Sol_33330220RF0010005.pdf

PDF 824 KB Posted

Attached to
Revitalize Hirshhorn Museum and Sculpture Garden design service
Solicitation number
33330220RF0010005
Issued by

About this file

This pre-solicitation notice announces a forthcoming solicitation for architectural and engineering design services to revitalize the Hirshhorn Museum and Sculpture Garden in Washington, D.C. The solicitation will be issued on or around November 5th. The scope of work includes planning, programming, concept design, schematic design, design development, construction documents, and construction phase services to completely rehabilitate the museum's interior and components of the exterior. The project encompasses art handling and exhibit spaces, offices, laboratories, auditoriums, historic preservation, building systems replacement, vertical transportation, hazard abatement, and potential expansion including underground areas. Services are also required to achieve LEED and SITES certification. The contract will be a firm-fixed price Architect-Engineer contract awarded in accordance with the Brooks Act and FAR Subpart 36.6. The NAICS code is 541310 and there is no size standard. The solicitation and resultant contract will be open to all qualified businesses.

View the file

Other files

File Type Posted
33330220RF0010005 amsndment 1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

SMITHSONIAN INSTITUTION

P.O. BOX 37012

MRC 1200

Washington DC 20013-7012

OCON

Willard Powell 202-633-7286

1921101 x 11/15/2019

33330220RF0010005

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

This announcement is for the selection and award of an Architect-Engineer

Multidiscipline Contract that would provide planning and design support for the revitalization of the Smithsonian Institution's Hirshhorn Museum and Sculpture

Garden (HMSG), the Smithsonian Institution's museum of modern and contemporary art itself housed in an outstanding example of modernist architectural design on the

National Mall. The current size of the HMSG is approximately 172,240 gross square feet (16,001 sq. meters). This project is for the Revitalization of the Museum

Building and Plaza

Objective: To provide planning and design services for HMSG for a complete interior rehabilitation, for components of an exterior rehabilitation, and for museum expansion. The project includes art handling and exhibit spaces, office and conservation laboratory spaces, auditorium and education space design, historic preservation, replacement of the majority of building systems, new vertical transportation, hazmat abatement, blast and chemical, biological and radiological

(CBR) mitigation and potential expansion, including underground areas. This scope of work includes the development of pre-project planning and programming documents, studies, concept design, schematic design, design development, construction documents, and A/E Construction Phase Services as well as services to achieve USGBC

Continued ...

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

calendar days and complete it within ________________ ________________ calendar days after receiving

12/19/2019

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

PAGES

33330220RF0010005 -11/15/2019 -Page 1 of 80

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

PAGE OF

OCON

P.O. BOX 37012

MRC 1200

Washington DC 20013-7012

OCON

Thomas Dempsey

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

2 80

33330220RF0010005 -11/15/2019 -Page 2 of 80

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

33330220RF0010005

- LEED and/or SITES certification.

Period of Performance: 03/31/2020 to 12/31/2027

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

33330220RF0010005 -11/15/2019 -Page 3 of 80

Solicitation Number: 33330220RF0010005

Date: November 15, 2019

Project # 1921101

B - Supplies or Services/Prices

This solicitation is for Architectural/Engineering Services

This is not a request for fee proposal

This contract procurement is in accordance with the Brooks Architect-Engineer (AE) Act as implemented by the Federal Acquisition Regulation (FAR) Subpart 36.6. The objective is to provide planning and design services for the Smithsonian Institution’s Hirshhorn Museum and

Sculpture Garden (HMSG). The North American Industry Classification Code (NAICS) for this procurement is 541310 (Architectural Services) and the size standard under this code is

$7,500,000 (maximum average annual receipts to qualify as a Small Business per 13 CFR §

121.104 a). This announcement is open to all qualified businesses regardless of size. The contract awarded will be firm-fixed-price.

C - Description/Specifications

2. PROJECT INFORMATION:

This announcement is for the selection and award of an Architect-Engineer Multidiscipline

Contract that would provide planning and design support for the revitalization of the Smithsonian

Institution’s Hirshhorn Museum and Sculpture Garden (HMSG), the Smithsonian Institution’s museum of modern and contemporary art itself housed in an outstanding example of modernist architectural design on the National Mall. The current size of the HMSG is approximately

172,240 gross square feet (16,001 sq. meters). This project is for the Revitalization of the

Museum Building and Plaza

Objective: To provide planning and design services for HMSG for a complete interior rehabilitation, for components of an exterior rehabilitation, and for museum expansion. The project includes art handling and exhibit spaces, office and conservation laboratory spaces, auditorium and education space design, historic preservation, replacement of the majority of building systems, new vertical transportation, hazmat abatement, blast and chemical, biological and radiological (CBR) mitigation and potential expansion, including underground areas. This scope of work includes the development of pre-project planning and programming documents, studies, concept design, schematic design, design development, construction documents, and A/E Construction Phase Services as well as services to achieve USGBC -

LEED and/or SITES certification.

