shall supersede, control, and render ineffective any inconsistent, conflicting, or duplicative provision in any commercial license agreement. In the event of conflict between this Clause and any provision in the Contract/Order or the commercial license agreement or elsewhere, the terms of this Clause shall prevail. Claims of patent or copyright infringement brought against the Government as a party shall be defended by the U.S. Department of Justice (DOJ). 28 U.S.C. § 516. At the discretion of DOJ, the Contractor may be allowed reasonable participation in the defense of the litigation. Any additional changes to the Contract/Order must be made by contract/order modification (Standard Form 30) and shall only be affected by a warranted Contracting Officer. Nothing in this Contract/Order or any commercial license agreement shall be construed as a waiver of sovereign immunity.
B.2 SOFTWARE LICENSE, MAINTENANCE AND TECHNICAL SUPPORT
(1). Definitions. a) Licensee. The term “licensee” shall mean the U.S. Department of Veterans Affairs (“VA”) and is synonymous with “Government.” b) Licensor. The term “licensor” shall mean the Contractor having the necessary license or ownership rights to deliver license, software maintenance and support of the computer software being acquired. The term “Contractor” is the party identified in Block 17a on the SF1449. If the Contractor is a reseller and not the Licensor, the Contractor remains responsible for performance under this Contract/Order. c) Software. The term “software” shall mean the licensed computer software product(s) cited in the Schedule of Supplies/Services. d) Maintenance. The term “maintenance” is the process of enhancing and optimizing software, as well as remedying defects. It shall include all new fixes, patches, releases, updates, versions, and upgrades, as further defined below. e) Technical Support. The term “technical support” refers to the range of services providing assistance for the software via the telephone, email, a website or otherwise. f) Release or Update. The term “release” or “update” are terms that refer to a revision of software that contains defect corrections, minor enhancements or improvements of the software’s functionality. This is usually designated by a change in the number to the right of the decimal point (e.g., from Version 5.3 to 5.4). An example of an update is the addition of new hardware. g) Version or Upgrade. The term “version” or “upgrade” are terms that refer to a revision of software that contains new or improved functionality. This is usually designated by a change in the number to the left of the decimal point (e.g., from Version 5.4 to 6).
(2). Software License. a) Unless otherwise stated in the Schedule of Supplies/Services, the Performance Work Statement or Product Description, the software license provided to the Government is a perpetual, nonexclusive license to use the software. b) The Government may use the software in a networked environment. c) Any dispute regarding the license grant or usage limitations shall be resolved in accordance with the Disputes Clause incorporated in FAR 52.212-4(d). d) All limitations of software usage are expressly stated in the Schedule of Supplies/Services and the Performance Work Statement/Product Description.
(3). Software Maintenance and Technical Support.
a) If the Government desires to continue software maintenance and support beyond the period of performance identified in this Contract/Order, the Government will issue a separate contract or order for maintenance and support. Conversely, if a contract or order for continuing software maintenance and technical support is not received, the Contractor is neither authorized nor permitted to renew any of the previously furnished services.
b) The Contractor shall provide software support services, which includes periodic updates, enhancements and corrections to the software, and reasonable technical support, all of which are customarily provided by the Contractor to its commercial customers so as to cause the software to perform according to its specifications, documentation or demonstrated claims.
c) Any telephone support provided by Contractor shall be at no additional cost.
d) The Contractor shall provide all maintenance services in a timely manner in accordance with the Contractor’s customary practice or as defined in the Performance Work Statement or Product Description. However, prolonged delay (exceeding 2 business days) in resolving software problems will be noted in the Government’s various past performance records on the Contractor (e.g., www.cpars.gov).
e) If the Government allows the maintenance and support to lapse and subsequently wishes to reinstate it, any reinstatement fee charged shall not exceed the amounts that would have been charged if the Government had not allowed the subscription to lapse.
(4). Disabling Software Code. The Government requires delivery of computer software that does not contain any code that will, upon the occurrence or the nonoccurrence of any event, disable the software. Such code includes but is not limited to a computer virus, restrictive key, node lock, time-out or other function, whether implemented by electronic, mechanical, or other means, which limits or hinders the use or access to any computer software based on residency on a specific hardware configuration, frequency of duration of use, or other limiting criteria. If any such disabling code is present, the Contractor agrees to indemnify the Government for all damages suffered as a result of a disabling caused by such code, and the Contractor agrees to remove such code upon the Government’s request at no extra cost to the Government. Inability of the Contractor to remove the disabling software code will be considered an inexcusable delay and a material breach of contract, and the Government may exercise its right to terminate for cause. In addition, the Government is permitted to remove the code as it deems appropriate and charge the Contractor for consideration for the time and effort expended in removing the code.
(5). Manuals and Publications. Upon Government request, the Contractor shall furnish the most current version of the user manual and publications for all products/services provided under this Contract/Order at no cost.
