This Request for Proposal (RFP) is issued by Eagle Mountain City, Utah, seeking qualified engineering consulting firms to provide professional engineering services for the design of the Silver Lake Parkway Roundabout Removal and Roadway Improvements Project. The project encompasses improvements along Silver Lake Parkway at Golden Eagle Road and Woodhaven Boulevard, extending south toward the Saratoga Springs boundary. Specific deliverables include removal of two existing roundabouts and their replacement with conventional signalized intersections, roadway realignment, turn-lane improvements, pedestrian and trail modifications, access management, landscaping and irrigation design, right-of-way documentation, coordination of three mailbox relocations, and design of approximately 350 feet of full roadway section. The scope requires complete construction documents, bid documents, and optional construction-phase engineering support. Proposals are due December 15, 2026, at 12:00 PM via the State of Utah's Public Procurement Portal, with an anticipated contract award date of January 4, 2027. The RFP reference number is EMC-FY27-13, and inquiries must be submitted by December 4, 2026. No site visit or bidders conference is explicitly required, though the consultant is expected to perform necessary field verification and survey work as part of project delivery.
Pricing will be evaluated as one component of the overall proposal, constituting 10 percent of the evaluation criteria, alongside firm experience (25 percent), project team experience (25 percent), functional approach (20 percent), technical approach (17 percent), and introductory letter content (3 percent). The consultant must submit a lump-sum fee by major task with a separate fee for optional construction-phase services and current hourly rates. Proposals must not exceed 15 single-sided pages in 11- or 12-point font on 8.5-by-11-inch paper. The successful consultant shall maintain professional liability insurance with limits of $1,000,000 per claim and $3,000,000 aggregate, general liability insurance of $1,000,000 per occurrence and $3,000,000 aggregate, and commercial automobile insurance of $1,000,000 combined single limit. The consultant must also carry valuable papers and records coverage and workers' compensation insurance. No set-aside is designated for this solicitation. Eagle Mountain City reserves the right to award based on initial proposals without further discussion, to reject any or all proposals, and to cancel the RFP if deemed in the city's best interest.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Eagle Mountain City
EMC Design Silverlake Pkwy Roundabout Removal & Roadway
Improvements
REQUEST FOR PROPOSAL (RFP) NO. EMC-FY27-13
RFP Due Date: January 7, 2027, by 12:00 P.M.
RFP Administrator: Melissa Yates, Purchasing Agent P: (801) 789-6641 E: Myates@EagleMountain.gov
Issued: November 24, 2026
Interested parties may obtain a copy of this RFP and submit responses through the State of Utah’s Public
Procurement Portal:
Revised: February 2026 2 purchasing.utah.gov
TABLE OF CONTENTS
OVERVIEW 3
I. INTRODUCTION 3
II. SCOPE OF SERVICES 3
III. PROPOSAL EVALUATION CRITERIA 10
IV. PROPOSAL RESPONSE OUTLINE 11
IV. INSURANCE REQUIREMENTS 13
V. TIMELINE 14
VI. ADMINISTRATIVE GUIDANCE 14
VII. ISSUING OFFICE AND RFP REFERENCE NUMBER 15
VIII. SUBMISSION OF PROPOSAL 15
IX. BID BOND Error! Bookmark not defined.
X. VENDOR PREQUALIFICATION 15
XI. INQUIRIES 16
XII. RESPONDENT’S RESPONSIBILITY FOR PROPOSAL COSTS 16
XIII. EVALUATION OF PROPOSALS 16
XIV. KEY COMPANY PERSONNEL 16
XV. ORAL PRESENTATION 17
XVI. AWARD OF THE CONTRACT 17
XVII. PROTECTED INFORMATION 17
XVIII. ADDENDUM TO RFP 17
XIX. AUTHORIZED REPRESENTATIVES 18
XX. ANTI-COLLUSION 18
XXI. RESTRICTIONS / CONFLICT OF INTEREST 18
XXII. RIGHT TO REJECT 18
XXIII. PRIVACY NOTICE 18
ATTACHMENT A 20
ATTACHMENT B 24
https://purchasing.utah.gov/
Revised: February 2026 3
OVERVIEW
I. INTRODUCTION
Eagle Mountain City is seeking proposals and detailed cost estimates from qualified engineering consultants to provide professional engineering services for the design of the Silver Lake Parkway
Roundabout Removal and Roadway Improvements Project.
II. SCOPE OF SERVICES
The project includes improvements along Silver Lake Parkway at Golden Eagle Road and Woodhaven Boulevard, as well as roadway improvements extending south toward the Saratoga Springs boundary.
The project will remove the existing roundabouts at Silver Lake Parkway and Golden Eagle Road and at Silver Lake Parkway and Woodhaven Boulevard and replace them with conventional signalized intersections. The project will also include roadway realignment, turn-lane improvements, pedestrian and trail modifications, access management, landscaping and irrigation, right-of-way documentation, mailbox relocations, and design of approximately 350 feet of full roadway section south of Golden Eagle Road to the Saratoga Springs boundary.
The project includes three primary design elements:
1. Removal and reconstruction of the existing roundabout at Silver Lake Parkway and Golden Eagle Road as a conventional signalized intersection.
2. Removal and reconstruction of the existing roundabout at Silver Lake Parkway and Woodhaven Boulevard as a signalized T-intersection, with Silver Lake Parkway terminating at Woodhaven Boulevard and Woodhaven Boulevard continuing south.
