The document is a Schedule of Items for the M2 Pavement Patching project at Mendocino National Forest, Grindstone Ranger District. The schedule outlines five line items with their corresponding measurement methods (MM), units, and quantities: 1) Mobilization (1 LS), 2) Erosion Control (1 LS), 3) Pavement Removal (220 SY), 4) AC Pavement Patching, Type 2, Grade 1/2" (220 SY), and 5) Temporary Traffic Control (1 LS). All items are coded with a "CQ" measurement method and have placeholder unit prices, indicating this is a preliminary pricing structure for the roadway maintenance project. The quantities suggest a focused scope of work involving surface layer removal, preparation, and patch placement along a specific road segment within the national forest.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 5. Drawings 11x17.pdf | ||
| 2. Sources Sought (Market Survey).pdf | ||
| 1. SF 1442 - 127EAW25R0034 (NRE Included).pdf | ||
| 4. Site Plan.pdf | ||
| 9. SAM.gov Q&A.xlsx | XLSX spreadsheet | |
| 8. Davis-Bacon Act WD # CA20250007 (Tehama County).pdf | ||
| 6. FP-14.pdf | ||
| 7. Evaluation Factors.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
08-CON-M2 PAVEMENT PATCHING - Schedule of Items
Item Description MM Unit Qnty Unit Price Cost
151-01 Mobilization CQ LS 1
157-02 Erosion Control CQ LS 1
413-01 Pavement Removal CQ SY 220
418-01 AC pavement patching, Type: 2, Grade: 1/2" CQ SY 220
635-01 Temporary Traffic Control CQ LS 1
TOTAL