This is an AIA Document A132-2019 Standard Form of Agreement between the County of Bucks, Pennsylvania and a contractor for the Emergency Communications Radio Tower HVAC Replacements project (Mechanical Contract Spec #52-11/26). The work encompasses demolition and removal of existing Bard units from building exterior walls, furnishing and installation of new Bard units with all related ductwork connections and controls systems, and all associated power and electrical work. The project spans four sites: Buckwampum Radio Tower, New Hope Radio Tower, Newtown Radio Tower, and Solebury Radio Tower, with bidders required to submit pricing for Unit 1 replacement at each location and alternate pricing for Unit 2 replacement at each location. The contract time for completion is not later than 122 calendar days from the date of commencement, which will be fixed by notice to proceed issued by the County. The Construction Manager is Thomas Newman, P.E., and the Architect/Engineer is Jamie Boles, P.E. of Holstein White, Inc.

The contract is structured as a stipulated sum agreement with base bid and alternate pricing components. Payment terms include progress payments based on applications submitted monthly, with 10 percent retainage until 50 percent of work completion is achieved, at which point retainage reduces to 5 percent, provided written approval is granted by the Architect, Construction Manager, and Owner. Final payment shall be made within 30 days of issuance of the final Certificate for Payment. Liquidated damages are established at $500 per calendar day for delays beyond the contract completion date. The contractor must provide a 100 percent Performance Bond, 100 percent Labor and Materials Payment Bond, and 10 percent Maintenance Bond, along with comprehensive insurance including Commercial General Liability with $2,000,000 General Aggregate Limit, $1,000,000 Each Occurrence Limit, Automobile Liability with $1,000,000 Combined Single Limit, and Workers Compensation at statutory limits. The County of Bucks and associated entities must be named as additional insured on a primary and non-contributory basis. Disputes shall be resolved exclusively through litigation in the Court of Common Pleas of Bucks County.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Document A132® – 2019

AIA Document A132 – 2019. Copyright © 1975, 1980, 1992, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 15:24:02 EST on 11/04/2026 under Subscription No.20240075296 which expires on 11/25/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (6aeb9420c85023b222441751)

ADDITIONS AND DELETIONS:

The author of this document may have revised the text of the original AIA standard form. An Additions and Deletions Report that notes revisions to the standard form text is available from the author and should be reviewed. A vertical line in the left margin of this document indicates where the author has added to or deleted from the original AIA text.

This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.

This document is intended to be used in conjunction with AIA Documents A232™–2019, General Conditions of the Contract for Construction, Construction Manager as Adviser Edition; B132™–2019, Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition; and C132™–2019, Standard Form of Agreement Between Owner and Construction Manager as Adviser.

AIA Document A232™–2019 is adopted in this document by reference. Do not use with other general conditions unless this document is modified.

ADDITIONS AND DELETIONS:

The author of this document may have revised the text of the original AIA standard form. An Additions and Deletions Report that notes revisions to the standard form text is available from the author and should be reviewed. A vertical line in the left margin of this document indicates where the author has added to or deleted from the original AIA text.

This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.

This document is intended to be used in conjunction with AIA Documents A232™–2019, General Conditions of the Contract for Construction, Construction Manager as Adviser Edition; B132™–2019, Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition; and C132™–2019, Standard Form of Agreement Between Owner and Construction Manager as Adviser.

AIA Document A232™–2019 is adopted in this document by reference. Do not use with other general conditions unless this document is modified.

Standard Form of Agreement Between Owner and Contractor, Construction Manager as Adviser Edition

AGREEMENT made as of the ________ day of _________ in the year ________

BETWEEN the Owner:

(Name, legal status, address, and other information)

County of Bucks 55 East Court Street Doylestown, PA 18901 and the Contractor:

(Name, legal status, address, and other information) for the following Project:

Emergency Communications Radio Tower HVAC Replacements Mechanical Contract Spec #52-11/26

The Construction Manager:

Thomas Newman, P.E ., Project Manager County of Bucks

55 East Court Street Doylestown, PA 18901

The Architect/Engineer:

Jamie Boles, P.E.