B.3 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR: TBD`
b. GOVERNMENT: Contracting Officer 36C10B Patrick Hamilton Department of Veterans Affairs Technology Acquisition Center 23 Christopher Way Eatontown NJ 07724
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
| [X] |
| 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or |
| [] |
| 52.232-36, Payment by Third Party |
3. INVOICES: Invoices shall be submitted in arrears:
| a. Quarterly | [] |
| b. Semi-Annually | [] |
| c. Other | [X] In accordance with Section B.4, Price Schedule |
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
5. Subcontracting Plan - Monitoring and Compliance The Contractor is advised in performing contract administration functions, the CO may use the services of a support contractor(s) to assist in assessing the Contractor's compliance with the plan, including reviewing the Contractor's accomplishments in achieving the subcontracting goals in the plan. To that end, the support Contractor(s) may require access to the contractor's business records or other proprietary data to review such business records regarding the contractor's compliance with this requirement. All support contractors conducting this review on behalf of VA will be required to sign an “Information Protection and Non-Disclosure and Disclosure of Conflicts of Interest Agreement” to ensure the contractor's business records or other proprietary data reviewed or obtained in the course of assisting the CO in assessing the contractor for compliance are protected to ensure information or data is not improperly disclosed or other impropriety occurs. Furthermore, if VA determines any services the support contractor(s) will perform in assessing compliance are advisory and assistance services as defined in FAR 2.101, Definitions, the support Contractor(s) must also enter into an agreement with the contractor to protect proprietary information as required by FAR 9.505-4, obtaining access to proprietary information, paragraph (b). The Contractor is required to cooperate fully and make available any records as may be required to enable the CO to assess the contractor compliance with the subcontracting plan.
ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
| AMENDMENT NO |
| DATE |
B.4 PRICE SCHEDULE
Note: All deliverables shall be electronically submitted to the VA Program Manager Contracting Officer’s Representative (COR), and the Contracting Officer (CO). Days used in the table below refer to calendar days unless otherwise stated. Deliverables with due dates falling on a weekend or holiday shall be submitted the following Government workday after the weekend or holiday.
Point of Contact:
VA Program Manager/COR Name: TBD Email: TBD Phone: TBD
Inspection and Acceptance: Destination
Base Period (12 Months) Period of Performance (PoP) shall be 12-months after contract award date.
| CONTRACT LINE ITEM NUMBER (CLIN) |
| Description |
| Qty |
Unit
Unit Price
Extended Price
| 0001 |
| PROGRAM MANAGEMENT AND PLANNING IN ACCORDANCE WITH (IAW) PWS PARAGRAPH 5.1 AND ALL OF ITS SUBPARAGRAPHS. |
This Firm Fixed Price (FFP) Contract Line Item Number (CLIN) includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS section 5.1 and all of its subparagraphs.
Electronic submission to: Veterans Affairs (VA) Program Manager (PM), Contracting Officer Representative (COR), Contracting Officer (CO).
Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0001AA |
| Weekly VA ELMS Status Call Meeting Materials IAW PWS Paragraph 5.1.1 |
Due three (3) business days prior to the meeting, then every seven (7) days thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0001AB |
| Weekly VA ELMS Status Call Meeting Minutes and Action Items IAW PWS Paragraph 5.1.1 |
Due two (2) business days after each meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 0001AC |
| Kick-Off Meeting Agenda and Materials (PowerPoint or Similar Presentation) IAW PWS Paragraph 5.1.2 |
Due five (5) business days before the meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 0001AD |
| Kick-Off Meeting IAW PWS Paragraph 5.1.2 |
Due ten (10) business days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0001AE |
| Kick-Off Meeting Minutes IAW PWS Paragraph 5.1.2 |
Due two (2) business days after the meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 0001AF |
| Monthly Status Reports IAW PWS Paragraph 5.1.3 |
Due thirty (30) days after contract award and then the second Tuesday of every month thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0001AG |
| User Help Guides IAW PWS Paragraph 5.1.5 |
Due thirty (30) days prior to implementation of any functional/technical changes to the application.
| 1 |
| LO |
| NSP |
| NSP |
| 0001AH |
| Technical Documents IAW PWS Paragraph 5.1.5 |
Due thirty (30) days prior to implementation of any functional/technical changes to the application.
| 1 |
| LO |
| NSP |
| NSP |
| 0001AI |
| Online Help References IAW PWS Paragraph 5.1.5 |
Due thirty (30) days prior to implementation of any functional/technical changes to the application.
| 1 |
| LO |
| NSP |
| NSP |
| 0001AJ |
| Product Documentation IAW PWS Paragraph 5.1.5 |
Due thirty (30) days prior to implementation of any functional/technical changes to the application.
| 1 |
| LO |
| NSP |
| NSP |
| 0001AK |
| Installation Guides IAW PWS Paragraph 5.1.5 |
Due thirty (30) days prior to implementation of any functional/technical changes to the application.
| 1 |
| LO |
| NSP |
| NSP |
| 0001AL |
| Reference Materials IAW PWS Paragraph 5.1.5 |
Due thirty (30) days prior to implementation of any functional/technical changes to the application.
