This is a bid schedule for the Big Bend Habitat Restoration Project located along the Jordan River in West Jordan, Utah, dated November 23, 2026. The project encompasses comprehensive habitat restoration and infrastructure improvements including general construction activities, demolition and removal of existing features, in-channel work and landscape grading, revegetation across multiple flood and spray zones, installation of an extensive irrigation system, and construction of a pump station facility. The bid schedule contains 94 line items organized into a base bid and four add-alternates, with quantities ranging from individual equipment units to large-scale site work such as 47,552 cubic yards of general excavation and grading, 7,493 cubic yards of topsoil salvage and placement, 41,004 plug plantings, and 2,172 linear feet of irrigation mainline. The base bid encompasses nine major work categories: general construction methods and best management practices; demolitions and removals; in-channel work, landscape grading, and drainage; revegetation for flood zones A and B; irrigation systems for flood zones A and B; pump system components; with additional work available through four add-alternates covering spray zone irrigation and plantings (Zones A/B, C, and D) and miscellaneous landscape, irrigation, and pump system items.

All bid items in the schedule contain zero dollar unit costs and total costs, indicating this is a template document awaiting contractor pricing submissions. The project is structured as a lump-sum contract with a base bid total and separate lump-sum totals for each of the four add-alternates. No specific pricing terms, set-asides, incumbents, funding sources, or contract duration information is provided in this bid schedule document.

View the file

Other files

File Type Posted
2-PROTECTED INFORMATION REQUEST FORM.docx DOCX document
4-WJPS27112301 Big Bend Habitat Restoration.pdf PDF
1-COI Guide for Contractors.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SCHEDULE

PROJECT: Big Bend Habitat Restoration Project - Jordan River, West Jordan, UTVer 1 -Date:November 23, 2026
BID SCHEDULE
BASE BID
Item #DescriptionQuantityUnitUnit CostTotal CostNotes / Assumptions

Alex Heller: Alex Heller:

Include spec reference column. These notes are not included in bid schedule.