3. Design of approximately 350 feet of full roadway section south of Golden Eagle Road to the Saratoga Springs boundary, including roadway, drainage, trail, curb and gutter, and park strip improvements.
The consultant shall provide all engineering services necessary to prepare complete construction documents and bid documents for the project.
Project Management and Coordination
• Conduct a kickoff meeting with Eagle Mountain City staff.
• Coordinate regularly with City staff throughout design.
• Develop and maintain a project schedule identifying major design milestones and City review periods.
• Coordinate with affected utilities, adjacent property owners, Saratoga Springs, emergency services, USPS, and other agencies or stakeholders as necessary.
• Coordinate roadway, traffic signal, pedestrian, trail, landscaping, irrigation, access, mailbox relocation, and right-of-way improvements throughout the project.
Survey and Existing Conditions The consultant shall perform the survey and field verification necessary to complete the design, including:
• Existing roadway geometry.
• Existing roundabout geometry.
Revised: February 2026 4
• Existing pavement limits.
• Existing curb and gutter.
• Existing roadway profiles and cross slopes.
• Existing drainage facilities and drainage patterns.
• Existing utilities and utility appurtenances.
• Existing traffic control, signing, and pavement markings.
• Existing street lighting.
• Existing sidewalks, trails, pedestrian ramps, and crosswalks.
• Existing landscaping and irrigation.
• Existing mailboxes and cluster mailbox unit locations.
• Existing driveways and property accesses.
• Existing right-of-way and property boundaries.
• Existing fencing, gates, and other features that may be impacted by the proposed improvements.
The consultant shall identify potential conflicts early in design and coordinate recommended resolutions with the City.
Right-of-Way Documentation The consultant shall prepare right-of-way and property documentation necessary to support the proposed improvements. Right-of-way work shall include, at a minimum:
• Right-of-way documentation for the northeast corner of the Silver Lake Parkway and Golden Eagle Road intersection.
• Right-of-way documentation for the two parcels located south of Golden Eagle Road along Silver Lake Parkway adjacent to the Saratoga Springs boundary.
• Property research and verification of existing ownership, parcel boundaries, easements, and existing right-of-way.
• Preparation of legal descriptions and exhibits for required right-of-way, easements, temporary construction easements, or other property interests identified during design.
• Coordination with Eagle Mountain City regarding limits of acquisition.
• Preparation of survey documentation necessary to support the City’s acquisition process.
The consultant shall identify anticipated right-of-way needs as early as practical in the design process so property acquisition does not delay final design or construction.
Silver Lake Parkway and Golden Eagle Road Intersection The consultant shall design removal of the existing roundabout at Silver Lake Parkway and Golden Eagle Road and reconstruction of the intersection as a conventional signalized intersection. The design shall include:
• Removal of the existing roundabout.
• Reconstruction of the intersection as a standard four-leg intersection.
• Realignment of the east leg to create proper intersection geometry.
• Reconstruction of roadway approaches as necessary.
• Addition of appropriate left-turn and right-turn lanes.
• Turn-lane storage lengths based on anticipated traffic queues.
• Installation of a new traffic signal.
• Signal poles, mast arms, foundations, conduit, pull boxes, controller equipment, vehicle detection, and associated electrical improvements.
• Relocation of pedestrian crossings so all crosswalks are located directly at the reconstructed intersection.
Revised: February 2026 5
• ADA-compliant pedestrian ramps and crossings.
• Signing and pavement markings.
• Street lighting modifications as required.
• Drainage modifications.
• Utility coordination.
• Landscaping and irrigation restoration as necessary.
• Appropriate roadway transitions into the existing roadway network.
The consultant shall perform the traffic engineering necessary to determine appropriate lane configurations, turn-lane storage, signal phasing, and intersection geometry.
Silver Lake Parkway and Woodhaven Boulevard Intersection The consultant shall design removal of the existing roundabout at Silver Lake Parkway and Woodhaven Boulevard and reconstruction of the area as a signalized T-intersection. The proposed roadway configuration shall terminate Silver Lake Parkway at Woodhaven Boulevard. Woodhaven Boulevard shall become the continuous north-south roadway through and south of the intersection.
The design shall include:
• Removal of the existing roundabout.
• Reconstruction as a conventional T-intersection.
• Termination of Silver Lake Parkway at Woodhaven Boulevard.
• Continuation of Woodhaven Boulevard south through the intersection.
• Realignment of roadway approaches as necessary.
• Addition of appropriate turn lanes and turn-lane storage.
• Installation of a new traffic signal.
• Signal poles, mast arms, foundations, conduit, pull boxes, controller equipment, detection, and associated electrical improvements.
• Crosswalks located at the new intersection.
• ADA-compliant pedestrian ramps and facilities.
• Signing and pavement markings.
• New street-name signs reflecting the revised roadway configuration.
• Relocation of applicable street-name signage farther south to reflect the continuation of
Woodhaven Boulevard.
• Drainage modifications.
• Utility coordination.
• Street lighting modifications as necessary.
Property Readdressing Because Woodhaven Boulevard will become the continuous north-south roadway south of the reconstructed intersection, two properties located immediately south of the intersection will require readdressing to reflect the revised roadway configuration. Eagle Mountain City will perform the property readdressing and associated address coordination. The consultant shall show the revised roadway naming and configuration on the construction plans as necessary to support the City’s readdressing effort.
