3_Stuart Bathrroms SOW.pdf
PDF 7 MB Posted
- Attached to
- Monongahela National Forest, Stuart Bathroom Replacement Federal contract opportunity
- Solicitation number
- 12445523Q0089
- Issued by
- Department of Agriculture Forest Service
About this file
This statement of work outlines the technical requirements for a roof replacement project at two bathroom buildings located at the Stuart Recreation Area near Elkins, West Virginia. The USDA Forest Service is seeking to replace the cedar shake roof systems and rafter insulation on Building 1 and Building 2, which were built in 2005 and have roof areas of approximately 660 square feet each including skylights. The contractor will be responsible for demolishing the existing roofing systems, disposing of debris, installing new sheathing, underlayments, fasteners, flashings, cedar shakes and fiberglass insulation. The solicitation number for this opportunity is 12445523Q0089. The contractor must complete all work within the period of performance stated in the contract documents.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12445523Q0089 Amendmen 1 SF 30.pdf | ||
| wv24.txt | TXT text file | |
| 8_Stuart Bathroom Roof Replacement Specifications.pdf | ||
| 5_Stuart Bathrooms Eval. Criteria.pdf | ||
| 10_Stuart Bathrooms Vicinity Map.pdf | ||
| 12445523Q0089 SF 1442(8_2014).pdf | ||
| 2_Stuart Bathrooms SOI.xlsx | XLSX spreadsheet | |
| 9_Stuart Bathrooms Close-Up Map.pdf | ||
| 12445523Q0089 Monongahela Stuart Roof RFQ.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Project Identification Stuart Bathroom Roof Replacement
General Information
1.0 Scope of Work
• Contractor shall supply all materials, labor, and incidentals to complete the work described in the contract documents.
• Comply with all contract requirements in all contract documents.
• All work shall be completed within the Period of Performance.
• Work shall be completed for structures indicated in the contract documents.
• See photos in this document and attached maps for building identification.
2.0 Background
• Roof Systems of some bathroom buildings at the Stuart Recreation Area require total replacement.
• The insulation in the rafters may also need replaced.
• These buildings have had active roof leaks for a considerable time.
• Please note that neither structure has electrical service.
• Building 1 and Building 2 were built in 2005 and have similar dimensions.
• Each roof has an approximate gross area of 660 square feet. The 660sf gross area includes the area of the skylights.
o The skylights have approximate dimensions of 47”x30” (not including base flashing). There are 4 skylights on each building.
• Contractor is responsible to verify building and roof dimensions prior to purchase and installation of materials. The given dimensions and areas are not warrantied to be exact.
• Approximate Location – Stuart Recreation Area, near Elkins, WV o Approximate Building 1 Coordinates – (38.92037972909719, -79.77869530003248) o Approximate Building 2 Coordinates – (38.918198143557994, -79.77814911433134)
Contractor Requirements
3.0 Technical Requirements / Tasks
Base Bid:
• 0001 - Mobilization o Mobilize to the Site.
• 0002 - Building 1 - Remove and Dispose of Existing Roofing System. Provide and Install New Roofing System
(Underlayments, Sheathing Fasteners, Flashing, Shakes, etc.)
o Remove and Properly Dispose of existing cedar shakes, damaged or unusable flashing, vent flashings, felt underlayment, sheathing, and all corresponding fasteners for each building indicated. Carefully remove existing fascia shield/drip edge and set aside. Reinstall fascia shield/drip edge after replacement of sheathing. Replace any fascia shield/drip edge damaged by contractor operations. Metal rafters, fascia, and other items indicated shall remain in place. See specifications section 024119 for demolition requirements.
o Provide and install a new roofing system in accordance with the contract specifications and applicable references.
Sheathing Underlayments (Ice and Water Shield, Drainage Mat/Breathable Mesh, Felt) All Required and Incidental Fasteners Flashings Cedar Shakes All other incidental items to proper installation of a cedar shake roofing system.
Option Items (If exercised by the government):
• 1001 - Building 2 - Remove and Dispose of Existing Roofing System. Provide and Install New Roofing System
(Underlayments, Sheathing Fasteners, Flashing, Shakes, etc.)
o Remove and Properly Dispose of existing cedar shakes, damaged or unusable flashing, vent flashings, felt underlayment, sheathing, and all corresponding fasteners for each building indicated. Carefully remove existing fascia shield/drip edge and set aside. Reinstall fascia shield/drip edge after replacement of sheathing. Replace any fascia shield/drip edge damaged by contractor operations. Metal rafters, fascia, and other items indicated shall remain in place. See specifications section 024119 for demolition requirements.
o Provide and install a new roofing system in accordance with the contract specifications and applicable references.
Sheathing Underlayments (Ice and Water Shield, Drainage Mat/Breathable Mesh, Felt) All Required and Incidental Fasteners Flashings Cedar Shakes All other incidental items to proper installation of a cedar shake roofing system.
• 1002 - Building 1 - Rafter Insulation Removal & Replacement o Remove and properly dispose of insulation below existing sheathing and between the rafters.
o Provide and install new R-19 fiberglass insulation of adequate width to fit the rafter spacing and of adequate length to fit the space between the peak and the eaves.
• 1003 - Building 2 - Rafter Insulation Removal & Replacement o Remove and properly dispose of insulation below existing sheathing and between the rafters.
o Provide and install new R-19 fiberglass insulation of adequate width to fit the rafter spacing and of adequate length to fit the space between the peak and the eaves.
4.0 Government Furnished
• If the recreation area is open to the public, any open public restroom may be used by the contractor’s employees.
• Access to the interior of the building(s) is not likely to be provided unless otherwise open to the public.
• If necessary, request COR approval 7 business days in advance of accessing the interior of the building(s).
• See specifications for restrictions on work hours and other applicable work restrictions.
Attachments See Attached Photos. All documents in the contract package apply.
Figure 1: Building 1 Exterior Front View
Figure 2: Building 1 View of Rooftop – Ridge Units Are Missing Outside of this Photo
Figure 3: Building 1 – Area of Roof in Worst Condition
Figure 4: Building 1 – Roof Side View
Figure 5: Building 1 – Roof Side View
Figure 6: Building 1 – Missing Ridge Sections
Figure 7: Building 2 Exterior Front View
Figure 8: Building 2 Exterior Side View – Note Condition of Roofing System
Figure 9: Building 2 – Close Up View of Existing Roof Condition
Figure 10: Building 2 – Close Up View of Existing Roof Condition
| Project Identification |
| General Information |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| Attachments |
File details come from the government source that posted it. Updated .