3. Schedule.docx

DOCX document 21 KB Posted

Attached to
127EAW22R0035 - Valhalla & Kiva Parking Lot
Solicitation number
127EAW22R0035
Issued by

About this file

This document contains a schedule of items and notes for a construction project solicitation from the Forest Service. The solicitation seeks bids for work on the Valhalla and Kiva parking lots in the Lake Tahoe Basin Management Unit, including a base scope of work and two option items. The estimated value is between $250,000 and $500,000. The schedule of items lists the construction items required along with estimated quantities, units, unit prices, and total prices. The base work includes items such as clearing and grubbing, excavation, aggregate base, asphalt paving, signage, and traffic control. Option 1 adds additional related items such as pavement removal and markings. Option 2 involves further minor roadwork and drainage. Bids are due by May 12, 2022. The work must be completed for the Forest Service in accordance with the specifications.

View the file

Other files

File Type Posted
RFI Official Responses - 2.pdf PDF
A00002 - RFIs and Time Extension.pdf PDF
RFI Official Responses 1.pdf PDF
A00001 - RFIs.pdf PDF
7. RFI Form.docx DOCX document
1. Statement of Work.pdf PDF
2. Fire Plan.pdf PDF
4. Drawings.pdf PDF
6. Davis-Bacon Act WD # CA20220007.pdf PDF
127EAW22R0035.pdf PDF
5. Forest Service Supplemental Specifications.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART I—THE SCHEDULE

SECTION B-- SCHEDULE OF ITEMS

B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)

Item
Construction Items
Qty
UNIT
Unit Price
Total Price
15101
Mobilization
1
L.S.
$
$
15201
Construction Survey and Staking, method 2
1
L.S.
$
$
20104
Clearing and Grubbing, Disposal Method (a)
0.79
Acre
$
$
20207
Removal of Individual Trees, disposal method (FS Permit)
29
Each
$
$
20301
Pavement Removal, Disposal Method (a)
400
S.Y.
$
$
20401
Roadway excavation, compaction method B, finishing method A
350
C.Y.
$
$
20425A
Drainage Excavation, Sediment Basin
3
Each
$
$
20425B
Drainage Excavation, Swale Ditch
675
L.F.
$
$
30102
Aggregate Base - CalTrans 3/4" Class 2, Compaction D
620
Ton
$
$
40304
Asphalt Concrete, CalTrans 1/2" 'B' Type PG64-22
485
Ton
$
$
40305
Asphalt Concrete, CalTrans 1/2" 'A' Type PG64-28PM w/ 0.25% Ad-Here XL-9000 LAS
300
Ton
$
$
61905
Relocate Existing Boulders
31
Each
$
$
63302
Sign System and Installation
9
Each
$
$
63304
Install Camera Pole
8
Each
$
$
63401
Pavement Markings, Solid Line (4"), Type B
2625
L.F.
$
$
63405
Pavement Markings, Accessible Symbol
3
Each
$
$
63501
Temporary Traffic Control
1
L.S.
$
$
63606
Conduit, 2-inch, Schedule 40 PVC
130
L.F.
$
$
63610
Pull Box
2
Each
$
$
BASE TOTAL:
$___________

B.1 SCHEDULE OF ITEMS – OPTION 1

Item
Construction Items
Qty
UNIT
Unit Price
Total Price
15101-OP1
Mobilization
L.S.
1
$
$
15201-OP1
Construction Survey and Staking, method 2
L.S.
1
$
$
20104-OP1
Clearing and Grubbing, Disposal Method (a)
Acre
0.18
$
$
20207-OP1
Removal of Individual Trees, disposal method (FS Permit)
Each
7
$
$
20301-OP1
Pavement Removal, Disposal Method (a)
S.Y.
95
$
$
20401-OP1
Roadway excavation, compaction method B, finishing method A
C.Y.
60
$
$
30102-OP1
Aggregate Base - CalTrans 3/4" Class 2, Compaction D
Ton
160
$
$
40304-OP1
Asphalt Concrete, CalTrans 1/2" 'B' Type PG64-22
Ton
115
$
$
60405
24"x14" Utility Box Adjustment, replace w/ traffic rated
L.S.
1
$
$
63302-OP1
Sign System and Installation
Each
6
$
$
63401-OP1
Pavement Markings, Solid Line (4"), Type B
L.F.
1610
$
$
63501-OP1
Temporary Traffic Control
L.S.
1
$
$
OPTION 1 TOTAL:
$___________

B.1 SCHEDULE OF ITEMS – OPTION 2

Item
Construction Items
Qty
UNIT
Unit Price
Total Price
15101-OP2
Mobilization
L.S.
1
$
$
15201-OP2
Construction Survey and Staking, method 2
L.S.
1
$
$
20301-OP2
Pavement Removal, Disposal Method (a)
S.Y.
0.11
$
$
20207-OP2
Removal of Individual Trees, disposal method (FS Permit)
Each
4
$
$
20401-OP2
Roadway excavation, compaction method B, finishing method A
C.Y.
40
$
$
30102-OP2
Aggregate Base - CalTrans 3/4" Class 2, Compaction D
Ton
90
$
$
40304-OP2
Asphalt Concrete, CalTrans 1/2" 'B' Type PG64-22
Ton
65
$
$
60105
Install Concrete Valley Gutter
Each
1
$
$
63302-OP2
Sign System and Installation
Each
9
$
$
63401-OP2
Pavement Markings, Solid Line (4"), Type B
L.F.
710
$
$
63501-OP2
Temporary Traffic Control
L.S.
1
$
$
OPTION 2 TOTAL:
$___________
BASE + OPTION 1 + OPTION 2 TOTAL:
$___________

B.2 SCHEDULE NOTES

* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.

NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

Company Name:
POC & Title:
Email:
Phone Number:
DUNS Number:
Tax ID:

File details come from the government source that posted it. Updated .