Campbell Circle Emergency Access The consultant shall design a gated emergency-access connection at Campbell Circle. The design shall include:
• A normally closed gate.
Revised: February 2026 6
• Emergency vehicle access.
• Appropriate pavement or roadway connection.
• Signing.
• Coordination with emergency services.
• Gate type and access-control details as directed by the City.
• Grading, drainage, and restoration associated with the emergency-access connection.
Jimmy Lane Access Modification The consultant shall modify access at Jimmy Lane to restrict the intersection to right-in/right-out movements only. The design shall include:
• Appropriate raised median, channelization, or other physical access-control improvements.
• Signing and pavement markings.
• Evaluation of turning movements and roadway geometry.
• Coordination with adjacent accesses and properties.
• Pedestrian and trail considerations, where applicable.
Mailbox Relocation The consultant shall design and coordinate relocation of three existing cluster mailbox unit locations affected by the proposed roadway improvements. The mailbox relocations shall include:
• Relocate one existing cluster mailbox unit currently located along Woodhaven Boulevard south of Pony Express Parkway to the north park strip of East High Noon Avenue.
• Relocate two existing cluster mailbox units currently located along Woodhaven Boulevard south of East High Noon Avenue to the north park strip of Oakwood Drive.
• Coordinate the proposed relocation locations and mailbox configuration with the United States Postal Service and the appropriate local postmaster.
• Verify required mailbox clearances, access, parking considerations, and USPS requirements.
• Remove the existing concrete mailbox pads at the existing locations.
• Restore the former mailbox pad areas with landscaping consistent with the surrounding park strip.
• Modify, reconnect, or extend irrigation as necessary to maintain continuous irrigation in the restored landscape areas.
• Remove or modify existing landscaping and park strip improvements at the proposed mailbox locations as necessary.
• Cap, relocate, or modify irrigation facilities conflicting with the new mailbox pads.
• Construct new concrete pads suitable for the relocated cluster mailbox units.
• Coordinate grading and pedestrian access to the relocated mailbox locations.
• Include all necessary demolition, concrete, landscaping, irrigation, and restoration work in the construction documents.
The consultant shall coordinate mailbox relocation early in design so USPS approval and relocation requirements do not delay construction.
Trail and Pedestrian Improvements The consultant shall evaluate existing pedestrian and trail facilities affected by removal of the Woodhaven Boulevard roundabout and reconstruction of the new T-intersection. The design shall include:
• Demolition of the existing trail section and pedestrian ramp affected by the proposed roadway configuration.
• Relocation and reconstruction of the trail to connect appropriately to the new intersection.
• New ADA-compliant pedestrian ramps.
Revised: February 2026 7
• Crosswalks at the new signalized intersection.
• Appropriate pedestrian connections between existing and proposed facilities.
• Restoration of disturbed trail areas.
Landscaping and Irrigation The consultant shall provide landscaping and irrigation design for infill and disturbed areas created by removal of the existing roundabouts, construction of the new conventional intersections, mailbox relocation, and other roadway improvements. The design shall include:
• Removal of landscaping and irrigation conflicting with proposed improvements.
• Landscaping of infill areas around the reconstructed T-intersection.
• Irrigation modifications.
• Restoration of disturbed landscape areas.
• Restoration of former mailbox-pad locations.
• Irrigation modifications associated with new mailbox-pad locations.
• Coordination with sight-distance requirements, traffic signals, utilities, trails, mailbox facilities, and street lighting.
• Landscaping materials generally consistent with surrounding City improvements unless otherwise directed by Eagle Mountain City.
Southern Silver Lake Parkway / Woodhaven Boulevard Roadway Section The consultant shall design approximately 350 feet of full roadway section south of Golden Eagle Road to the Saratoga Springs boundary. Following the proposed roadway-name and alignment changes, this portion of roadway is anticipated to function as an extension of Woodhaven Boulevard. The design shall include:
• Horizontal and vertical roadway alignment.
• Full pavement section.
• Travel lanes.
• Appropriate roadway width and lane configuration.
• Curb and gutter.
• Park strip.
• Trail facilities.
• Grading.
• Storm drainage.
• Utility coordination.
• Signing and striping.
• Street lighting, if required by City standards.
• Landscaping and irrigation.
• Tie-in to existing or planned improvements at the Saratoga Springs boundary.
The consultant shall coordinate the roadway section with the two adjacent parcels and identify right-of-way or easement needs necessary to construct the proposed roadway section.
Traffic Engineering and Signal Design The consultant shall provide traffic engineering necessary to support design of the Golden Eagle Road and Woodhaven Boulevard intersections. Traffic engineering shall include:
• Review of available City traffic studies and traffic counts.
Revised: February 2026 8
• Evaluation of projected traffic volumes.
• Intersection lane configuration.
• Turn-lane requirements.
• Queue and storage analysis.
• Signal phasing.
• Signal timing considerations.
• Pedestrian crossing needs.
• Access-management impacts.
• Evaluation of Jimmy Lane right-in/right-out operations.
The consultant shall coordinate proposed traffic signal designs with Eagle Mountain City standards and existing signal infrastructure.
Drainage The consultant shall evaluate existing drainage conditions and design drainage improvements necessary to support the proposed roadway and intersection improvements. Drainage design shall include, as applicable:
• Roadway drainage calculations.