Commented [TA1]: NEED # and issue date

Architectural Engineering Services HMSG Revitalize Building and Plaza

A - Solicitation/Contract Form

M - Evaluation Factors for Award

L - Instructions,Conditions, and Notices to Bidders

K - Representations, Certifications, and Other Statements of Bidders

J - List of Documents, Exhibits and Other Attachments

I - Contract Clauses

H - Special Contract Requirements

G - Contract Administration Data

F - Deliveries or Performance

E - Inspection and Acceptance

D - Packaging and Marking

C - Description/Specifications

B - Supplies or Services/Prices

A - Solicitation/Contract Form

33330220RF0010005 -11/15/2019 -Page 4 of 80

Background:

The Hirshhorn Museum and Sculpture Garden (HMSG), designed by architect Gordon

Bunshaft, FAIA, of Skidmore, Owings, and Merrill, opened to the public in 1974. The museum is located at the northwest corner of 7th Street and Independence Avenue, SW, and the Sculpture Garden is north of the museum across Jefferson Drive. The building is a cylindrical volume 231 feet in diameter raised 14 feet above a paved plaza on four concrete piers. The building is clad in crushed pink granite aggregate precast concrete panels. Beneath the center of the drum is a courtyard with a large, shallow, bronze fountain. The minimally articulated solid outer shell contrasts with the walls of the inner courtyard, composed of equal, glazed cells that light the interior galleries. The museum building has four above-grade stories and a basement, extending below most of the plaza that surrounds the building. The plaza connects to the Sculpture Garden via an underground passage below Jefferson Drive that is currently enclosed and used for educational programs.

The Hirshhorn Museum and Sculpture Garden is a Contributing Building of the National Mall

Historic District and has been determined to be Individually Eligible for listing on the

National Register of Historic Places.

Major alterations to the building include revisions to the gift shop in 1986 and 2010, an expansion to the loading dock in 2008, conversion of the underground passage beneath

Jefferson Drive to education space in 2010, and a new Conservation Lab added to the fourth level in 2019. Other, smaller alterations include black box spaces in the basement that allow for exhibitions of video and other new media art and a lobby café designed by Hiroshi

Sugimoto. Landscape Architect Lester Collins designed a rehabilitation of the Sculpture

Garden in 1981 and the Plaza underwent design revisions in 1993 by Urban and Associates.

Current projects not a part of this contract include replacement of the exterior precast panels and roof and modernization of the existing vertical transportation systems including the elevators and replacement of loading dock levelers. The revitalization of the Sculpture

Garden, already underway, is not a part of this contract. That project will be complete before this project goes into construction and will provide continuity of museum programing during the rehabilitation and expansion of the main museum building and plaza. Future connectivity and a possible new main entrance to the museum from the sculpture garden will explored during this project’s planning phase and may be part of the design scope for this project.

Design Considerations: The revitalization design should be constrained and respectful of the historic Bunshaft building and site as well as engaging and responsive to the National Mall and broader urban context. This undertaking will re-envision the building to support diverse modern and contemporary art programming for the next 50 years. This effort shall consider expansion, new or improved public access, the addition of amenities and event spaces, prioritization of program for the campus, structural and envelope improvements, updated building systems that are robust, resilient, and versatile, and improvements to the plaza to include replacement of waterproofing, repair or replacement of the plaza walls, and repair of the fountain. The Smithsonian seeks a talented design team with the proven ability to integrate creative design and systems engineering solutions within a constrained modern historic context.

Services: The A/E shall provide multidisciplinary architectural and engineering services for the preparation of pre-project planning and programming documents and studies, concept design, schematic design, design development, and construction documents for the complete revitalization of the Hirshhorn Museum Building, A/E Construction Phase Services and services to achieve LEED and/or SITES certification. The multidisciplinary team shall include, at a minimum, the following disciplines and expertise:

• Planning, including for collections moves and staff relocations

• Architecture, including Historic Preservation

33330220RF0010005 -11/15/2019 -Page 5 of 80

• Landscape Architecture

• Mechanical, Electrical, Plumbing and Fire Protection/Life Safety Engineering

• Security

• Structural Engineering

• Civil Engineering

• Geotechnical Engineering

• Materials Handling

• Hazardous materials abatement

• Lighting Design

• Vertical Transportation Design

• Envelope Design

• Accessibility

• Sustainability

• Acoustics

• Audio-Visual and Theater Design

• Graphic Design

• Information Technology Design

• Food Service

• Retail Design

• Exhibit Design

• Moisture Protection and Water-proofing Design

• Cost Estimating

• Blast and CBR resistant design and

• all other design and engineering disciplines as may be required for full renovation of structures of this age and significance.