| 1 |
| LO |
| NSP |
| NSP |
| 0001AM |
| Release Notes IAW PWS Paragraph 5.1.5 |
Due thirty (30) days prior to implementation of any functional/technical changes to the application.
| 1 |
| LO |
| NSP |
| NSP |
| 0002 |
| PROJECT MANAGEMENT PLANNING IAW PWS Paragraph 5.2 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.2 and all of its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0002AA |
| Contractor Project Management Plan (CPMP) IAW PWS Paragraph 5.2.1 |
Due thirty (30) days after contract award and updated monthly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0002AB |
| Integrated Master Schedule (IMS) IAW PWS Paragraph 5.2.1 |
Due seven (7) days after contract award and updated weekly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0002AC |
| Decision Log IAW PWS Paragraph 5.2.1 |
Due sixty (60) days after contract award and updated seven (7) days after any change.
| 1 |
| LO |
| NSP |
| NSP |
| 0002AD |
| Risk Management Plan (RMP) IAW PWS Paragraph 5.2.2 |
Due thirty (30) days after contract award and three (3) business days after any changes thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0002AE |
| Risk Log IAW PWS Paragraph 5.2.2 |
Due thirty (30) days after contract award and seven (7) days after any change thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0002AF |
| Risk Matrix IAW PWS Paragraph 5.2.2 |
Due thirty (30) days after contract award and seven (7) days after any change thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0002AG |
| Subject Matter Expert (SME) Evaluation Implementation Kick-Off Meeting Agenda and Materials IAW PWS Paragraph 5.2.3 (PowerPoint or Similar Presentation) |
Due five (5) days prior to the meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 0002AH |
| SME Evaluation Implementation Kick-Off Meeting Minutes IAW PWS Paragraph 5.2.3 |
Due two (2) days after the kick-off meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 0002AI |
| SME Evaluation Implementation Strategy IAW PWS Paragraph 5.2.4 |
Due five (5) days prior to the Implementation Kick-off.
| 1 |
| LO |
| NSP |
| NSP |
| 0002AJ |
| SME Evaluation Implementation Schedule IAW PWS Paragraph 5.2.4 |
Due two (2) days after the Kick-off Meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 0003 |
| ENTERPRISE ARCHITECTURE IAW PWS Paragraph 5.3 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.3 and all of its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0003AA |
| Enterprise Architecture (EA) Plan IAW PWS Paragraph 5.3 |
Due thirty (30) days after contract award and updated quarterly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0004 |
| SYSTEM DESIGN AND IMPLEMENTATION IAW PARAGRAPH 5.4 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.4 and all its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
0004AA
Enterprise Solution Design Documentation (ESDD) with Updates IAW PWS Paragraph 5.4 Draft due twenty (20) days prior to implementation or upgrades. Final due no later than fifteen (15) days following the implementation or any upgrades.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AB |
| Deployment Plan IAW PWS Paragraph 5.4 |
Draft due thirty (30) days after contract award. Final due ten (10) days after receipt of Government comments. Updated quarterly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AC |
| Pre-Deployment Checklist IAW PWS Paragraph 5.4 |
Due thirty (30) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AD |
| Post-Deployment Checklist IAW PWS Paragraph 5.4 |
Due thirty (30) days after Solution Deployment.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AE |
| Deployment Schedules IAW PWS Paragraph 5.4 |
Due thirty (30) days before Solution Deployment.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AF |
| Service Desk Workflow IAW PWS Paragraph 5.4 |
Due thirty (30) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AG |
| Service Desk Communication Plan IAW PWS Paragraph 5.4 |
Due thirty (30) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AH |
| Service Desk Call-in Tree IAW PWS Paragraph 5.4 |
Due thirty (30) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AI |
| Service Desk After Action Reports IAW PWS Paragraph 5.4 |
Due thirty (30) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AJ |
| Configuration Management Plan IAW PWS Paragraph 5.4.1.1 |
Due thirty (30) days after contract award and updated quarterly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
0004AK
Configuration Control Documents IAW PWS Paragraph 5.4.1.1 Due thirty (30) days after contract award and updated quarterly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AL |
| Configuration Workbooks IAW PWS Paragraph 5.4.1.1 |
Due ten (10) days before each Configuration Workshop and updated after any configuration change.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AM |
| Configuration Review Documentation IAW PWS Paragraph 5.4.1.1 |
Due thirty (30) days after each configuration workshop.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AN |
| Use Case Documentation IAW PWS Paragraph 5.4.1.1 |
Due thirty (30) days after each configuration workshop.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AO |
| Configuration Decision Documentation IAW PWS Paragraph 5.4.1.1 |
Due thirty (30) days after each configuration workshop.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AP |
| Initial Plan of Action & Milestone (POA&M) Documents IAW PWS Paragraph 5.4.1.2 |
Due at time of award.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AQ |
| VA Section 508 Audit POA&M Documents IAW PWS Paragraph 5.4.1.2 |
Due within fifteen (15) days of receiving VA Section 508 audit results.
| 1 |
| LO |
| NSP |
| NSP |
0004AR
Section 508 Testing and Results Documentation IAW Paragraph 5.4.1.2 Draft due one (1) week after 508 testing. Final due ten (10) days after receipt of Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AS |
| Data Rights and Ownership IAW PWS Paragraph 5.4.1.3 |
Code and associated artifacts for any product developed exclusively for VA.