• Existing drainage-system evaluation.
• Inlets, catch basins, manholes, storm drain pipe, and associated improvements.
• Modification or relocation of existing facilities.
• Drainage associated with removal of the existing roundabouts.
• Drainage associated with the southern roadway extension.
• Grading of landscape and infill areas.
• Tie-ins to existing drainage infrastructure.
Utility Coordination The consultant shall identify existing utilities and potential conflicts throughout the project limits. The consultant shall:
• Identify utilities requiring adjustment or relocation.
• Coordinate with utility providers and Eagle Mountain City.
• Identify conflicts with roadway, signal, drainage, trail, landscaping, irrigation, mailbox, and right-of-way improvements.
• Incorporate utility adjustments into the construction plans where appropriate.
• Clearly identify anticipated utility work in the construction documents.
Design Submittals The consultant shall provide formal design submittals at the following milestones:
30% Design
• Existing conditions and survey.
• Preliminary roadway and intersection layouts.
• Preliminary right-of-way needs.
• Preliminary signal layouts.
• Preliminary trail and pedestrian modifications.
• Preliminary mailbox relocation layouts.
• Preliminary southern roadway-section layout.
• Identification of major utility and drainage conflicts.
50% Design
Revised: February 2026 9
• Developed roadway, intersection, signal, drainage, trail, utility, landscaping, irrigation, mailbox, signing, and striping plans.
• Draft right-of-way exhibits and legal descriptions.
• Preliminary quantities.
• Engineer’s Opinion of Probable Construction Cost.
90% Design
• Substantially complete construction plans.
• Draft bid documents.
• Substantially complete right-of-way documentation.
• Updated quantities.
• Updated Engineer’s Opinion of Probable Construction Cost.
• Response to previous City review comments.
100% Design
• Final signed and sealed construction documents.
• Final right-of-way exhibits and legal descriptions.
• Final quantities.
• Final Engineer’s Opinion of Probable Construction Cost.
• Final bid documents.
• Final response to City review comments.
Bid Documents The consultant shall prepare project-specific bidding documents using Eagle Mountain City-provided templates, including:
• Project scope.
• Bid schedule and bid quantities.
• Measurement and Payment provisions.
• Technical specifications.
• Project-specific special provisions.
• Engineer’s Opinion of Probable Construction Cost.
• Final construction plans.
The consultant shall coordinate bid quantities directly with the final construction plans and Measurement and Payment provisions.
Optional Construction-Phase Engineering Services The consultant shall provide a separate optional fee for construction-phase engineering support, including:
• Preconstruction meeting attendance.
• Responses to contractor RFIs.
• Review of submittals and shop drawings.
• Design clarifications.
• Preparation of revised details or drawings when necessary.
• Limited construction-site visits when requested by the City.
• Assistance with interpretation of plans and specifications.
Proposal Requirements Please submit a concise proposal that includes:
• Proposed scope of work and methodology.
• Assumptions and exclusions.
Revised: February 2026 10
• Identification of any additional services recommended by the consultant.
• Project schedule and anticipated design milestones.
• Estimated manpower by task.
• Lump-sum fee by major task.
• Separate fee for optional construction-phase services.
• Current hourly rate schedule.
• Proposed project team and responsibilities.
• Proposed subconsultants.
• Relevant experience with roadway reconstruction, roundabout removal, traffic signal design, right-of-way documentation, access management, pedestrian improvements, landscaping and irrigation, and USPS mailbox relocation coordination.
• List of information or services anticipated to be provided by Eagle Mountain City.
III. PROPOSAL EVALUATION CRITERIA
Proposals will be evaluated based on the response to all provisions of this RFP. Since this solicitation is an
RFP as opposed to a Bid, pricing alone will not constitute the entire selection criteria. The city may use some or all of the following criteria and corresponding percentages in its evaluation and comparison of proposals submitted. The criteria listed are not necessarily an all-inclusive list. The order in which they appear is not intended to indicate their relative importance. The City reserves the right to modify the evaluation criterion and percentage of the score as deemed appropriate prior to the commencement of evaluation.
Evaluation Process
Proposals will be reviewed by the individual committee members against certain criteria through a pre-prepared scoring matrix. The committee will submit their scores to the City
Purchasing Agent who will compile the scores and rank the submissions. The committee will meet to review the top three scoring firms and may schedule a 1-hour virtual or in-person presentation from each vendor. The presentations will not be scored, but the evaluation committee will, at the conclusion of all presentations, select a firm for award or withdraw the
RFP.
POTENTIAL PROPOSAL EVALUATION CRITERIA
Evaluation Criteria Description Percentage
Firm Experience Qualifications and experience of the firm. Demonstrated expertise and subject matter expertise in the requested Scope of Services
25%
Project Team Experience Qualifications and experience of the 25%
Revised: February 2026 11
IV. PROPOSAL RESPONSE OUTLINE
Proposals must be clear, concise, specific and, in an outline, format not exceeding 15 single side pages.
Font size must be an 11- or 12-point font. Paper size not to exceed 8.5 x 11 inches. Pertinent supplemental information should be referenced and provided as attachments but will not be considered part of the proposal. All proposals must be organized and tabbed to comply with the following sections. Tabs will not be counted toward page count as long as they do not contain proposal information.