Holstein White, Inc.

210 East Street Rd., Ste. 2D Feasterville, PA 19053

This document has been prepared and significantly modified by the County of Bucks. Please read in its entirety.

The Owner and Contractor agree as follows.

AIA Document A132 – 2019. Copyright © 1975, 1980, 1992, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 15:24:02 EST on 11/04/2026 under Subscription No.20240075296 which expires on 11/25/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (6aeb9420c85023b222441751)

TABLE OF ARTICLES

1 THE CONTRACT DOCUMENTS

2 THE WORK OF THIS CONTRACT

3 DATE OF COMMENCEMENT AND DATES OF SUBSTANTIAL COMPLETION

4 CONTRACT SUM

5 PAYMENTS

6 DISPUTE RESOLUTION

7 TERMINATION OR SUSPENSION

8 MISCELLANEOUS PROVISIONS

9 ENUMERATION OF CONTRACT DOCUMENTS

AIA Document A132 – 2019. Copyright © 1975, 1980, 1992, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 15:24:02 EST on 11/04/2026 under Subscription No.20240075296 which expires on 11/25/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (6aeb9420c85023b222441751)

ARTICLE 1 THE CONTRACT DOCUMENTS

The Contract Documents consist of the Invitation to Bid, this Agreement, Conditions of the Contract (General, Supplementary, and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. An enumeration of the Contract Documents, other than Modifications, appears in Article 9.

ARTICLE 2 THE WORK OF THIS CONTRACT

The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others.

ARTICLE 3 DATE OF COMMENCEMENT AND DATES OF SUBSTANTIAL COMPLETION

§ 3.1 The date of commencement of the Work shall be:

The date of commencement of the Work shall be the date of this Agreement unless a different date is stated below or provision is made for the date to be fixed in a notice to proceed issued by the County.

The date of commencement will be fixed in a notice to proceed.

If, prior to the commencement of the Work, the County requires time to file mortgages, mechanics’ liens and other security interests, the County’s time requirement shall be as follows:

N/A

§ 3.2 The Contract Time shall be measured from the date of commencement of the Work.

§ 3.3 Substantial Completion of the Project or Portions Thereof § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the date of Substantial Completion of the Work of all of the Contractors for the Project will be:

N/A

§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work of all of the Contractors for the Project are to be completed prior to Substantial Completion of the entire Work of all of the Contractors for the Project, the Contractors shall achieve Substantial Completion of such portions by the following dates:

Portion of Work Substantial Completion Date

§ 3.4 When the Work of this Contract, or any Portion Thereof, is Substantially Complete § 3.4.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall substantially complete the entire Work of this Contract:

Not later than 122 calendar days from the date of commencement of the Work.

By the following date: N/A

§ 3.4.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work of this Contract are to be substantially complete prior to when the entire Work of this Contract shall be substantially complete, the Contractor shall substantially complete such portions by the following dates:

AIA Document A132 – 2019. Copyright © 1975, 1980, 1992, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 15:24:02 EST on 11/04/2026 under Subscription No.20240075296 which expires on 11/25/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (6aeb9420c85023b222441751)

Portion of Work Date to be substantially complete N/A

§ 3.4.3 If the Contractor fails to substantially complete the Work of this Contract, or portions thereof, as provided in this Section 3.4, liquidated damages, if any, shall be assessed as set forth in Section 4.5.