Due sixty (60) days of Government acceptance.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AT |
| Test Plan IAW Paragraph 5.4.1.4 |
Draft Due thirty (30) days before User Acceptance Testing (UAT) testing to begin. Final due seven (7) days after Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AU |
| Test Results Report IAW 5.4.1.4 |
Due thirty (30) days after testing.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AV |
| Remediation Plan IAW Paragraph 5.4.1.4 |
Due thirty (30) days after contract award and updated as testing requires.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AW |
| De-identified Data Migration Plan for SME Testing IAW Paragraph 5.4.2.1 |
Draft due sixty (60) days after contract award. Final due thirty (30) days after receipt of Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AX |
| Data Migration Plan IAW Paragraph 5.4.2.1 |
Draft due sixty (60) days after contract award. Final due thirty (30) days after receipt of Government comments.
| 1 |
| LO |
| NSP |
| NSP |
0004AY
Lessons Learned IAW Paragraph 5.4.2.1 Due sixty (60) days after data migration complete. Then due on an as needed basis throughout contract lifecycle.
| 1 |
| LO |
| NSP |
| NSP |
| 0004AZ |
| Fit Gap Analysis Report IAW Paragraph 5.4.2.1 |
Due thirty (30) DAC award.
| 1 |
| LO |
| NSP |
| NSP |
0004BA
User Acceptance Test Plan for SMEs IAW Paragraph 5.4.3 Draft due thirty (30) days before scheduled User Acceptance Test (UAT). Final due ten (10) days after receipt of Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BB |
| UAT Scenarios/Scripts for SMEs IAW Paragraph 5.4.3 |
Draft due thirty (30) days before scheduled UAT. Final due ten (10) days after receipt of Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BC |
| UAT Test Summary Reports IAW Paragraph 5.4.3 |
Due one (1) week after completion of UAT.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BD |
| Weekly Defect Report IAW Paragraph 5.4.4 |
Due sixty (60) days after contract award. Then updated weekly thereafter once in production.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BE |
| Weekly Defect Meeting Agenda and Materials IAW Paragraph 5.4.4 |
Due one (1) business day before scheduled meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BF |
| Weekly Defect Meeting Minutes IAW Paragraph 5.4.4 |
Due one (1) business day after scheduled meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BG |
| Defect Management Plan IAW Paragraph 5.4.4 |
Draft due sixty (60) days after contract award. Final due ten (10) days after receiving Government comments.
| 1 |
| LO |
| NSP |
| NSP |
0004BH
Training Plan for SMEs IAW Paragraph 5.4.5.1 Draft due thirty (30) days after contract award. Final due ten (10) days after receiving Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BI |
| Satisfaction Survey for SMEs IAW Paragraph 5.4.5.1 |
Due thirty (30) days after each training session is conducted.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BJ |
| Quarterly SME Training Plan IAW Paragraph 5.4.5.1 |
Due ninety (90) days after contract award then updated quarterly.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BK |
| Set of Frequently Asked Questions IAW Paragraph 5.4.5.2 |
Due thirty (30) days before initial solution deployment. Updated monthly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BL |
| User Guides IAW Paragraph 5.4.5.2 |
Due thirty (30) days before initial solution deployment. Updated monthly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BM |
| Training Manuals IAW Paragraph 5.4.5.2 |
Due thirty (30) days before initial solution deployment. Updated monthly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BN |
| Job Aids IAW Paragraph 5.4.5.2 |
Due thirty (30) days before initial solution deployment. Updated monthly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BO |
| Training Videos IAW Paragraph 5.4.5.2 |
Due thirty (30) days before initial solution deployment. Updated monthly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BP |
| Activity Guides IAW Paragraph 5.4.5.2 |
Due thirty (30) days before initial solution deployment. Updated monthly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BQ |
| Micro-Learning IAW Paragraph 5.4.5.2 |
Due thirty (30) days before initial solution deployment. Updated monthly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BR |
| Simulation Learning – Self Paced IAW Paragraph 5.4.5.2 |
Due thirty (30) days before initial solution deployment. Updated monthly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BS |
| Train-the-Trainer Training Sessions IAW Paragraph 5.4.5.3 |
Due thirty (30) days prior to training session.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BT |
| Train-the-Trainer Session Recordings IAW Paragraph 5.4.5.3 |
Due seven (7) days after training session.
| 1 |
| LO |
| NSP |
| NSP |
| 0004BU |
| VA SME Training Instance IAW Paragraph 5.4.5.3 |
Due thirty (30) days prior to training session.