Tab 1 - LETTER OF TRANSMITTAL. The letter of transmittal should include an introduction of the Project
Team: the name, address, telephone number, and email address of the person to be contacted along with others who are authorized to represent the company in dealing with this RFP.
Tab 2 - EXECUTIVE SUMMARY. Should include an introduction of the Firm and parent company: the name, address, telephone number, email address, nature of firm’s principal business, number of years in business, state and federal licensing certificates and Federal Tax Identification. Provide a brief statement that summarizes the unique qualifications of the Firm in relation to the unique and general requirements of this project. The respondent shall provide evidence of their firm’s capability to apply and commit staff and equipment successfully to the project and to complete the required services in a timely manner.
The respondent shall list all bankruptcy filings within the last ten years, and all current pending litigation involving the firm. Failure to provide full information may result in the proposal being deemed nonresponsive.
Tab 3 - DETAILED DISCUSSION. This section should constitute the major portion of the proposal and must contain:
Firm’s Project Team, including the Firm’s Project Team’s demonstrated expertise and subject matter expertise in the requested Scope of Services
Functional Approach The Firm’s project team demonstrates the ability to formulate a plan that includes the elements listed in the scope of work.
20%
Technical Approach The quality and clarity of the Firm’s proposal demonstrates the ability to formulate a plan that is concise and easily understood by stakeholders.
17%
Cost Project costs / fee schedule as compared to other firms. 10%
Introduction
Introductory Letter contains all the information requested.
3%
Revised: February 2026 12
1. Proposed Project Team Organization and Qualifications: Provide a chart that identifies the roles of each of the Key Individuals involved in each phase of the project. Firm should provide a listing of staff to be assigned to the project and commentary on their existing workload, and a description of the project management processes used to ensure work continues uninterrupted and communication with the city and firm is strong. Respondent shall provide, rather than a standard resume, only relevant experience and qualification of each technical person who will be involved on the project, including:
a. Educational background, academic degrees, professional association.
b. Current job title, responsibilities and type of work performed.
c. Experience on projects similar to that requested in this RFP.
Provide a matrix that indicates past project collaborations carried out by the proposed team.
2. Proposed Project Team Performance on Past Projects: Provide information for similar studies that demonstrate the Firm’s ability to accomplish this project. For each project identified, provide the following information: Owner, Description of Work, and Project Team Members’ involvement.
3. References: Provide a reference for each project listed above who may be contacted for further information regarding the performance of the Firm’s Project Team. The respondent should provide examples of similar projects through access to deliverables such as studies, reports, maps, images, video, etc.
4. Team Roles and Responsibilities: Provide a description of the roles and responsibilities of the
Firm’s Project Team members and how the Team will work together to achieve the objectives of the project. List any applicable sub-consultants.
5. Proposed Project Schedule: Provide a schedule that includes individual phases as applicable. The proposed schedule shall list important dates, times, and locations of meetings and submittals.
6. Proposed Project Approach: Outline the tasks, any special approaches, and the plan for completion. Innovation and alternatives to the scope proposed here are welcome.
7. Information addressing Project Objectives and Scope that have not been addressed.
Tab 4 - COST PROPOSAL. The Firm must submit a cost proposal allowing costs to be evaluated independently of other criteria in the proposal, both in grand total, as well as component pricing for logical subsets of service with any associated discounts listed separately. The cost proposal should include the method of determining compensation for the required services with a not-to-exceed cost estimate. It should also include the estimated cost to complete all of the Firm’s Basic Services.
Revised: February 2026 13
Tab 5 – BID FORM (Attachment A), Certificate of Insurance AND MISCELLANEOUS additional information and attachments, including company literature and catalogs.
IV. INSURANCE REQUIREMENTS
Should the successful firm be invited to negotiate a contract for the work identified in this RFP, it shall have the capability of maintaining insurance and indemnification as follows to cover any claims incurred or arising as a result of the work. The Contractor / Consultant shall furnish Eagle
Mountain a Certificate of Insurance applying to the contract for each type of insurance required, to be approved by Eagle Mountain City. The Consultant’s insurer must be authorized to do business in Utah and must meet the specified A.M. Best rating or better at the time this contract is executed. The following insurance shall be maintained in force until all activities which are required by the Contract or as changed by contract modification are completed and accepted by Eagle Mountain:
a. General Liability insurance with a limit of not less than $1,000,000 per occurrence and not less than $3,000,000 aggregate and having an A.M. Best rating of A-class VIII or better. If this coverage is written on a claims-made basis, the Certificate of Insurance shall so indicate. Consultant represents that as long as commercially available the insurance shall remain in effect such that claims reported up to three (3) years beyond the date of substantial completion of this contract are covered.
b. Commercial Automobile insurance with a minimum combined single limit of $1,000,000 per occurrence OR $500,000 liability per person, $1,000,000 per occurrence, $250,000 Property Damage, and having an A.M. Best rate of A-class VIII or better.
c. Architect and/or Engineers Professional Liability (errors and omissions) insurance having an A.M.