The above services and expertise may be provided by the prime or by separate consultants. In addition, the A/E shall be required to prepare presentations and project submissions of the proposed designs for review by external agencies and their staff, including the Commission of

Fine Arts (CFA), the National Capital Planning Commission (NCPC), and the D.C. State

Historic Preservation Office. The A/E will be expected to attend and participate in video-conferencing and on-site meetings in Washington, D.C., often at short notice, in connection with the services described herein.

D - Packaging and Marking

All references to this solicitation shall reference the following:

Architectural Engineering Services HMSG Revitalize Building and Plaza

Solicitation Number: 33330220RF0010005

Project # 1921101

E - Inspection and Acceptance

F - Deliveries or Performance

G - Contract Administration Data

52.202-S0059 Contract Management

Notwithstanding the Contractor's responsibility for total management during the performance of this contract, the administration of the contract will require maximum coordination between the Smithsonian and the Contractor. The following individuals will be the Smithsonian points of contact during the performance of the contract.

33330220RF0010005 -11/15/2019 -Page 6 of 80

52.202-S0060 Contracting Officer

All contract administration will be effected by the Contracting Officer. Communications pertaining to contractual administrative matters will be addressed to the Contracting Officer. No changes in or deviation from the scope of work shall be effected without a written modification to the contract executed by the

Contracting Officer authorizing such changes.

52.202-S0061 Contracting Officer's Technical Representative (COTR) (Apr 1988)

(a) The Contracting Officer's Technical Representative (COTR) to be determined at time of award, or her authorized representative shall act for and on behalf of the Contracting Officer in the administration of any resultant contract with respect to:

1. Resolution of issues that may arise between the Contractor and the Smithsonian Institution in connection with such matters as acceptability of workmanship and other technical requirements;

2. Evaluation on an overall basis of the acceptability of workmanship and Contractor's compliance with technical requirements; and

3. The approval and acceptance of work performed under this contract.

(b) This delegation does not authorize the modification of any of the contract's provisions, terms or conditions. All authorities not herein delegated are reserved to the Contracting Officer.

(c) The Contractor shall make available such records, reports and facilities as may be required to carry out this assignment.

52.202-S0062 Authorities

The Contractor is advised that only the Contracting Officer can change or modify the terms of this contract or take any other action which obligates the Smithsonian and then such action must be set forth in a formal modification to the Contract. The authority of the COTR is strictly limited to the specific duties set forth in her letter of appointment, a copy of which will be furnished the Contractor. Contractors who rely on direction from persons other than the Contracting Officer (or a COTR acting within the strict limits of his/her responsibilities as set forth in his/her letter of appointment) do so at their own risk and expense, as such actions do not bind the Smithsonian contractually. All questions concerning the authority of a

Smithsonian employee to direct the Contractor contractually should be referred to the Contracting Officer.

52.215-S0002 Authorized Negotiators (Apr 1984)

The offeror or quoter represents that the following persons are authorized to negotiate on its behalf with the

Government in connection with this request for proposals or quotations: [list names, titles, and telephone numbers of the authorized negotiators].

52.215-S0063 Key Personnel

(a) The Contractor shall include the key personnel to be assigned under this contract those persons listed below:

33330220RF0010005 -11/15/2019 -Page 7 of 80

NAME LABOR CATEGORY

Offerors shall also provide this information in their technical proposal.

(b) The persons named above are considered key personnel. The Contractor shall give at least 14 calendar days advance notice if any of these persons are to be removed or diverted from this contract, and shall supply written justification as part of this notice, and shall name the proposed substitute or replacement; but the Contractor will not remove or divert such persons unless authorized by written consent of the

Contracting Officer.

(c) General Approval. All Contractor personnel assigned to this contract are subject to Smithsonian review in accordance with the defined labor categories herein. Contractor personnel found unacceptable by the

Smithsonian at any time shall be removed from performing under this contract within 14 calendar days after notification. Such notification shall be delivered in writing by the Contracting Officer to the

Contractor.

H - Special Contract Requirements

52.202-S0010 Use of Smithsonian Name (Jun 2000)

It is recognized and acknowledged that Contractor shall have no right to use the name "Smithsonian" or

"Smithsonian Institution", or the name of any Smithsonian Museum or part thereof, including the Facilities, in connection with any of its own advertising, marketing or promotion. However, any marketing or promotional programs concerning the Smithsonian or the Project shall be submitted to the Smithsonian for review and approval prior to any implementation thereof. The Smithsonian may withhold any approval required hereunder as it wishes.