| 1 |
| LO |
| NSP |
| NSP |
| 0005 |
| OPERATION AND MAINTENANCE SUPPORT IAW PARAGRAPH 5.5 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.5 and all of its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0005AA |
| Operation and Maintenance Plan IAW Paragraph 5.5 |
Draft due thirty (30) days after contract award. Final due ten (10) days after Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0005AB |
| Disaster Recovery Plan IAW Paragraph 5.5 |
Draft due thirty (30) days after contract award. Final due ten (10) days after Government comments. Updated annually thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0005AC |
| Release Notes IAW Paragraph 5.5 |
Draft due thirty (30) days after solution release. Final due ten (10) days after Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0006 |
| SYSTEM HOSTING IAW PARAGRAPH 5.6 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.6 and all its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0006AA |
| Weekly Hosting Reports IAW Paragraph 5.6 |
Due seven (7) days after contract award and then updated weekly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0006AB |
| Monthly Hosting Summary and Operations Metrics Reports IAW Paragraph 5.6 |
Due thirty (30) days after contract award and then updated every 2nd Tuesday of every month thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0006AC |
| System Capacity Strategy IAW Paragraph 5.6 |
Draft due sixty (60) days after contract award. Final due ten (10) days after Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0006AD |
| Two Enterprise-Wide Instances: (Sandbox & Customer Training) IAW Paragraph 5.6 |
Due thirty (30) days prior to solution release.
| 1 |
| LO |
| NSP |
| NSP |
| 0006AE |
| FedRAMP System Security Plan (SSP) and Supporting Documentation IAW Paragraph 5.6.1 |
Due seventy-five (75) calendar days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0006AF |
| VA Implementation Diagram IAW Paragraph 5.6.1 |
Due ten (10) calendar days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0006AG |
| 3PAO Security Assessment Plan (SAP) IAW Paragraph 5.6.1 |
Due ninety (90) calendar days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0006AH |
| 3PAO Security Assessment Report (SAR) IAW Paragraph 5.6.1 |
Due ninety (90) calendar days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0006AI |
| IRP Scenario IAW Paragraph 5.6.1 |
Due thirty (30) calendar days after SSP being delivered.
| 1 |
| LO |
| NSP |
| NSP |
| 0007 |
| SYSTEM LICENSING IAW PARAGRAPH 5.7 |
This FFP CLIN includes all tasks, labor, supplies, program management and travel required for the successful completion of the services detailed in PWS Section 5.7 and all its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0007AA |
| 2,000 Full Access Licenses and Maintenance IAW Paragraph 5.7 |
Due thirty (30) days prior to solution release.
| 1 |
| LO |
| NSP |
| NSP |
| 0007AB |
| 1,000 Limited Licenses and Maintenance IAW Paragraph 5.7 |
Due thirty (30) days prior to solution release.
| 1 |
| LO |
| NSP |
| NSP |
| 0007AC |
| Up to 1,000 Individual or Enterprise Virtual Classroom Licenses and Maintenance IAW Paragraph 5.7.1 |
Due thirty (30) days prior to solution release.
| 1 |
| LO |
| NSP |
| NSP |
| 0008 |
| SOFTWARE MAINTENANCE IAW PARAGRAPH 5.8 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.8 and all its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0008AA |
| Error Troubleshooting Guide IAW Paragraph 5.8.1 |
Draft due sixty (60) days after contract award. Final due ten (10) days after Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0008AB |
| Major and Minor Release Notes IAW Paragraph 5.8.1 |
Due sixty (60) days after each Release.
| 1 |
| LO |
| NSP |
| NSP |
| 0008AC |
| Maintenance Release Notes IAW Paragraph 5.8.1 |
Due sixty (60) days after each Maintenance Release.
| 1 |
| LO |
| NSP |
| NSP |
| 0008AD |
| Out of Cycle Release Notes IAW Paragraph 5.8.1 |
Due sixty (60) days after each Out-of-Cycle Release.
| 1 |
| LO |
| NSP |
| NSP |
| 0009 |
| PRODUCTION SUPPORT IAW PARAGRAPH 5.9 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.9 and all its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0009AA |
| Routine Maintenance Schedule IAW Paragraph 5.9 |
Due thirty (30) days prior to System Maintenance.
| 1 |
| LO |
| NSP |
| NSP |
| 0009AB |
| Issue Tracking Log IAW Paragraph 5.9 |
Due thirty (30) days after contract award and updated weekly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0010 |
| SOFTWARE INTEGRATION IAW PARAGRAPH 5.10 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.10 and all its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0010AA |
| System Integration Plan IAW Paragraph 5.10.1 |
Draft due ninety (90) days after contract award. Final due ten (10) days after Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0010AB |
| System Integration SOP IAW Paragraph 5.10.1 |
Draft due one hundred twenty (120) DAC award. Final due thirty (30) days after Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0010AC |
| System Integration Workbooks IAW Paragraph 5.10.1 |
Due one hundred twenty (120) days after contract award. Final due thirty (30) days after new integrations set-up.