General Construction Methods and BMPs
1Bonds and Insurance1LS$ - 0
2Contractor Submittals1LS$ - 0Includes plans, schedules, and equipment lists for Engineer and Owner approval
3Permits1LS$ - 0Includes UDOT ROW permit, UPDES permits, local construction permits
4Mobilization and Demobilization1LS$ - 0Includes construction access, temporary facilities, staging, and repair
5Traffic Control1LS$ - 0
6Construction Stakeout and Survey1LS$ - 0
7Protect-In-Place (PIP)1LS$ - 0Tree, utility, monitoring well protection
8Erosion Control and General BMPs1LS$ - 0
9Care of Water1LS$ - 0
Sub Total:$ - 0
Demolitions and Removals
10Remove and Dispose Groundwater Monitoring Well1EA$ - 0Cut down MW6 and dispose offsite.
11Remove and Dispose Chainlink Fence1,742LF$ - 0Keep in place until split-rail is installed to keep people out of site.
12Remove and Dispose Pipe - 18" HDPE Pipe40LF$ - 0At Jordan River Parkway Trail over south channel inlet.
13Remove and Dispose Asphalt Pavement138SF$ - 0At Jordan River Parkway Trail over south channel inlet
14Remove and Dispose Invasive Species Trees, Stumps, and Roots12EA$ - 0Within Project Limits
15Remove and Reuse Mature Cottonwood4EA$ - 0At meander inlet area
16Salvage Existing Tree and Transplanting10EA$ - 0At confluence area
Sub Total:$ - 0
In-Channel Work, Landscape Grading, and Drainage
17Salvage, Stockpile, and Place Topsoil7,493CY$ - 0Assume average 8" topsoil to be salvaged in areas identified. Includes clearing and grubbing. Placed quantity shown includes 25% bulking factor.
18General Excavation and Grading47,552CY$ - 0Assume excavated material will be mostly gravel/clay/mixed material. Use as fill for landscaped berm.
19Furnish and Install Boulder1,812TON$ - 0Placed in boulder grade controls, stacked boulder wall, habitat boulder, and headwall around 15" HDPE pipes
20Furnish and Install Boulder Grout112CY$ - 0Placed at drop structure A
21Furnish and Install Coarse Alluvium379CY$ - 0Placed at meander channel inlet, between drop structures A and B, low flow crossing, and south inlet channel fish screen.
22Furnish and Install 8oz Filter Fabric445SY$ - 0Placed behind stacked boulder wall
23Furnish and Install Crusher Fines228CY$ - 0Placed at pond trail, and future parking lot connection. Overlook Trail is an Add-Alt
24Furnish and Install UTBC, Grade 1-1/2536CY$ - 0Placed under all trails listed above and for maintenance road. Overlook Trail is an Add-Alt
25Furnish and Install 4oz Filter Fabric1,368SY$ - 0Placed under all trails listed above. Overlook Trail is an Add-Alt
26Furnish and Install Drainage Pipe - 15" HDPE200LF$ - 0Placed under pond trail and maintenance road for site drainage. Pipe backfill materials (UTBC Grades 1 and 3/4) are incidental.
27Furnish and Install Drainage Pipe - 24" HDPE40LF$ - 0Placed at south inlet channel with fish screen structure. Pipe backfill materials (UTBC Grades 1 and 3/4) are incidental.
28Rebuild Boulder Headwall1LS$ - 0Placed with 24" pipe - salvage and reuse existing boulder
29Furnish and Install Asphalt Paving138SF$ - 0
30Furnish and Install Post-and-Wire Fence2,165LF$ - 0
31Furnish and Install Maintenance Access Gate1EA$ - 0
Sub Total:$ - 0
Revegetation (Flood Zones A and B)
32Supply, Broadcast, and Rake Seed Mix13.55AC$ - 0
33Supply and Plant D40 Container Plantings4,732EA$ - 0
34Supply and Plant Riparian Poles0EA$ - 0
35Supply and Plant Large Trees (10 gal)35EA$ - 0
36Supply and Plant Large Trees (4-6" Dia)0EA$ - 0
37Supply and Plant Plug Plantings41,004EA$ - 0
Sub Total:$ - 0
Irrigation System (Flood Zones A and B)
38Irrigation Control System1LS$ - 0Controller, Control Wire, Grounding, Conduit, Power Connection, Antenna
39Irrigation Connection1LS$ - 0Filter, Master Valve, Flow Sensor, Enclosures, Concrete Pads, Etc
40Irrigation Mainline Area A2,172LF$ - 0From Pump House Across River and Upper Limits of Floodplain, Includes Irrigation Main and Control Wire/Conduit
41Irrigation Mainline Area B1,976LF$ - 0Lower Limits of Floodplan (Both Sides of River), Includes Irrigation Main and Control Wire/Conduit
42Irrigation Mainline Area A (Fused HDPE)120LF$ - 0Where Irrigation Main Crosses River
43Mainline Area A Flood Irrigation Zones20EA$ - 0Each zone is approximately 10,000 SF and inlcudes automatic control valve, wiring, decoder, valve box, piping and fiitings from mainline, piping and fittings to bubble up box, and bubble up box.
44Mainline Area B Flood Irrigation Zones29EA$ - 0Each zone is approximately 10,000 SF and inlcudes automatic control valve, wiring, decoder, valve box, piping and fiitings from mainline, piping and fittings to bubble up box, and bubble up box.
Sub Total:$ - 0
Pump System
45Shoring and Dewatering for Structural Fill1LS$ - 0
46Existing Pond Outlet Fish Screen Modifications1LS$ - 0
47Existing Pond Intake Structure Modifications1LS$ - 0
486-Inch DR-25 C900 PVC Pipe760LF$ - 0
496-Inch Gate Valve5EA$ - 0
50Fish Screen Structure1LS$ - 0
51Pump Station Site Work and Demo1LS$ - 0
52Pump Station Building1LS$ - 0
53Pump Station Piping1LS$ - 0
54Pump Station Electrical and Site Electrical1LS$ - 0
55Pump Station HVAC1LS$ - 0
56Wet Well1LS$ - 0
57Supply and Install Pump (Duty Pump)1EA$ - 0
58Supply and Install Pump (Jockey Pump)1EA$ - 0
59Reconnection of Aerator System, Piping, and Electrical1LS$ - 0
Sub Total:$ - 0
BASE BID LUMP SUM (NOT TO EXCEED):$ - 0
ADD-ALT 1: Spray Zone A and B Irrigation and Plantings
Item #DescriptionQuantityUnitUnit CostTotal CostNotes / Assumptions

Alex Heller: Alex Heller:

Include spec reference column. These notes are not included in bid schedule.