Best rating of A-class VIII or better, is required at the coverage amount of $1,000,000 per claim and $3,000,000 aggregate. If this coverage is written on a claims-made basis, the Certificate of Insurance shall so indicate. Consultant represents that as long as commercially available the insurance shall remain in effect such that claims reported up to three (3) years beyond the date of substantial completion of this contract are covered (on construction contracts or modifications for construction management the insurance, shall remain in effect for one (1) year after completion of the project).
d. Valuable Papers & Records Coverage and/or Electronic Data Processing (Data and Media) Coverage for the physical loss or destruction of the work product including drawings, plans, specifications and electronic data and media. Such insurance shall be of a sufficient limit to protect Consultant, its sub-consultants and Eagle Mountain from the loss of said information.
e. Workers Compensation Insurance: Consultant shall provide evidence that his employees and sub-consultant employees are covered by Workers Compensation. If they are covered by Workers Compensation Fund of Utah, then the A.M. Best rating is not required in this area.
f. Consultant shall require the insurance company that issues the Certificates of Insurance for the evidence of the required insurance coverage to endeavor to provide Eagle Mountain with 30-
Revised: February 2026 14 days written notice in the event that coverage is canceled before the policy expiration date stated in the Certificate. Consultant further agrees to provide Eagle Mountain with 30 days written notice prior to making an alternation or material change to the required insurance coverage. Insurance certificates and notice(s) should be sent to recorder@emcity.org.
g. Builders Risk Insurance. Builder’s Risk Insurance must be indicated by a checked box on the Certificate of Insurance (COI). The Contractor shall provide the City with the price for the Builder’s Risk Insurance coverage applicable to the project. Upon receipt of the Contractor’s quoted price, the City will obtain a comparable quote from the Utah Local Government Trust for the same policy limits. If the Utah Local Government Trust premium is lower than the Contractor’s quoted price, the City will procure the Builder’s Risk policy through the Trust. In such case, the Contractor shall reimburse the City for the cost of the policy, and the amount will be deducted from payments due under the contract.
h. Policies referred to in (a) and (b) above are required to be endorsed naming Eagle Mountain as Additional Insured and, on General Liability, indicate they are primary and not contributing coverage. All required policies, endorsements, insurance companies issuing same, and self-insured programs are subject to review and approval by Eagle Mountain.
V. TIMELINE
The following is a tentative schedule of this entire RFP process. While the City will attempt to apply the necessary resources to maintain this schedule, the following dates are merely projections. The City reserves the right to modify this schedule as needed to accommodate the completion of this RFP process.
TENTATIVE PROJECT SCHEDULE
RFP Published November 24, 2026
Questions from Firms Due December 4, 2026
Questions and Answers Posted December 8, 2026
Proposals Due December 15, 2026, at 12:00 PM
Anticipated Contract Award January 4, 2027
VI. ADMINISTRATIVE GUIDANCE
The information provided herein is intended to assist Firms in the preparation of proposals necessary to properly respond to this RFP. The RFP is designed to provide interested Firms with sufficient basic information to submit proposals meeting minimum requirements but is not intended to limit a proposal's content or to exclude any relevant or essential data therefrom. Firms are at liberty and are encouraged
Revised: February 2026 15 to expand upon the specifications to give additional evidence of their ability to provide the services requested in this RFP.
VII. ISSUING OFFICE AND RFP REFERENCE NUMBER
Eagle Mountain City <Engineering Department> is the issuing office for this RFP and all subsequent addenda. The reference number for this RFP is EMC-FY27-13. This number must be referenced on all proposals, correspondence, and documentation relating to this RFP. During the RFP process, the
Purchasing Agent is the sole source of official information. All other communications regarding this RFP, both spoken and written, which are received by any representative of the Firm from other sources (such as any elected or appointed official of the city or any other city staff, unless said communication is required by the primary contact) shall result in the disqualification of the proposal. This refers to both formal and informal conversations and communications.
Contact: Melissa Yates, Purchasing Agent 1650 E Stagecoach Run Eagle Mountain, Utah 84005 Myates@EagleMountain.gov
(801) 789-6641
VIII. SUBMISSION OF PROPOSAL
Proposal RFP documents will be available online on November 24, 2026, at purchasing.utah.gov (select the search bar> select Current Bids > enter “EM” > select search.) Sealed proposals will then be accepted online only via purchasing.utah.gov procurement portal until, December 15, 2026, at 12:00 PM. Proposals submitted after this deadline will be rejected. All proposals, upon submission to the City, shall become
City property.
Failure to provide a response to items indicated in this RFP will be interpreted by the city as an inability by the Firm to provide the requested service. All submittals shall be complete in all material respects and failure to provide a complete submittal may result in rejection of the response.
IX. VENDOR PREQUALIFICATION
All potential vendors are required to register with Eagle Mountain City prior to doing business. You may complete required prequalification forms by going to EagleMountain.gov/purchasing. Fill out the vendor prequalification form and submit W9.
The City may conduct such investigations as the City deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals, or entities to perform the Work in accordance with the contract Documents.
Revised: February 2026 16
X. INQUIRIES
Questions arising subsequent to the issuance of this RFP shall be submitted in writing through the State of Utah’s online procurement portal. Questions and answers will be posted online or consolidated and provided to all Firms on record of receiving this RFP on the procurement portal. All inquiries must be submitted by the close of business (5:00 PM MST) on December 4, 2026. Questions submitted after the deadline will not be addressed.
XI. RESPONDENT’S RESPONSIBILITY FOR PROPOSAL COSTS
The City is not liable for any cost incurred by Firms associated with the preparation of the proposal or the negotiation of a contract for services prior to the issuance of the contract.
XII. EVALUATION OF PROPOSALS
The City may award a contract based on initial proposals received without discussion of such proposals with the Firm. Accordingly, each initial proposal should be submitted with the most favorable price and service available.