ARTICLE 4 CONTRACT SUM

§ 4.1 The County shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the Contract. The Contract Sum shall be:

Stipulated Sum, in accordance with Section 4.2 below

§ 4.2 Stipulated Sum The Contract Sum shall include:

§ 4.2.1 Base Bid:

Buckwampum Radio Tower-Price to replace Unit 1: $_____________________

New Hope Radio Tower-Price to replace Unit 1: $_____________________

Newtown Radio Tower-Price to replace Unit 1: $_____________________

Solebury Radio Tower-Price to replace Unit 1: $_____________________

§ 4.2.2 Alternates § 4.2.2.1 Alternates, if any, which are described in the Contract Documents and are hereby accepted by the County:

Item Price Buckwampum Radio Tower Add Alternate-Price to replace Unit 2 $___________________

New Hope Radio Tower Add Alternate-Price to replace Unit 2 $___________________

Newtown Radio Tower Add Alternate-Price to replace Unit 2 $___________________

Solebury Radio Tower Add Alternate-Price to replace Unit 2 $___________________

§ 4.2.3 Allowances § 4.2.3.1 Allowances, if any, included in the Contract Sum:

Item Price N/A N/A

§ 4.2.4 Unit Prices § 4.2.4.1 Unit prices, if any:

Item Units and Limitations Price per Unit ($0.00) N/A N/A

§ 4.3 <Reserved for Cost of the Work Plus Contractor’s Fee without a Guaranteed Maximum Price>

§ 4.4 <Reserved for Cost of the Work Plus Contractor’s Fee

AIA Document A132 – 2019. Copyright © 1975, 1980, 1992, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 15:24:02 EST on 11/04/2026 under Subscription No.20240075296 which expires on 11/25/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (6aeb9420c85023b222441751) with a Guaranteed Maximum Price>

§ 4.5 Liquidated Damages § 4.5.1 Liquidated damages, if any:

It is mutually agreed that damages to the County for failure of the Contractor to fully complete the work under this Contract on or before the stipulated date/time within the Contract shall be $500 (five hundred dollars) for each calendar day after said date that shall elapse before the work is fully completed, which amount shall in no event be considered as a penalty, but as liquidated damages due the County because of said delay. The County may retain the amount thereof from any moneys which otherwise would be payable hereunder to the Contractor.

§ 4.6 The Total Stipulated Sum (Base Bid, Alternates and Allowance(s)) as identified above is:

Total Stipulated Sum: ___________________________________________________________________________ ($ ___________________ ), subject to additions and deletions as provided in the Contract Documents.

ARTICLE 5 PAYMENTS

§ 5.1 Progress Payments § 5.1.1 Based upon Applications for Payment submitted to the Construction Manager by the Contractor, and Certificates for Payment issued by the Construction Manager and Architect / Engineer, the County shall make progress payments on account of the Contract Sum, to the Contractor, as provided below and elsewhere in the Contract Documents.

§ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or as follows:

N/A

§ 5.1.3 Provided that an Application for Payment is received by the Construction Manager not later than the 20th day of a month, the County shall make payment of the amount certified to the Contractor not later than the last day of the following month. If an Application for Payment is received by the Construction Manager after the application date fixed above, payment of the amount certified shall be made by the County not later than 40 days after the Construction Manager receives the Application for Payment.

§ 5.1.4 Progress Payments Where the Contract Sum is Based on a Stipulated Sum § 5.1.4.1 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work. The schedule of values shall be prepared in such form, and supported by such data to substantiate its accuracy, as the Construction Manager and Architect / Engineer may require. This schedule of values shall be used as a basis for reviewing the Contractor’s Applications for Payment.

§ 5.1.4.2 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment.

§ 5.1.4.3 In accordance with AIA Document A232™–2019, General Conditions of the Contract for Construction, Construction Manager as Adviser Edition, and subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:

§ 5.1.4.3.1 The amount of each progress payment shall first include:

.1 That portion of the Contract Sum properly allocable to completed Work;

AIA Document A132 – 2019. Copyright © 1975, 1980, 1992, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 15:24:02 EST on 11/04/2026 under Subscription No.20240075296 which expires on 11/25/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (6aeb9420c85023b222441751)

.2 That portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction, or, if approved in advance by the County, suitably stored off the site at a location agreed upon in writing; and

.3 That portion of Construction Change Directives that the Architect / Engineer determines, in the Architect’s professional judgment, to be reasonably justified.

§ 5.1.4.3.2 The amount of each progress payment shall then be reduced by:

.1 The aggregate of any amounts previously paid by the County;

.2 The amount, if any, for Work that remains uncorrected and for which the Architect / Engineer has previously withheld a Certificate for Payment as provided in Article 9 of AIA Document A232–2019;

.3 Any amount for which the Contractor does not intend to pay a Subcontractor or material supplier, unless the Work has been performed by others the Contractor intends to pay;

.4 For Work performed or defects discovered since the last payment application, any amount for which the Architect / Engineer may withhold payment, or nullify a Certificate of Payment in whole or in part, as provided in Article 9 of AIA Document A232–2019; and

.5 Retainage withheld pursuant to Section 5.1.4.4.

§ 5.1.4.4 Reduction or limitation of retainage, if any, shall be as follows:

§ 5.1.4.4.1 Payment under this Contract shall be subject to a retainage of ten percent (10%) of the amount due the Contractor until fifty percent (50%) of the Work required by the Contract is completed at which time one half of the retainage will be returned to the Contractor if upon written request to the Architect, CM and Owner their approval is granted to this reduction in retainage. After fifty percent (50%) of the Work required by the Contract is completed, the retainage shall be reduced from ten percent (10%) to five percent (5%) of the value of completed work based on monthly progress payment requests.

§ 5.1.4.4.2 However, in the event a dispute arises between County and the Contractor, which dispute is based upon increased costs claimed by Other Contractors occasioned by delays or other actions of this Contractor, additional retainage in the sum of one and one half (1 ½) times the amount of any possible liability may be withheld until such time as a final resolution is agreed to by all parties directly or indirectly involved, unless the Contractor causing the additional claim furnishes a bond satisfactory to County to indemnify the County against the claim. However, all such monies retained by County may be withheld from the Contractor until Substantial Completion of the Contract.

§ 5.1.4.4.3 N/A

§ 5.1.5 <Reserved for Progress Payments Where the Contract Sum is Based on the Cost of the Work without a Guaranteed Maximum Price>

§ 5.1.6 <Reserved for Progress Payments Where the Contract Sum is Based on the Cost of the Work with a Guaranteed Maximum Price>

§ 5.2 Final Payment § 5.2.1 Final Payment Where the Contract Sum is Based on a Stipulated Sum § 5.2.1.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the County to the Contractor when

.1 the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct Work as provided in Article 12 of AIA Document A232–2019, and to satisfy other requirements, if any, which extend beyond final payment; and

.2 the Contractor has submitted a final accounting for the Cost of the Work, Determination of the Cost of the Work when payment is on the basis of the Cost of the Work, with or without a Guaranteed Maximum payment; and

.3 a final Certificate for Payment or Project Certificate for Payment has been issued by the Architect / Engineer; such final payment shall be made by the County no later than 30 days after the issuance of the final Certificate for Payment or Project Certificate for Payment.

AIA Document A132 – 2019. Copyright © 1975, 1980, 1992, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 15:24:02 EST on 11/04/2026 under Subscription No.20240075296 which expires on 11/25/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (6aeb9420c85023b222441751)

§ 5.2.2 <Reserved for Final Payment Where the Contract Sum is Based on the Cost of the Work without a Guaranteed Maximum Price>

ARTICLE 6 DISPUTE RESOLUTION

§ 6.1 Initial Decision Maker The Architect / Engineer will serve as Initial Decision Maker pursuant to Article 15 of AIA Document A232–2019, unless the parties appoint below another individual, not a party to this Agreement, to serve as Initial Decision Maker.

N/A

§ 6.2 Binding Resolution for Any Unresolved Claims For any Claim subject to, but not resolved by the Initial Decision Maker, the only method of resolution shall be as follows:

Litigation shall be exclusively held in the Court of Common Pleas of Bucks County.

ARTICLE 7 TERMINATION OR SUSPENSION

§ 7.1 Where the Contract Sum is a Stipulated Sum § 7.1.1 The Contract may be terminated by the County or the Contractor as provided in Article 14 of AIA Document A232–2019.

§ 7.1.1.1 If the Contract is terminated for the County’s convenience in accordance with Article 14 of AIA Document A232–2019, then the County shall pay the Contractor a termination fee as follows:

N/A

§ 7.1.2 The Work may be suspended by the County as provided in Article 14 of AIA Document A232–2019.

§ 7.2 <Reserved for Where the Contract Sum is Based on the Cost of the Work with or without a Guaranteed Maximum Price>

ARTICLE 8 MISCELLANEOUS PROVISIONS

§ 8.1 Where reference is made in this Agreement to a provision of AIA Document A232–2019 or another Contract Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract Documents.

§ 8.2 The County’s representative:

Thomas Newman, PE County of Bucks

§ 8.3 The Contractor’s representative:

§ 8.4 Neither the County’s nor the Contractor’s representative shall be changed without 10 days’ prior notice to the other party.

AIA Document A132 – 2019. Copyright © 1975, 1980, 1992, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 15:24:02 EST on 11/04/2026 under Subscription No.20240075296 which expires on 11/25/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (6aeb9420c85023b222441751)

§ 8.5 Insurance and Bonds The Contractor shall purchase and maintain insurance and provide bonds as set forth in Article 11 of AIA Document A232–2019.

100% Performance Bond 100% Labor and Materials Payment Bond 10% Maintenance Bond

The vendor awarded this contract is required to provide a Certificate of Insurance that contains a minimum of the following coverage and limits:

Commercial General Liability - (policy to include premises and operations, products/completed operations and blanket contractual liability- the contractual section of the coverage must cover this agreement and limit applies to a project specific basis) General Aggregate Limit $2,000,000.

Products & Completed Operations Aggregate Limit $2,000,000.

Each Occurrence Limit $1,000,000.

Automobile Liability - to include owned, non-owned and hired vehicles:

Combined Single Limit $1,000,000.

Excess Liability - coverage is to be in an umbrella form, any restrictions or limitations in coverage should be specified on the certificate of insurance:

Each Occurrence $2,000,000.

Aggregate Limit $2,000,000.

Workers Compensation Statutory and Employer's Liability:

Bodily Injury by Accident $ 100,000. ea. accident Bodily Injury by Disease $ 100,000. ea. employee Bodily Injury by Disease $ 500,000. policy limit

Waiver of Subrogation in favor of the County of Bucks, its Board of Commissioners, employees, directors, officers, departments and divisions applies under all policies where allowed by law.

When it applies, Additional Insured shall read: The County of Bucks, its Board of Commissioners, employees, directors, officers, departments and divisions and [as applicable] the Construction Manager, Architect/Engineer and their employees, directors, and officers shall be included as additional insured on a primary and non-contributory basis with respect to the work performed for this contract: Emergency Communications Radio Tower HVAC Replacements; Spec #52-11/26.

Cancellation Clause shall read: Should any of the above-described policies be cancelled before the expiration date thereof, notice will be delivered in accordance with the policy provisions.

Certificate Holder - County of Bucks Board of Commissioners, Attn: Office of the Controller, 55 East Court St, Doylestown PA 18901.

§ 8.6 Notice in electronic format, pursuant to Article 1 of AIA Document A232–2019, may be given in accordance with AIA Document E203™–2013, Building Information Modeling and Digital Data Exhibit, if completed, or as otherwise set forth below:

N/A

AIA Document A132 – 2019. Copyright © 1975, 1980, 1992, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 15:24:02 EST on 11/04/2026 under Subscription No.20240075296 which expires on 11/25/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (6aeb9420c85023b222441751)

§ 8.7 Relationship of the Parties Where the Contract is based on the Cost of the Work plus the Contractor’s Fee, with or without a Guaranteed Maximum Price, the Contractor accepts the relationship of trust and confidence established by this Agreement and covenants with the County to cooperate with the Architect / Engineer and exercise the Contractor’s skill and judgment in furthering the interests of the County; to furnish efficient business administration and supervision; to furnish at all times an adequate supply of workers and materials; and to perform the Work in an expeditious and economical manner consistent with the County’s interests. The County agrees to furnish and approve, in a timely manner, information required by the Contractor and to make payments to the Contractor in accordance with the requirements of the Contract Documents.

§ 8.8 Other provisions:

N/A

ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS

§ 9.1 This Agreement is comprised of the following documents and those documents referenced therein:

.1 AIA Document A132™–2019, Standard Form of Agreement Between County and Contractor, Construction Manager as Adviser Edition

.2 AIA Document A232™–2019, General Conditions of the Contract for Construction, Construction Manager as Adviser Edition

.3 Drawings

Number Title Date See Invitation to Bid

.4 Specifications

Section Title Date Pages See Invitation to Bid

.5 Addenda, if any:

Number Date Pages

Portions of Addenda relating to bidding or proposal requirements are not part of the Contract Documents unless the bidding or proposal requirements are also enumerated in this Article 9.

6 Additional documents, if any, forming part of the Contract Documents are listed below:

AIA Document A151 – 2019. Copyright © 2003, 2007, and 2019. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 10:54:08 EDT on 03/16/2026 under Subscription No.20240075296 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (640e2aeef442e4498d096842)

This Agreement entered into as of the day and year first written above.

COUNTY OF BUCKS CONTRACTOR

BOARD OF COMMISSIONERS

Diane M. Ellis-Marseglia, LCSW, Chair (Signature)

Robert J. Harvie Jr., Vice Chair (Printed name)

Gene DiGirolamo, Secretary (Printed title)

Gail Humphrey, Chief Clerk Date

AIA 132 Signature Page.pdf
Sig.pdf
Signature page.pdf
Signature page.pdf
AIA Signature Page.pdf
TABLE OF ARTICLES
ARTICLE 1 GENERAL PROVISIONS
ARTICLE 2 CONTRACT SUM AND PAYMENTS
ARTICLE 3 TIME
ARTICLE 4 OWNER
ARTICLE 5 VENDOR
ARTICLE 6 TITLE AND RISK OF LOSS
ARTICLE 7 DELIVERY AND INSTALLATION
ARTICLE 8 ACCEPTANCE
ARTICLE 9 WARRANTIES
ARTICLE 10 ARCHITECT
ARTICLE 11 RELATED ACTIVITIES OF OWNER OR OF SEPARATE VENDORS
ARTICLE 12 PROTECTION OF PERSONS AND PROPERTY
ARTICLE 13 INSURANCE AND BONDS
ARTICLE 14 CLAIMS AND DISPUTES
ARTICLE 15 ENUMERATION OF CONTRACT DOCUMENTS
AIA Signature Page.pdf
TABLE OF ARTICLES
ARTICLE 1 GENERAL PROVISIONS
ARTICLE 2 CONTRACT SUM AND PAYMENTS
ARTICLE 3 TIME
ARTICLE 4 OWNER
ARTICLE 5 VENDOR
ARTICLE 6 TITLE AND RISK OF LOSS
ARTICLE 7 DELIVERY AND INSTALLATION
ARTICLE 8 ACCEPTANCE
ARTICLE 9 WARRANTIES
ARTICLE 10 ARCHITECT
ARTICLE 11 RELATED ACTIVITIES OF OWNER OR OF SEPARATE VENDORS
ARTICLE 12 PROTECTION OF PERSONS AND PROPERTY
ARTICLE 13 INSURANCE AND BONDS
ARTICLE 14 CLAIMS AND DISPUTES
ARTICLE 15 ENUMERATION OF CONTRACT DOCUMENTS