The Prime Contractor shall be responsible for compliance by any subcontractor or supplier or lower tier subcontractor or lower tier supplier with this clause. After award of the contract and upon request of the

Contracting Officer, the Prime Contractor shall deliver a written statement acknowledging that this clause has been included in contracts with all subcontractors and suppliers.

52.203-S0004 Advertising of Award Smithsonian Institution

The Contractor shall not refer to the Smithsonian or to any of its museums, organizations, or facilities in any manner or through any medium, whether written, oral or visual, for any purpose whatsoever, including advertising, marketing, and promotion.

52.215-S0009 Information, Services and Rights of the Smithsonian (Apr 1988)

(a) The S.I., through the C.O. and COTR, will provide administration of the contract as hereinafter described.

(b) The S.I. or its authorized representatives shall at all times have access to the Work whenever it is in preparation or progress. The Contractor shall provide safe facilities for such access.

33330220RF0010005 -11/15/2019 -Page 8 of 80

(c) The S.I. or its authorized representatives shall not be responsible for or have control or charge of the construction means, methods, techniques, sequences, or procedures, or for safety precautions and program in connection with the Work, and will not be responsible for the Contractor's failure to carry out the Work in accordance with the Contract Documents.

(d) The COTR shall have authority to reject Work when in his opinion, the Work does not conform to the

Contract Documents.

(e) Whenever in the COTR's reasonable opinion it is considered necessary or advisable for the implementation of the intent of the Contract Documents, the COTR will have authority to require special inspection or testing of the Work in accordance with the provisions of the Contract Documents whether or not such Work be then fabricated, installed or completed.

(f) The COTR shall have the authority and discretion to call, schedule, and conduct job meetings to be attended by the Contractor, representatives of his Subcontractors, and the Architect to discuss such matters as procedures, progress, problems, payments and scheduling.

(g) The COTR will establish procedures to be followed for processing all Shop Drawings, catalogs, and other project reports and other documentation, test reports, and maintenance manuals.

(h) The COTR will review all requests for changes and shall implement the processing of Change Orders, including applications for extension of the Contract Time.

(1) The COTR will review and process all Progress Payments including the Final Payment.

(2) The Smithsonian Institution or its authorized representatives shall not be responsible or liable to the

Contractor for the acts, errors or omissions of the Contractor, any separate Subcontractor, any separate contractor or any contractor's or subcontractor's agents or employees, or any other persons performing any of the Work.

(k) Unless otherwise provided in the Contract Documents, the Contractor will be furnished, free of charge, ten copies of full size Drawings and Specifications reasonably necessary for the execution of the Work.

(l) The foregoing rights are in addition to other rights of the S.I. enumerated herein and those provided by law.

52.223-S0070 Dissemination of Information

There shall be no dissemination or publication of information, except between the Contractor and any subcontractors, of information developed under this contract or any task orders awarded under the terms of this contract or contained in reports to be furnished pursuant to this contract without the prior written approval of the Contracting Officer.

I - Contract Clauses

52.203-3 Gratuities. (APR 1984)

52.203-5 Covenant Against Contingent Fees. (MAY 2014)

52.203-7 Anti-Kickback Procedures. (MAY 2014)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (MAY

2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (MAY 2014)

52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (OCT 2010)

33330220RF0010005 -11/15/2019 -Page 9 of 80

52.203-13 Contractor Code of Business Ethics and Conduct. (OCT 2015)

52.203-14 Display of Hotline Poster(s). (OCT 2015)

(a) Definition.

United States, as used in this clause, means the 50 States, the District of Columbia, and outlying areas.

(b) Display of fraud hotline poster(s). Except as provided in paragraph (c)-

(1) During contract performance in the United States, the Contractor shall prominently display in common work areas within business segments performing work under this contract and at contract work sites-

(i) Any agency fraud hotline poster or Department of Homeland Security (DHS) fraud hotline poster identified in paragraph (b)(3) of this clause; and

(ii) Any DHS fraud hotline poster subsequently identified by the Contracting

Officer.

(2) Additionally, if the Contractor maintains a company website as a method of providing information to employees, the Contractor shall display an electronic version of the poster(s) at the website.

(3) Any required posters may be obtained as follows:

Poster(s) Obtain from

[Contracting Officer shall insert-(i) Appropriate agency name(s) and/or title of applicable Department of Homeland Security fraud hotline poster); and (ii) The website(s) or other contact information for obtaining the poster(s) to be provided at award.]

(c) If the Contractor has implemented a business ethics and conduct awareness program, including a reporting mechanism, such as a hotline poster, then the Contractor need not display any agency fraud hotline posters as required in paragraph (b) of this clause, other than any required DHS posters.