In evaluating proposals, the city will consider whether or not the proposals comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the proposal or prior to the Notice of Award. Evaluation committee members will evaluate and rank each submittal based on required information provided. Evaluation factors are based on the abilities of the proposer to efficiently perform the Scope of Services as generally outlined in the Request for Proposals. The city will be seeking to identify the submittal(s) which will best meet the needs of Eagle Mountain City as determined from the responses to the Request for Proposals.
The City will also consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities. During the evaluation process and at the sole discretion of the City, requests for clarification of one or more proposer’s submittals may be conducted. This request for clarification may be performed by the city in a written format, or through scheduled oral interviews. Such clarification request will provide proposers with an opportunity to answer any questions the City may have on a proposer’s submittal.
XIII. KEY COMPANY PERSONNEL
In submitting a proposal package, the Respondent is representing that each person listed or referenced in the proposal package shall be available to perform the services described for the city, barring illness, accident, or other unforeseeable events of a similar nature in which case the Respondent must be able to promptly provide a qualified replacement. In the event the Respondent wishes to substitute personnel, the Respondent shall propose a person with equal or higher qualifications and each replacement person is subject to prior written city approval. In the event the requested substitute
Revised: February 2026 17 person is not satisfactory to the city and the matter cannot be resolved to the satisfaction of the city, EAGLE MOUNTAIN CITY reserves the right to cancel the contract for cause.
XIV. ORAL PRESENTATION
The city may require an oral presentation by Firms to supplement a proposal. The presentations, if required, shall be scheduled by Melissa Yates, Purchasing Agent, after the proposals have been received and prior to the award of the contract.
XV. AWARD OF THE CONTRACT
Upon completion of the evaluation process, the City may negotiate with and award the contract to the
Firm whose proposal is determined to be most advantageous and produces the best possible outcome for the city. If detailed in the proposal, factors such as additive alternate bids, discounts, transportation costs, and life cycle costs may be used to determine which bidder, if any, is offered the award. It is understood that the city is not obligated to make an award under or as a result of this RFP or to award such contract.
The parties must execute the contract prior to the commencement of performance. The contract will incorporate the provisions of this RFP (including any addenda) and other terms negotiated by the parties.
By submitting a signed proposal, the Firm agrees to the provisions of the contract described herein.
XVI. PROTECTED INFORMATION
Under the Government Records Access and Management Act, Section 63-2-101 et seq., Utah Code Ann.
(1993 and supp. 1996), as amended ("GRAMA"), the proposal submitted is open for public inspection. If the Firm desires to have information contained in its proposal protected from such disclosure, the Firm may request such treatment by providing a "written claim of business confidentiality and a concise statement of reasons supporting the claim of business confidentiality" with the proposal (GRAMA, Section
63G-2-309). All material contained in and/or submitted with the proposal becomes the Owner's property and may be returned only at the Owner's option. A business confidentiality claim form is available on the
Utah State Records Committee website:
https://eaglemountaincity.com/wp-content/uploads/2022/10/GRAMA-Claim-of-Business-
Confidentiality-Fillable.pdf
XVII. ADDENDUM TO RFP
In the event that it becomes necessary to review this RFP in whole or in part, an addendum will be provided to all Firms on record as having received this RFP through the State of Utah’s online procurement portal.
https://eaglemountaincity.com/wp-content/uploads/2022/10/GRAMA-Claim-of-Business-Confidentiality-Fillable.pdf
Revised: February 2026 18
XVIII. AUTHORIZED REPRESENTATIVES
The proposal or bid must contain the signature of a duly authorized officer, or agent of the Firm’s company empowered with the right to bind the Firm for the amounts estimated and terms proposed. The Firm must also provide evidence of the authority of the officer or agent to bind the Firm. The owner shall have the option to change the Firm’s contact person if it is in the best interest of the Owner.
Include this information within the "Letter of Transmittal", which will be tabbed section "1" of a successful proposal.
XIX. ANTI-COLLUSION
The submission of a proposal constitutes agreement that the Firm has not divulged its proposal to, or conspired with, any other Firm or party to a proposal whatsoever.
This Bid is genuine and not made in the interest of or on the behalf of any undisclosed individual or entity and is not submitted in conformity with any agreement or rules of any group, association, organization, or corporation. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract.
XX. RESTRICTIONS / CONFLICT OF INTEREST
All proposals must clearly set forth any restrictions or provisions deemed necessary by the Firm to effectively service the proposed Contract.
If any officer, director, or agent of your organization is also an employee of Eagle Mountain City, then you shall clearly identify in your response the name of the individual(s) and the position he or she holds in your organization. Further, you shall disclose the name(s) of any City employee(s) who owns, directly or indirectly, any interest in your organization or any of its branches. This does not include stock in a publicly traded organization unless the individual holds more than a ten-percent (10%) stake.
XXI. RIGHT TO REJECT
The City reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. The City further reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to be non-responsible. The City also reserves the right to waive all informalities or technicality in any bid or proposal in the interest of the City not involving price, time, or changes in the Work and to negotiate contract terms with the Successful
Bidder. The city has the sole discretion and reserves the right to cancel this RFP, and to waive any and all informalities and/or irregularities, or to re-advertise with either the identical or revised specifications, if it is deemed to be in the city’s best interests to do so.