Revegetation (Spray Zones A and B)
60Supply, Broadcast, and Rake Seed Mix9.62AC$ - 0
61Supply and Plant D40 Container Plantings1,555EA$ - 0
62Supply and Plant Riparian Poles0EA$ - 0
63Supply and Plant Large Trees (10 gal)92EA$ - 0
64Supply and Plant Large Trees (4-6" Dia)0EA$ - 0
65Supply and Plant Plug Plantings0EA$ - 0
Sub Total:$ - 0
Irrigation System (Spray Zones A and B)
66Mainline Area A Spray Irrigation Zones18EA$ - 0
67Mainline Area B Spray Irrigation Zones5EA$ - 0
Sub Total:$ - 0
ADD-ALT 1 LUMP SUM (NOT TO EXCEED):$ - 0
ADD-ALT 2: Spray Zone C Irrigation and Plantings
Item #DescriptionQuantityUnitUnit CostTotal CostNotes / Assumptions

Alex Heller: Alex Heller:

Include spec reference column. These notes are not included in bid schedule.

Revegetation (Spray Zone C)
68Supply, Broadcast, and Rake Seed Mix7.13AC$ - 0
69Supply and Plant D40 Container Plantings1,529EA$ - 0
70Supply and Plant Riparian Poles0EA$ - 0
71Supply and Plant Large Trees (10 gal)16EA$ - 0
72Supply and Plant Large Trees (4-6" Dia)12EA$ - 0
73Supply and Plant Plug Plantings1,167EA$ - 0
Sub Total:$ - 0
Irrigation System (Spray Zone C)
74Irrigation Mainline Area C1,423LF$ - 0
75Mainline Area C Spray Irrigation Zones10EA$ - 0
Sub Total:$ - 0
ADD-ALT 2 LUMP SUM (NOT TO EXCEED):$ - 0
ADD-ALT 3: Spray Zone D Irrigation and Plantings
Item #DescriptionQuantityUnitUnit CostTotal CostNotes / Assumptions

Alex Heller: Alex Heller:

Include spec reference column. These notes are not included in bid schedule.

Alex Heller: Alex Heller:

Include spec reference column. These notes are not included in bid schedule.Revegetation (Spray Zone D)
76Supply, Broadcast, and Rake Seed Mix7.51AC$ - 0
77Supply and Plant D40 Container Plantings847EA$ - 0
78Supply and Plant Riparian Poles0EA$ - 0
79Supply and Plant Large Trees (10 gal)39EA$ - 0
80Supply and Plant Large Trees (4-6" Dia)72EA$ - 0
81Supply and Plant Plug Plantings1,974EA$ - 0
Sub Total:$ - 0
Irrigation System (Spray Zone D)
82Irrigation Mainline Area D1,618LF$ - 0
83Mainline Area D Spray Irrigation Zones11EA$ - 0
Sub Total:$ - 0
ADD-ALT 3 LUMP SUM (NOT TO EXCEED):$ - 0
ADD-ALT 4: Misc. Landscape, Irrigation and Pump System Items
Item #DescriptionQuantityUnitUnit CostTotal CostNotes / Assumptions

Alex Heller: Alex Heller:

Include spec reference column. These notes are not included in bid schedule.

Landscape
84Haul-off Stockpile10,000CY$ - 0
85Furnish and Install Crusher Fines641CY$ - 0Placed at overlook trail.
86Furnish and Install UTBC, Grade 1-1/2641CY$ - 0Placed under all crusher fines trails listed above.
87Furnish and Install 4oz Filter Fabric4,999SY$ - 0Placed under all crusher fines trails listed above.
Sub Total:$ - 0
Irrigation System
88Flow/Pressure Control Valves Locking Handle49EA$ - 0Add pressure/flow control valves to floodplain zones.
Sub Total:$ - 0
Pump System
8948-Inch Manhole with Ballast2EA$ - 0
902-Inch Stabilization Rock205TON$ - 0
91Stabilization Fabric325SY$ - 0
92Geogrid100SY$ - 0
93Supply and Install Pump (Duty Pump)1EA$ - 0
94Electrical for Additional Duty Pump1LS$ - 0
Sub Total:$ - 0
ADD-ALT 4 LUMP SUM (NOT TO EXCEED):$ - 0