(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in all subcontracts that exceed $5.5 million, except when the subcontract-

(1) Is for the acquisition of a commercial item; or

(2) Is performed entirely outside the United States.

(End of clause)

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper. (MAY 2011)

52.204-7 System for Award Management. (OCT 2018)

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (OCT 2018)

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment. (OCT 2015)

52.215-2 Audit and Records - Negotiation. (OCT 2010)

33330220RF0010005 -11/15/2019 -Page 10 of 80

52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997)

52.215-10 Price Reduction for Defective Certified Cost or Pricing Data. (AUG 2011)

52.215-11 Price Reduction for Defective Certified Cost or Pricing Data - Modifications. (AUG 2011)

52.215-12 Subcontractor Certified Cost or Pricing Data. (OCT 2010)

52.215-13 Subcontractor Certified Cost or Pricing Data - Modifications. (OCT 2010)

52.216-7 Allowable Cost and Payment. (AUG 2018)

(a) Invoicing. (1) The Government will make payments to the Contractor when requested as work progresses, but (except for small business concerns) not more often than once every 2 weeks, in amounts determined to be allowable by the Contracting Officer in accordance with Federal

Acquisition Regulation (FAR) subpart 31.2 in effect on the date of this contract and the terms of this contract. The Contractor may submit to an authorized representative of the Contracting

Officer, in such form and reasonable detail as the representative may require, an invoice or voucher supported by a statement of the claimed allowable cost for performing this contract.

(2) Contract financing payments are not subject to the interest penalty provisions of the

Prompt Payment Act. Interim payments made prior to the final payment under the contract are contract financing payments, except interim payments if this contract contains Alternate I to the clause at 52.232-25.

(3) The designated payment office will make interim payments for contract financing on the [Contracting Officer insert day as prescribed by agency head; if not prescribed, insert

"30th"] day after the designated billing office receives a proper payment request.

In the event that the Government requires an audit or other review of a specific payment request to ensure compliance with the terms and conditions of the contract, the designated payment office is not compelled to make payment by the specified due date.

(b) Reimbursing costs. (1) For the purpose of reimbursing allowable costs (except as provided in paragraph (b)(2) of the clause, with respect to pension, deferred profit sharing, and employee stock ownership plan contributions), the term costs includes only-

(i) Those recorded costs that, at the time of the request for reimbursement, the

Contractor has paid by cash, check, or other form of actual payment for items or services purchased directly for the contract;

(ii) When the Contractor is not delinquent in paying costs of contract performance in the ordinary course of business, costs incurred, but not necessarily paid, for-

(A) Supplies and services purchased directly for the contract and associated financing payments to subcontractors, provided payments determined due will be made-

(1) In accordance with the terms and conditions of a subcontract or invoice; and

(2) Ordinarily within 30 days of the submission of the

Contractor's payment request to the Government;

(B) Materials issued from the Contractor's inventory and placed in the production process for use on the contract;

33330220RF0010005 -11/15/2019 -Page 11 of 80

(C) Direct labor;

(D) Direct travel;

(E) Other direct in-house costs; and

(F) Properly allocable and allowable indirect costs, as shown in the records maintained by the Contractor for purposes of obtaining reimbursement under Government contracts; and

(iii) The amount of financing payments that have been paid by cash, check, or other forms of payment to subcontractors.

(2) Accrued costs of Contractor contributions under employee pension plans shall be excluded until actually paid unless-

(i) The Contractor's practice is to make contributions to the retirement fund quarterly or more frequently; and

(ii) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contribution remaining unpaid shall be excluded from the Contractor's indirect costs for payment purposes).

(3) Notwithstanding the audit and adjustment of invoices or vouchers under paragraph (g) below, allowable indirect costs under this contract shall be obtained by applying indirect cost rates established in accordance with paragraph (d) below.

(4) Any statements in specifications or other documents incorporated in this contract by reference designating performance of services or furnishing of materials at the

Contractor's expense or at no cost to the Government shall be disregarded for purposes of cost-reimbursement under this clause.

(c) Small business concerns. A small business concern may receive more frequent payments than every 2 weeks.

(d) Final indirect cost rates. (1) Final annual indirect cost rates and the appropriate bases shall be established in accordance with subpart 42.7 of the Federal Acquisition Regulation (FAR) in effect for the period covered by the indirect cost rate proposal.

(2)(i) The Contractor shall submit an adequate final indirect cost rate proposal to the

Contracting Officer (or cognizant Federal agency official) and auditor within the 6-month period following the expiration of each of its fiscal years. Reasonable extensions, for exceptional circumstances only, may be requested in writing by the Contractor and granted in writing by the Contracting Officer. The Contractor shall support its proposal with adequate supporting data.

(ii) The proposed rates shall be based on the Contractor's actual cost experience for that period. The appropriate Government representative and the Contractor shall establish the final indirect cost rates as promptly as practical after receipt of the Contractor's proposal.

(iii) An adequate indirect cost rate proposal shall include the following data unless otherwise specified by the cognizant Federal agency official:

(A) Summary of all claimed indirect expense rates, including pool, base, and calculated indirect rate.

33330220RF0010005 -11/15/2019 -Page 12 of 80

(B) General and Administrative expenses (final indirect cost pool).

Schedule of claimed expenses by element of cost as identified in accounting records (Chart of Accounts).

(C) Overhead expenses (final indirect cost pool). Schedule of claimed expenses by element of cost as identified in accounting records (Chart of Accounts) for each final indirect cost pool.

(D) Occupancy expenses (intermediate indirect cost pool). Schedule of claimed expenses by element of cost as identified in accounting records

(Chart of Accounts) and expense reallocation to final indirect cost pools.

(E) Claimed allocation bases, by element of cost, used to distribute indirect costs.

(F) Facilities capital cost of money factors computation.

(G) Reconciliation of books of account (i.e., General Ledger) and claimed direct costs by major cost element.

(H) Schedule of direct costs by contract and subcontract and indirect expense applied at claimed rates, as well as a subsidiary schedule of

Government participation percentages in each of the allocation base amounts.

(I) Schedule of cumulative direct and indirect costs claimed and billed by contract and subcontract.

(J) Subcontract information. Listing of subcontracts awarded to companies for which the contractor is the prime or upper-tier contractor

(include prime and subcontract numbers; subcontract value and award type; amount claimed during the fiscal year; and the subcontractor name, address, and point of contact information).

(K) Summary of each time-and-materials and labor-hour contract information, including labor categories, labor rates, hours, and amounts; direct materials; other direct costs; and, indirect expense applied at claimed rates.

(L) Reconciliation of total payroll per IRS form 941 to total labor costs distribution.

(M) Listing of decisions/agreements/approvals and description of accounting/organizational changes.

(N) Certificate of final indirect costs (see 52.242-4, Certification of

Final Indirect Costs).

(O) Contract closing information for contracts physically completed in this fiscal year (include contract number, period of performance, contract ceiling amounts, contract fee computations, level of effort, and indicate if the contract is ready to close).

(iv) The following supplemental information is not required to determine if a proposal is adequate, but may be required during the audit process:

33330220RF0010005 -11/15/2019 -Page 13 of 80

(A) Comparative analysis of indirect expense pools detailed by account to prior fiscal year and budgetary data.

(B) General organizational information and limitation on allowability of compensation for certain contractor personnel. See 31.205-6(p).

Additional salary reference information is available at https://www.whitehouse.gov/ wp-content/uploads/2017/11/ContractorCompensationCapContractsAward edBeforeJune24.pdf and https://www.whitehouse.gov/wp-content/uploads/2017/11/ContractorCompensationCapContractsAward edafterJune24.pdf.

(C) Identification of prime contracts under which the contractor performs as a subcontractor.

(D) Description of accounting system (excludes contractors required to submit a CAS Disclosure Statement or contractors where the description of the accounting system has not changed from the previous year's submission).

(E) Procedures for identifying and excluding unallowable costs from the costs claimed and billed (excludes contractors where the procedures have not changed from the previous year's submission).

(F) Certified financial statements and other financial data (e.g., trial balance, compilation, review, etc.).

(G) Management letter from outside CPAs concerning any internal control weaknesses.

(H) Actions that have been and/or will be implemented to correct the weaknesses described in the management letter from subparagraph (G) of this section.

(I) List of all internal audit reports issued since the last disclosure of internal audit reports to the Government.

(J) Annual internal audit plan of scheduled audits to be performed in the fiscal year when the final indirect cost rate submission is made.

(K) Federal and State income tax returns.

(L) Securities and Exchange Commission 10-K annual report.

(M) Minutes from board of directors meetings.

(N) Listing of delay claims and termination claims submitted which contain costs relating to the subject fiscal year.

(O) Contract briefings, which generally include a synopsis of all pertinent contract provisions, such as: Contract type, contract amount, product or service(s) to be provided, contract performance period, rate ceilings, advance approval requirements, pre-contract cost allowability limitations, and billing limitations.

(v) The Contractor shall update the billings on all contracts to reflect the final settled rates and update the schedule of cumulative direct and indirect costs

33330220RF0010005 -11/15/2019 -Page 14 of 80 claimed and billed, as required in paragraph (d)(2)(iii)(I) of this section, within

60 days after settlement of final indirect cost rates.