XXII. PRIVACY NOTICE
Eagle Mountain City is committed to protecting your privacy. The personal data you provide for bids/proposals is collected for the purpose of processing submitted bidding documentation, permit
Revised: February 2026 19 applications, verifying identity, and contracts and will be used only for those purposes. If you choose not to provide the requested information, we may be unable to process your request or provide the service you are seeking. Your information will not be sold and is not regularly disclosed to any private or governmental entities. However, it may be shared when required by law or contract. The information collected is maintained in the Eagle Mountain Recorders office in accordance with the City's retention records schedule. Some personal data may still be subject to public disclosure as required by the Utah
Government Records Access and Management Act (GRAMA), Utah Code § 63G-2-101 et seq.”
Revised: February 2026 20
ATTACHMENT A
Bid Form
Project Name: EMC Silver Lake Pkwy Roundabout Removal & Roadway Improvements Project
Project Number: EMC-FY27-13
ARTICLE 1 - BID RECIPIENT
1.01 This Bid Is Submitted To: EAGLE MOUNTAIN CITY
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with
Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in the Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2 - BIDDER’S ACKNOWLEDGMENTS
2.01 Bidder accepts all of the terms and conditions of the Advertisement and Instructions to Bidders, including without limitations those dealing with the dispositions of Bid security. The Bid will remain subject to acceptance for 30 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.
ARTICLE 3 - BIDDER’S REPRESENTATIONS
3.01 In submitting this Bid, Bidder represents that:
A. Bidder has examined and carefully studied the Bidding Documents, the other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged:
Addendum No. Addendum Date
B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local, and
Site conditions that may affect cost, progress, and performance of the Work.
Revised: February 2026 21
C. Bidder is familiar with and is satisfied as to all Federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work.
D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in SC-4.02, and (2) reports and drawings of Hazard Environmental
Conditions, if any, at the Site that have been identified in SC-4.06 as containing reliable
“technical data.”
E. Bidder has considered the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by
Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs.
F. Based on the information and observations referred to in Paragraph 3.01.E above, Bidder does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents.
G. Bidder is aware of the general nature of the Work to be performed by Owner and others at the
Site that relates to the Work as indicated in the Bidding Documents.
H. Bidder has given Purchasing Agent written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Purchasing Agent is acceptable to Bidder.
I. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.
J. Bidder will submit written evidence of its authority to do business in the State or other jurisdiction where the Project is located not later than the date of its execution of the
Agreement.
ARTICLE 4 - ATTACHEMENTS TO THIS BID
Revised: February 2026 22
4.01 The following documents are attached to and made a condition of the Bid:
A. Bid Form B. Concept Images for Silverlake Improvements
ARTICLE 5 - BID SUBMITTAL
5.01 This Bid is submitted by:
An Individual
Name (typed or printed): ____________________________________________________
By: _____________________________________________________________________
(Individual’s signature)
Doing business as: _______________________________________________________________
A Partnership
Partnership Name: _________________________________________________________
By: _____________________________________________________________________
(Signature of general partner -- attach evidence of authority to sign)
Name (typed or printed): __________________________________________________________
A Corporation
Corporation Name: _______________________________________________________________
State or Jurisdiction of Incorporation: ______________________________
Type (General Business, Profession, Service, Limited Liability): ___________________________
By: ___________________________________________________________________
(Signature -- attach evidence of authority to sign)
Name (typed or printed): ___________________________________________________________
SEAL,
if required by State
SEAL,
if required by State
CORPORAT
E SEAL,
if required by
State
Revised: February 2026 23
Title: ____________________________________________
Attest ____________________________________________________________
(Signature of Corporate Secretary)
Date of Qualification to do business in ____________ [State or other jurisdiction where Project is located] is ___/___/______
A Joint Venture
Name of Joint Venture: ________________________________________________________
First Joint Venture Name: ____________________________________________________
By: ____________________________________________________________________
(Signature of joint venture partner -- attach evidence of authority to sign)
Name (typed or printed): ____________________________________________________________
Second Joint Venture Name: ____________________________________________________
By: ____________________________________________________________________
(Signature of joint venture partner -- attach evidence of authority to sign)
Name (typed or printed): ____________________________________________________________
(Each joint venturer must sign. The manner of signing for each individual, partnership, and corporation that is party to the venture should be in the manner indicated above.)
5.02 Bid submitted on ______________________________, SEAL, by State
SEAL,
by State
Revised: February 2026 24
ATTACHMENT B
| OVERVIEW |
| I. INTRODUCTION |
| II. SCOPE OF SERVICES |
| III. PROPOSAL EVALUATION CRITERIA |
| IV. PROPOSAL RESPONSE OUTLINE |
| IV. INSURANCE REQUIREMENTS |
| V. TIMELINE |
| VI. ADMINISTRATIVE GUIDANCE |
| VII. ISSUING OFFICE AND RFP REFERENCE NUMBER |
| VIII. SUBMISSION OF PROPOSAL |
| IX. VENDOR PREQUALIFICATION |
| X. INQUIRIES |
| XI. RESPONDENT’S RESPONSIBILITY FOR PROPOSAL COSTS |
| XII. EVALUATION OF PROPOSALS |
| XIII. KEY COMPANY PERSONNEL |
| XIV. ORAL PRESENTATION |
| XV. AWARD OF THE CONTRACT |
| XVI. PROTECTED INFORMATION |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .