This is a Unit Pricing Form (Exhibit B) for a Request for Proposal submitted by the Greater Austin Area Telecommunications Network (GAATN) in Texas for maintenance services related to fiber optic telecommunications networks. The form establishes a comprehensive pricing structure for materials and services that may be required beyond the base annual maintenance work. Contractors are required to submit pricing in Excel format for 125 distinct line items, covering services including fiber placement, conduit installation, tree trimming, pole work, cable management, splicing and testing, underground work, removal and installation of various network components, labor categories, and specialized services such as traffic control and permitting. The pricing structure applies to both aerial plant and buried plant maintenance activities across GAATN's fiber optic network infrastructure.
All materials required to provide the listed services must be priced at cost plus 15% markup, with approved subcontractor services (including traffic control, engineering, and permitting) also allowed a 15% markup. Contractors must provide purchase receipts to GAATN Network Management to verify compliance with the allowable markup structure. The form includes detailed unit-of-measure designations for each line item, ranging from individual units (EA) to footage (FT), spans, pairs, hours (HR), days (DAY), and lots (LOT). One line item—Special-Delayed or Cancelled Work—includes a fixed price of $500.00. The total cost calculation field indicates this pricing exhibit will be used to establish the contractor's rates for any work orders issued beyond the base contract maintenance requirements, ensuring transparent and consistent pricing throughout the contract term.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
EXHIBIT B: UNIT PRICING FORM
| The following is a list of materials and services which may be required above and beyond the Base Annual Maintenance Work. |
| Contractor shall provide pricing and submit Exhibit B with the proposal in excel format. |
| Pricing shall include labor, delivery, storage, overhead, markup, etc. |
| CONTRACTOR ALLOWABLE MARKUP: | |||||
| All materials needed to provide the items mentioned below should be priced at cost plus 15%. All approved subcontractor | |||||
| services, such as traffic control, engineering, and permitting have an allowable markup of 15%. The GAATN Network Manager will | |||||
| require Contractor's purchase receipts in order to confirm the contractor is complying with proper markup. | |||||
| Line # | Description | Unit of Measure | Quantity | Line Item Cost | Extended Cost |
| 1 | All approved subcontractor services, such as traffic control, engineering, and permitting have an allowable markup of 15%. Network Management will require Contractor’s purchase receipts in order to confirm the contractor is complying with proper markup. | FT | 1 | ||
| 2 | Place New Fiber, Lashed (not ABV), 1-1000' | FT | 1 | ||
| 3 | Place New Fiber, Lashed (ABV), over 1000' | FT | 1 | ||
| 4 | Place New Fiber, Lashed (not ABV), over 1000' | FT | 1 | ||
| 5 | J-Hook Poles to temp. Cable | EA | 1 | ||
| 6 | Place 1-3”-3 cell fabric innerducts in Existing Conduit, 1-1000’ | FT | 1 | ||