(3) The Contractor and the appropriate Government representative shall execute a written understanding setting forth the final indirect cost rates. The understanding shall specify

(i) the agreed-upon final annual indirect cost rates, (ii) the bases to which the rates apply,

(iii) the periods for which the rates apply, (iv) any specific indirect cost items treated as direct costs in the settlement, and (v) the affected contract and/or subcontract, identifying any with advance agreements or special terms and the applicable rates. The understanding shall not change any monetary ceiling, contract obligation, or specific cost allowance or disallowance provided for in this contract. The understanding is incorporated into this contract upon execution.

(4) Failure by the parties to agree on a final annual indirect cost rate shall be a dispute within the meaning of the Disputes clause.

(5) Within 120 days (or longer period if approved in writing by the Contracting Officer) after settlement of the final annual indirect cost rates for all years of a physically complete contract, the Contractor shall submit a completion invoice or voucher to reflect the settled amounts and rates. The completion invoice or voucher shall include settled subcontract amounts and rates. The prime contractor is responsible for settling subcontractor amounts and rates included in the completion invoice or voucher and providing status of subcontractor audits to the contracting officer upon request.

(6)(i) If the Contractor fails to submit a completion invoice or voucher within the time specified in paragraph (d)(5) of this clause, the Contracting Officer may-

(A) Determine the amounts due to the Contractor under the contract;

and

(B) Record this determination in a unilateral modification to the contract.

(ii) This determination constitutes the final decision of the Contracting Officer in accordance with the Disputes clause.

(e) Billing rates. Until final annual indirect cost rates are established for any period, the

Government shall reimburse the Contractor at billing rates established by the Contracting Officer or by an authorized representative (the cognizant auditor), subject to adjustment when the final rates are established. These billing rates-

(1) Shall be the anticipated final rates; and

(2) May be prospectively or retroactively revised by mutual agreement, at either party's request, to prevent substantial overpayment or underpayment.

(f) Quick-closeout procedures. Quick-closeout procedures are applicable when the conditions in

FAR 42.708(a) are satisfied.

(g) Audit. At any time or times before final payment, the Contracting Officer may have the

Contractor's invoices or vouchers and statements of cost audited. Any payment may be (1) reduced by amounts found by the Contracting Officer not to constitute allowable costs or (2) adjusted for prior overpayments or underpayments.

(h) Final payment. (1) Upon approval of a completion invoice or voucher submitted by the

Contractor in accordance with paragraph (d)(5) of this clause, and upon the Contractor's compliance with all terms of this contract, the Government shall promptly pay any balance of allowable costs and that part of the fee (if any) not previously paid.

33330220RF0010005 -11/15/2019 -Page 15 of 80

(2) The Contractor shall pay to the Government any refunds, rebates, credits, or other amounts (including interest, if any) accruing to or received by the Contractor or any assignee under this contract, to the extent that those amounts are properly allocable to costs for which the Contractor has been reimbursed by the Government. Reasonable expenses incurred by the Contractor for securing refunds, rebates, credits, or other amounts shall be allowable costs if approved by the Contracting Officer. Before final payment under this contract, the Contractor and each assignee whose assignment is in effect at the time of final payment shall execute and deliver-

(i) An assignment to the Government, in form and substance satisfactory to the

Contracting Officer, of refunds, rebates, credits, or other amounts (including interest, if any) properly allocable to costs for which the Contractor has been reimbursed by the Government under this contract; and

(ii) A release discharging the Government, its officers, agents, and employees from all liabilities, obligations, and claims arising out of or under this contract, except-

(A) Specified claims stated in exact amounts, or in estimated amounts when the exact amounts are not known;

(B) Claims (including reasonable incidental expenses) based upon liabilities of the Contractor to third parties arising out of the performance of this contract; provided, that the claims are not known to the Contractor on the date of the execution of the release, and that the

Contractor gives notice of the claims in writing to the Contracting

Officer within 6 years following the release date or notice of final payment date, whichever is earlier; and

(C) Claims for reimbursement of costs, including reasonable incidental expenses, incurred by the Contractor under the patent clauses of this contract, excluding, however, any expenses arising from the

Contractor's indemnification of the Government against patent liability.

(End of clause)

52.216-8 Fixed Fee. (JUN 2011)

(a) The Government shall pay the Contractor for performing this contract the fixed fee specified in the Schedule.