| 1 |
| LO |
| NSP |
| NSP |
| 0010AD |
| Application Programming Interface (API) IAW Paragraph 5.10.1.1 |
Due one hundred twenty (120) DAC award.
| 1 |
| LO |
| NSP |
| NSP |
0010AE
Flat File Data Exchange Templates IAW Paragraph 5.10.1.1 Due one hundred twenty (120) DAC award.
| 1 |
| LO |
| NSP |
| NSP |
| 0010AF |
| EDR Memorandum of Understanding and Interconnection Security Agreement IAW Paragraph 5.10.1.1 |
Draft due thirty (30) days prior to integration effective date. Final due thirty (30) after Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0010AG |
| EDR Interface Control Document IAW Paragraph 5.10.1.1 |
Draft due thirty (30) days prior to integration effective date. Final due thirty (30) days after Government’s comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0010AH |
| EDR Integration Requirements Specification Document (iRSD) IAW Paragraph 5.10.1.1 |
Draft due thirty (30) days prior to integration effective date. Final due thirty (30) days after Government’s comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0011 |
| APPLICATION MONITORING/PROGRAM EVALUATION IAW PARAGRAPH 5.11 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.11 and all its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0011AA |
| Weekly Performance Monitoring Reports IAW Paragraph 5.11 |
Due seven (7) days after contract award and weekly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0011AB |
| Monthly Performance Monitoring Reports IAW Paragraph 5.11 |
Due thirty (30) days after contract award and on the 2nd Tuesday of every month thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0011AC |
| Readiness Assessment Report IAW Paragraph 5.11.1 |
Due thirty (30) days before each planned deployment.
| 1 |
| LO |
| NSP |
| NSP |
| 0012 |
| TRANSITION IN/OUT PLAN IAW Paragraph 5.12 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.12 and all its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0012AA |
| Transition Plan IAW 5.12 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013 |
| TEMPORARY AUTHORITY TO OPERATE (TATO)/AUTHORITY TO OPERATE (ATO) IAW PARAGRAPH 5.13 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.13 and all its subparagraphs.
Electronic Submission: VA PM, COR, and CO.
Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0013AA |
| Security Test and Evaluation Plan IAW Paragraph 5.13 |
Draft due sixty (60) days after contract award. Final due ten (10) days after Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AB |
| System Accreditation Boundary IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AC |
| System Assessment and Accreditation Plan IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AD |
| SCA Signatory Authority IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AE |
| System Security and Privacy Plan (SSPP) IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AF |
| Risk Assessment (RA) IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AG |
| Privacy Threshold Assessment (PTA) – VA 6508 IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AH |
| Privacy Impact Statement (PIA) – VA 6508.1 IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AI |
| System of Record Notice (SORN) – VA 6300.5 IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AJ |
| Privacy Act Statement – VA 6300.5 IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AK |
| IS Contingency Plan (ISCP) IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AL |
| Disaster Recovery Plan (DRP) IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AM |
| Incident Response Plan (IRP) IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AN |
| Configuration Management Plan (CMP) IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AO |
| SCA Security Configuration Checklist IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0013AP |
| Interconnected Systems Agreements (ISAs and/or MOUs) IAW Paragraph 5.13 |
Due sixty (60) days after contract award.
| 1 |
| LO |
| NSP |
| NSP |
| 0014 |
| DATA DICTIONARY IAW PARAGRAPH 5.14 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.14 an all its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0014AA |
| Data Dictionary IAW Paragraph 5.14 |
Due sixty (60) days after contract award and updated quarterly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0015 |
| DATA GOVERNANCE AND SUPPORT IAW PARAGRAPH 5.15 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.15 and all its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 0015AA |
| Data Quality Audit Strategy, IAW Paragraph 5.15.12 |
Due sixty (60) days after contract award and updated quarterly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0015AB |
| Weekly Strategic Data Reports, IAW Paragraph 5.15.12 |
Due seven (7) days after contract award and updated Weekly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0015AC |
| Bi-Weekly Data Trend Reports, IAW Paragraph 5.15.12 |
Due fourteen (14) days after contract award and updated every fourteen (14) days thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0015AD |
| Monthly Data Quality Reports, IAW Paragraph 5.15.12 |
Due thirty (30) days after contract award and updated the third Tuesday of each month thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0015AE |
| Quarterly Data Quality Audits (total of 4), IAW Paragraph 5.15.12 |
Due sixty (60) days after contract award and updated quarterly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0015AF |
| Data Quality Artifacts, IAW Paragraph 5.15.12 |
Due thirty (30) days after each audit.
| 1 |
| LO |
| NSP |
| NSP |
| 0015AG |
| Change Management Plan IAW Paragraph 5.15.15 |
Due sixty (60) days after contract award and updated quarterly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0015AH |
| Delivery Package, IAW Paragraph 5.15.15.2 |
Due sixty (60) days after contract award and updated quarterly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0015AI |
| Change Request Decision Log, IAW Paragraph 5.15.15.3 |
Due sixty (60) days after contract award and updated quarterly thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 0016 |
| SECURITY AND PRIVACY REQUIREMENTS IAW PARAGRAPH 6.2 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 6.2 and all its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 1 |
| LO |
| NSP |
| NSP |
| 0016AA |
| Contractor Staff Roster IAW Paragraph 6.2.2 |
Due three (3) days after contract award and updated after any change throughout the PoP.
| 1 |
| LO |
| $ |
| $ |
| Total Base Period |
| $ |
Option Period One (12 Months) This 12-month option period may be exercised in accordance with FAR 52.217-9, Option to Extend the Term of the Contract. Work shall not commence until, and unless, a formal modification is issued by the Contracting Officer. If exercised, this option shall commence immediately after expiration of the Base Period.
| 1001 |
| PROGRAM MANAGEMENT AND PLANNING IN ACCORDANCE WITH (IAW) PWS PARAGRAPH 5.1 AND ALL OF ITS SUBPARAGRAPHS. |
This Firm Fixed Price (FFP) CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS section 5.1 and all of its subparagraphs.
Electronic submission to: Veterans Affairs (VA) Program Manager (PM), Contracting Officer Representative (COR), and Contracting Officer (CO).
Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 1001AA |
| Weekly VA ELMS Status Call Meeting Materials IAW Paragraph 5.1.1 |
Due three (3) business days prior to the meeting and every seven (7) days thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 1001AB |
| Weekly VA ELMS Status Call Meeting Minutes and Action Items IAW Paragraph 5.1.1 |
Due two (2) business days after each meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 100AC |
| Bi-Weekly Pilot Community of Practice Call Meeting Materials IAW Paragraph 5.1.1 |
Due three (3) business days prior to the meeting
| 1 |
| LO |
| NSP |
| NSP |
| 1001AD |
| Bi-Weekly Pilot Community of Practice Meeting Minutes and Action Items IAW Paragraph 5.1.1 |
Due two (2) business days after each meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 1002 |
| PROJECT MANAGEMENT PLANNING IAW PWS Paragraph 5.2 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.2 and all of its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 1002AA |
| Pilot Site Implementation Kick-Off Meeting Agenda and Materials (PowerPoint or Similar Presentation) IAW Paragraph 5.2.3 |
Due five (5) days prior to the meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 1002AB |
| Pilot Site Implementation Kick-Off Meeting Minutes IAW Paragraph 5.2.3 |
Due two (2) days after the Kick-off Meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 1002AC |
| Pilot Site Implementation Strategy IAW Paragraph 5.2.4 |
Due five (5) days prior to the Kick-off meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 1002AD |
| Pilot Site Implementation Schedule IAW Paragraph 5.2.4 |
Due two (2) days after the Kick-off Meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 1003 |
| SYSTEM DESIGN AND IMPLEMENTATION IAW PARAGRAPH 5.4 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.4 and all its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 1003AA |
| 5.4.1.3 Data Rights and Ownership IAW Paragraph 5.4.1.3 |
Code and associated artifacts for any product developed exclusively for VA.
Due sixty (60) days of Government acceptance.
| 1 |
| LO |
| NSP |
| NSP |
| 1003AB |
| Data Migration Plan for Live Pilot Testing IAW Paragraph 5.4.2.1 |
Draft due sixty (60) days after Option Period One (1) award. Final due thirty (30) days after receiving Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 1003AC |
| Lessons Learned IAW Paragraph 5.4.2.1 |
Due sixty (60) days after data migration complete. Then due on an as needed basis throughout contract lifecycle.
| 1 |
| LO |
| NSP |
| NSP |
| 1003AD |
| Fit Gap Analysis Report IAW Paragraph 5.4.2.1 |
Due thirty (30) days after Option Period One (1) awarded.
| 1 |
| LO |
| NSP |
| NSP |
| 1003AE |
| Data Migration Plan IAW Paragraph 5.4.2.1 |
Due sixty (60) days after Option Period One (1) awarded. Final due thirty (30) days after receipt of Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 1003AF |
| User Acceptance Test (UAT) Plan for SMEs IAW Paragraph 5.4.3 |
Draft due thirty (30) days before scheduled UAT. Final due ten (10) days after receiving Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 1003AG |
| UAT Scenarios/Scripts for SMEs IAW Paragraph 5.4.3 |
Draft due thirty (30) days before scheduled UAT. Final due ten (10) days after receiving Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 1003AH |
| UAT Test Summary Reports IAW Paragraph 5.4.3 |
Due one (1) week after completion of UAT.
| 1 |
| LO |
| NSP |
| NSP |
| 1003AI |
| Pilot Site Training Plan IAW Paragraph 5.4.5.1 |
Draft due thirty (30) days after Option Period one (1) award. Final due ten (10) days after receiving Government comments.
| 1 |
| LO |
| NSP |
| NSP |
| 1003AJ |
| Pilot Site Satisfaction Survey IAW Paragraph 5.4.5.1 |
Due thirty (30) days after each training is conducted.