| 7 | Place 1-3”-3 cell fabric innerducts Existing Conduit, over 1001’ | FT | 1 | ||
| 8 | Place New Fiber Cable in Existing Conduit or DOM, 1-1000' | FT | 1 | ||
| 9 | Place New Fiber Cable in Existing Conduit or DOM, over 1001' | FT | 1 | ||
| 10 | Place new DOM/Strand | FT | 1 | ||
| 11 | Overlash New Fiber to Existing | FT | 1 | ||
| 12 | Replace Underground Conduit | FT | 1 | ||
| 13 | Place New Underground Conduit | FT | 1 | ||
| 14 | Trim Trees, Individual Spans (ABV) | SPAN | 1 | ||
| 15 | Trim Trees, Consecutive Spans (ABV) | SPAN | 1 | ||
| 16 | Trim Trees, Individual Spans (not ABV) | SPAN | 1 | ||
| 17 | Trim Trees, Consecutive Spans (not ABV) | SPAN | 1 | ||
| 18 | Place or Replace Tree Guard | EA | 1 | ||
| 19 | ½" Penetration thru Masonry | EA | 1 | ||
| 20 | ½" Penetration thru Siding/Sheetrock | EA | 1 | ||
| 21 | 2 or 4 inch core thru masonry/non-tensioned concrete | EA | 1 | ||
| 22 | 2 or 4 inch core thru post-tensioned concrete (requires x-ray) | EA | 1 | ||
| 23 | Place Fiber thru EMT, 1-200' | FT | 1 | ||
| 24 | Place Fiber thru EMT, over 201' | FT | 1 | ||
| 25 | Place 19" or 23" Bolt-down Rack, grounding, power strip | EA | 1 | ||
| 26 | Place Free-standing Rack + sides + fans, grounding, power strip | EA | 1 | ||
| 27 | Place Light guide Box + 6 packs in rack | EA | 1 | ||
| 28 | Place Light guide Box + 6 packs on wall | EA | 1 | ||
| 29 | Place Polished SC, ST and or LC connector/Terminate SM Fiber | EA | 1 | ||
| 30 | Hang or Rehang splice case | EA | 1 | ||
| 31 | Place or Replace Loopers (Slack Mgmt Brackets) | PAIR | 1 | ||
| 32 | Place or Replace Tie Wraps (Slack Coil) | EA | 1 | ||
| 33 | Place Extension Bracket | EA | 1 | ||
| 34 | Fusion Splice HLC Pigtails | EA | 1 | ||
| 35 | Fusion Splice Single Mode Fiber | EA | 1 | ||
| 36 | Test and Install Jumpers | EA | 1 | ||
| 37 | Bi-Directional OTDR Testing (node to node) | STRAND | 1 | ||
| 38 | Bi-Directional Power Meter Testing (node to node) | STRAND | 1 | ||
| 39 | Troubleshoot Fiber, Isolate Problem | HR | 1 | ||
| 40 | Transfer In-line Cable | EA | 1 | ||
| 41 | Pole Make Ready | EA | 1 | ||
| 42 | Contact Steel Pole 40'/60' | EA | 1 | ||
| 43 | Contact In-line Pole | EA | 1 | ||
| 44 | Contact Side-guyed Pole | EA | 1 | ||
| 45 | Transfer Cable at Deadend Pole | EA | 1 | ||
| 46 | Transfer Down or Overhead Guy | EA | 1 | ||
| 47 | Transfer False Deadend Pole | EA | 1 | ||
| 48 | Transfer Extension Bracket | EA | 1 | ||
| 49 | Transfer Riser Cable & U-guard | EA | 1 | ||
| 50 | Transfer 90 degree Bend with Cable | EA | 1 | ||
| 51 | Transfer 90 degree Bend only | EA | 1 | ||
| 52 | Transfer 90 degree Bend w/Cable & Conc. Cap | EA | 1 | ||
| 53 | Transfer 90 degree Bend Only w/Concrete Cap | EA | 1 | ||
| 54 | Transfer Sidewalk Guy | EA | 1 | ||
| 55 | Top Pole | EA | 1 | ||
| 56 | Unlash/Relash Broken Lashing Wire | SPAN | 1 | ||
| 57 | Rehoist Low cable span | SPAN | 1 | ||
| 58 | Strand Splice | EA | 1 | ||
| 59 | Rework Slack, Loopers | EA | 1 | ||
| 60 | Relocate Slack, Lashed Cable | SPAN | 1 | ||
| 61 | Slack Mgmt to support repair or construction activity (drop or rehang) | HR | 1 | ||
| 62 | Rework or Remove Loopers (Slack Mgmt Brackets) | PAIR | 1 | ||
| 63 | Remove Guy and Anchor | EA | 1 | ||
| 64 | Remove Guy Only | EA | 1 | ||
| 65 | Delash Cable | SPAN | 1 | ||
| 66 | Delash Slack | FT | 1 | ||
| 67 | Remove/Replace Strand | FT | 1 | ||
| 68 | Remove Strand, 1000' minimum | FT | 1 | ||
| 69 | Remove Cable + Strand, 1000' minimum | FT | 1 | ||
| 70 | Remove Self-supporting Cable, 1000' minimum | FT | 1 | ||
| 71 | Remove Self-support Cable and DOM | FT | 1 | ||
| 72 | Remove Cable from Building | FT | 1 | ||
| 73 | Remove Cable via Unlashing, 1-1000' | FT | 1 | ||
| 74 | Remove Cable via Unlashing, over 1001' | FT | 1 | ||
| 75 | Remove Pole (30’)(35') (40') | EA | 1 | ||
| 76 | Remove cable from DOM | FT | 1 | ||
| 77 | Remove UG Cable to Clear Duct | FT | 1 | ||
| 78 | Remove Cable and Install Pull String | FT | 1 | ||
| 79 | Misc. Removal (as in shoes or a foreign attachment) | EA | 1 | ||
| 80 | Remove Pole (30’)(35') (40') | EA | 1 | ||
| 81 | Place or Replace Hardware | LOT | 1 | ||
| 82 | Place or Replace Anchor w ½" Rod | EA | 1 | ||
| 83 | Hand Dig New Anchor | EA | 1 | ||
| 84 | Place New or Replace Overhead Guy | FT | 1 | ||
| 85 | Place, Replace or Rehoist Down Guy | EA | 1 | ||
| 86 | Place or Replace Guy Guard | EA | 1 | ||
| 87 | Place New or Replace Sidewalk Guy | EA | 1 | ||
| 88 | Place New Strand, 1-1000' with hardware | FT | 1 | ||
| 89 | Place New Strand, over 1001' with hardware | FT | 1 | ||
| 90 | Place New Riser | EA | 1 | ||
| 91 | Place or Replace Riser Guard | EA | 1 | ||
| 92 | Place or Replace ground rod | EA | 1 | ||
| 93 | Place grounding/bonding material | FT | 1 | ||
| 94 | Restore Concrete or Cold Patch Asphalt | SQ FT | 1 | ||
| 95 | Cleat Cable to Building, 1-500' | FT | 1 | ||
| 96 | Cleat Cable to Building, over 501' | FT | 1 | ||
| 97 | Install Fiber Markers | EA | 1 | ||
| 98 | Place Pole Tag (up to 1,000 included base contract) | EA | 1 | ||
| 99 | Splice Case Audit, Labeling, Documentation | SPL CASE | 1 | ||
| 100 | Field and Design (Limited) | HR | 1 | ||
| 101 | Field, Design, Permit | LOT | 1 | ||
| 102 | Administrative Support (Legal, Claims) | HR | 1 | ||
| 103 | Executive Production of Documents/Overview | HR | 1 | ||
| 104 | Supervisor Labor | HR | 1 | ||
| 105 | Lineman Labor | HR | 1 | ||
| 106 | Three (3)-man line crew | HR | 1 | ||
| 107 | Bucket Truck Usage | LOT | 1 | ||
| 108 | Data Compilation (Research, claims) | HR | 1 | ||
| 109 | Site Visit | HR | 1 | ||
| 110 | Special-Delayed or Cancelled Work | EA | 1 | $500.00 | |
| 111 | Rack and ID cable in manhole | EA | 1 | ||
| 112 | Traffic Control - simple | DAY | 1 | ||
| 113 | Traffic Control - intermediate | LOT | 1 | ||
| 114 | Traffic Control - elaborate | LOT | 1 | ||
| 115 | Permit - simple | LOT | 1 | ||
| 116 | Permit - intermediate | LOT | 1 | ||
| 117 | Permit - elaborate | LOT | 1 | ||
| 118 | Repair/Replace Manhole Ring/Cover | EA | 1 | ||
| 119 | Locate Request/Response | HR | 1 | ||
| 120 | Hwy Closing with Police Support | HR | 1 | ||
| 121 | Rolling Lane Closure | LOT | 1 | ||
| 122 | Adm. Fees/records | LOT | 1 | ||
| 123 | Project Manager Hourly Rate | HR | 1 | ||
| 124 | Emergency Repair Call Out Fee (2hrs) | LOT | 1 | ||
| 125 | NJUNs Priority 1 Ticket Call Out Fee (1 business day) | LOT | 1 | ||
| TOTAL COST FOR 1 UNIT OF EACH ITEM | $0.00 |