(b) Payment of the fixed fee shall be made as specified in the Schedule; provided that the

Contracting Officer withholds a reserve not to exceed 15 percent of the total fixed fee or $100,000, whichever is less, to protect the Government's interest. The Contracting Officer shall release 75 percent of all fee withholds under this contract after receipt of an adequate certified final indirect cost rate proposal covering the year of physical completion of this contract, provided the

Contractor has satisfied all other contract terms and conditions, including the submission of the final patent and royalty reports, and is not delinquent in submitting final vouchers on prior years' settlements. The Contracting Officer may release up to 90 percent of the fee withholds under this contract based on the Contractor's past performance related to the submission and settlement of final indirect cost rate proposals.

(End of clause)

52.216-21 Requirements. (OCT 1995)

33330220RF0010005 -11/15/2019 -Page 16 of 80

(a) This is a requirements contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies or services specified in the Schedule are estimates only and are not purchased by this contract. Except as this contract may otherwise provide, if the Government's requirements do not result in orders in the quantities described as estimated or maximum in the Schedule, that fact shall not constitute the basis for an equitable price adjustment.

(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. Subject to any limitations in the Order Limitations clause or elsewhere in this contract, the Contractor shall furnish to the Government all supplies or services specified in the

Schedule and called for by orders issued in accordance with the Ordering clause. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.

(c) Except as this contract otherwise provides, the Government shall order from the Contractor all the supplies or services specified in the Schedule that are required to be purchased by the

Government activity or activities specified in the Schedule.

(d) The Government is not required to purchase from the Contractor requirements in excess of any limit on total orders under this contract.

(e) If the Government urgently requires delivery of any quantity of an item before the earliest date that delivery may be specified under this contract, and if the Contractor will not accept an order providing for the accelerated delivery, the Government may acquire the urgently required goods or services from another source.

(f) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor's and Government's rights and obligations with respect to that order to the same extent as if the order were completed during the contract's effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after close of contract to be determined.

(End of clause)

52.219-8 Utilization of Small Business Concerns. (OCT 2018)

(a) Definitions. As used in this contract-

HUBZone small business concern means a small business concern, certified by the Small Business

Administration, that appears on the List of Qualified HUBZone Small Business Concerns maintained by the Small Business Administration.

Small business concern means a small business as defined pursuant to Section 3 of the Small

Business Act and relevant regulations promulgated pursuant thereto.

Small disadvantaged business concern, consistent with 13 CFR 124.1002, means a small business concern under the size standard applicable to the acquisition, that-

(1) Is at least 51 percent unconditionally and directly owned (as defined at 13 CFR

124.105) by-

(i) One or more socially disadvantaged (as defined at 13 CFR 124.103) and economically disadvantaged (as defined at 13 CFR 124.104) individuals who are citizens of the United States; and

(ii) Each individual claiming economic disadvantage has a net worth not exceeding $750,000 after taking into account the applicable exclusions set forth at 13 CFR 124.104(c)(2); and

33330220RF0010005 -11/15/2019 -Page 17 of 80

(2) The management and daily business operations of which are controlled (as defined at

13.CFR 124.106) by individuals, who meet the criteria in paragraphs (1)(i) and (ii) of this definition.

Veteran-owned small business concern means a small business concern-

(1) Not less than 51 percent of which is owned by one or more veterans (as defined at 38

U.S.C. 101(2)) or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more veterans; and

(2) The management and daily business operations of which are controlled by one or more veterans.

Women-owned small business concern means a small business concern-

(1) That is at least 51 percent owned by one or more women, or, in the case of any publicly owned business, at least 51 percent of the stock of which is owned by one or more women; and

(2) Whose management and daily business operations are controlled by one or more women.

(b) It is the policy of the United States that small business concerns, veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns shall have the maximum practicable opportunity to participate in performing contracts let by any

Federal agency, including contracts and subcontracts for subsystems, assemblies, components, and related services for major systems. It is further the policy of the United States that its prime contractors establish procedures to ensure the timely payment of amounts due pursuant to the terms of their subcontracts with small business concerns, veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns.

(c) The Contractor hereby agrees to carry out this policy in the awarding of subcontracts to the fullest extent consistent with efficient contract performance. The Contractor further agrees to cooperate in any studies or surveys as may be conducted by the United States Small Business

Administration or the awarding agency of the United States as may be necessary to determine the extent of the Contractor's compliance with this clause.

(d)(1) The Contractor may accept a subcontractor's written representations of its size and socioeconomic status as a small business, small disadvantaged business, veteran-owned small business, service-disabled veteran-owned small business, or a women-owned small business if the subcontractor represents that the size and socioeconomic status representations with its offer are current, accurate, and complete as of the date of the offer for the subcontract.

(2) The Contractor may accept a subcontractor's representations of its size and socioeconomic status as a small business, small disadvantaged business, veteran-owned small business, service-disabled veteran-owned small business, or a women-owned small business…