| 1 |
| LO |
| NSP |
| NSP |
| 1003AK |
| Quarterly Training Plan IAW Paragraph 5.4.5.1 |
Due ninety (90) days after option period one (1) exercised then updated quarterly.
| 1 |
| LO |
| NSP |
| NSP |
| 1004 |
| SYSTEM HOSTING IAW PARAGRAPH 5.6 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.6 and all of its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 1004AA |
| Five Enterprise-Wide instances (Customer Testing, Sandbox, Train, Pre-Production & Production) IAW Paragraph 5.6 |
Due thirty (30) days after option period one (1) award.
| 1 |
| LO |
| NSP |
| NSP |
| 1004AB |
| Weekly Hosting Report IAW Paragraph 5.6 |
Due seven (7) days after option period one (1) award.
| 1 |
| LO |
| NSP |
| NSP |
| 1004AC |
| Monthly Hosting Summary and Operations Metrics Report IAW Paragraph 5.6 |
Due thirty (30) days after option period one and updated every 2nd Tuesday of every month thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 1004AD |
| System Capacity Strategy IAW Paragraph 5.6 |
Draft due sixty (60) days after option period one. Final due ten (10) days after Government comments.
| 1 |
| LOI |
| NSP |
| NSP |
| 1005 |
| SYSTEM LICENSING IAW PARAGRAPH 5.7 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.7 and all its subparagraphs.
Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 1 |
| LO |
| NSP |
| NSP |
| 1005AA |
| Up to 20,000 Full Learning Management Licenses and Maintenance IAW Paragraph 5.7 |
This CLIN may be exercised any time and from time to time during this Option Period and up to the maximum cumulative value of QTY 20,000.
Delivery due thirty (30) days after date each instance this CLIN is exercised.
| 20,000 |
| EA |
| $ |
| $ |
| 1005AB |
| Up to 10,000 Limited Learning Management Licenses and Maintenance IAW Paragraph 5.7 |
This CLIN may be exercised any time and from time to time during this Option Period and up to the maximum cumulative value of QTY 10,000.
Delivery due thirty (30) days after date each instance this CLIN is exercised.
| 10,000 |
| EA |
| $ |
| $ |
| 1005AC |
| Up to 30,000 Individual or Enterprise Virtual Classroom Licenses and Maintenance IAW Paragraph 5.7.1 |
Due thirty (30) days after Option Period One (1) award.
| 30,000 |
| EA |
| $ |
| $ |
| 1006 |
| SYSTEM INTEGRATION IAW PARAGRAPH 5.10 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.10 Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 1006AA |
| Memorandum of Understanding and Interconnection Security Agreements IAW PARAGRAPH 5.10.1.1 |
Draft due thirty (30) days prior to integration effective date. Final due thirty (30) days after Government’s comments.
| 1 |
| LO |
| NSP |
| NSP |
| 1006AB |
| Interface Control Documents IAW Paragraph 5.10.1.1 |
Draft due thirty (30) days prior to integration effective date. Final due thirty (30) days after Government’s comments
| 1 |
| LO |
| NSP |
| NSP |
| 1006AC |
| Integration Requirements Specification Document IAW Paragraph 5.10.1.1 |
Draft due thirty (30) days prior to integration effective date. Final due thirty (30) days after Government’s comments.
| 1 |
| LO |
| NSP |
| NSP |
| 1007 |
| SECURITY AND PRIVACY REQUIREMENTS IAW PARAGRAPH 6.2 |
| 12 |
| MO |
| $ |
| $ |
| 1007AA |
| Contractor Staff Roster IAW Paragraph 6.2.2 |
Due three (3) days after contract award and updated after any change throughout Option Period One (1).
| 1 |
| LO |
| NSP |
| NSP |
| Total Option Period One |
| $ |
Option Period Two (12 Months) This 12-month option period may be exercised in accordance with FAR 52.217-9, Option to Extend the Term of the Contract. Work shall not commence until, and unless, a formal modification is issued by the Contracting Officer. If exercised, this option shall commence immediately after expiration of Option Period One.
| 2001 |
| PROGRAM MANAGEMENT AND PLANNING IAW PARAGRAPH 5.1 |
This FFP CLIN includes all tasks, labor, supplies, program management, and travel required for the successful completion of the services detailed in PWS Section 5.1 Electronic Submission: VA PM, COR, and CO Inspection: Destination Acceptance: Destination
| 12 |
| MO |
| $ |
| $ |
| 2001AA |
| Weekly VA ELMS Status Call Meeting Materials IAW Paragraph 5.1.1 |
Due three (3) business days prior to the meeting, then every seven (7) days thereafter.
| 1 |
| LO |
| NSP |
| NSP |
| 2001AB |
| Weekly VA ELMS Status Call Meeting Minutes and Action Items IAW Paragraph 5.1.1. |
Due two (2) business days after each meeting.
| 1 |
| LO |
| NSP |
| NSP |
| 2001AC |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .