The document is a Notice of Intent to Award from the Oregon Department of Transportation (ODOT) for the House Bill 2017, Section 75 Study. ECONORTHWEST has been selected as the top ranked firm for negotiations of a contract to provide Personal Services as specified in the RFP. The notice outlines the schedule for completing the Statement of Work, submitting the Breakdown of Costs, negotiating, and securing approvals. The notice also provides instructions for submitting a written selection protest by competing proposers who were adversely affected or aggrieved by the selection of a higher ranked proposer.
The contract is for the House Bill 2017, Section 75 Study, which aims to determine if alternative powered vehicles are paying a proportionate share in transportation costs related to fuel tax and emissions. The study will cover the jurisdictions of Marion County and the city of Salem, Oregon. The notice does not provide specific pricing terms, set asides, incumbent information, or funding details.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OREGON DEPARTMENT OF TRANSPORTATION
Notice of Intent to Award
DATE: May 7, 2023
TO: All Proposers of RFP REQ 73000-0003398 (PCMS Number 35594) for House Bill 2017, Section 75 Study.
SUBJECT: Intent To Award RFP “House Bill 2017, Section 75 Study” Contract
ECONORTHWEST is the top ranked firm selected for negotiations of a contract to provide Personal
Services as specified in the above referenced RFP. The scores and rankings of all
Proposers are shown in the score matrix accompanying this notice.
The award submittal requirements stated in the RFP are summarized on Attachment 1 of this notice.
Daniel Porter will be the ODOT Project Manager (PM) for this Project. ODOT’s PM will initiate contact with Consultant and will be the primary contact for negotiation of the statement of work (SOW), schedule of performance and costs under the contract. Following discussion and agreement on the SOW, a Breakdown of Costs (BOC) must be completed (using the BOC, BOC-CPFF or BOC-NBR as applicable) and submitted to ODOT’s PM. A BOC must demonstrate subcontractor utilization to meet the Disadvantaged Business Enterprise (DBE) goal set forth in the RFP. To set expectations for the contracting phase, listed below is a schedule for completing the SOW, preparing a BOC, completing negotiations, and securing approvals for both the Consultant and ODOT to follow:
Activity Responsible Party Business Days
N eg ot ia tio ns
Establish work session to discuss the SOW with
Consultant
ODOT PM Within 5-10 days of this notice (days depend on size and complexity of the project)
Respond to work session with comments/edits to SOW
Consultant Within 5 days of work session
Respond to SOW comments/edits
ODOT PM Within 3 days of receipt of Consultant comments/edits
Submission of BOC / Billing Rates
Consultant Within 5-10 days of final ODOT scope (days depend on size and complexity of the project)
Activity Responsible Party Business Days Respond to BOC, billing rates, negotiate, and
ODOT PM
Within 5-10 days of Consultant submission of the BOC (days depend on the size and complexity of the project)
Signature routing and execution OPO, Consultant, and ODOT Expenditure
Authority (if required)
Within 6-8 days from initial routing
Issue Notice to Proceed (NTP) ODOT PM 1 day after execution
Negotiations are anticipated to be completed (ready to submit to for legal sufficiency) within the schedule set forth in this notice.
If the schedule for negotiations cannot be met and the Consultant and ODOT are negotiating in good faith, additional time may be mutually agreed upon.
If agreement on costs, tasks, or other WOC requirements cannot be reached within this time frame, ODOT may terminate the negotiations and begin negotiations with the next highest ranked firm as provided in the solicitation and governing Oregon Administrative Rules (OARs).
Note that no work is authorized until the contract is executed and Consultant has received a written NTP from the ODOT PM.
Because this notice is being emailed, the date of this notice will start the protest period for competing proposers to submit a written selection protest (Section 5.2 of the RFP). Any proposer who claims to have been adversely affected or aggrieved by the selection of a higher ranked proposer must deliver a written selection protest to my attention and received at the email address below no later than 5:00 p.m. on Sunday, May 13. ODOT shall not consider a selection protest submitted after the deadline established herein. To be adversely affected or aggrieved, a protestor must demonstrate that the protester was ranked higher than other selected proposers and that higher ranked proposers are ineligible for selection.
ODOT would like to thank each Proposer for your time and efforts in preparing a response to this solicitation.
Sincerely, Austene Schneider, OPBC, OPMA
Contract Coordinator | ODOT Procurement Office, MS#2-2
355 Capitol Street NE, Salem OR 97302-1166 | 503-731-3254 Work
Austene.L.Schneider@odot.oregon.gov mailto:Austene.L.Schneider@odot.oregon.gov
Attachment 1 – Award Submittal Requirements
Please email to me, the Contract Coordinator, the following items if marked as “REQUIRED” in the RFP (see detailed requirements and due date for each item in Section XX of the RFP).
• COI Disclosure
• Responsibility Inquiry form
• Business Registry Number
• Quality Plan
• Committed DBE Breakdown & Cert. Form(s)
• W-9 Form
Direct Deposit via Automated Clearing House (ACH). For Consultants that receive ongoing monthly payments from Agency on one or more contracts or work orders, Agency prefers making Consultant payments via ACH direct deposit. While not required, if Consultant has not previously authorized ACH direct deposit and would prefer ACH to expedite transfer of payments after invoices are approved, Consultant must complete a Vendor ACH Authorization form and submit to Agency per the instructions on the form. To expedite Consultant’s payments to its subcontractors, if applicable, Consultant should make reasonable efforts to offer ACH direct deposit payments.
https://www.irs.gov/pub/irs-pdf/fw9.pdf https://www.oregon.gov/ODOT/Forms/2ODOT/7310781.pdf
| OREGON DEPARTMENT OF TRANSPORTATION |
| Committed DBE Breakdown & Cert. Form(s) |
| W-9 Form |
File details come from the government source that posted it. Updated .