About this file

This document is a Geotechnical Engineering Study prepared by Raba Kistner Consultants, Inc. (RKCI) for the City of Round Rock Waste Water Treatment Plant (WWTP) regarding a proposed 2 million gallon ground storage tank project located at 3939 East Palm Valley Boulevard in Round Rock, Texas. The study was conducted on November 19, 2021, and involved subsurface exploration utilizing 7 borings drilled to approximately 20 feet below the existing ground surface, with comprehensive laboratory testing of soil samples to evaluate geotechnical conditions for tank foundation design.

The geotechnical investigation revealed the site is underlain by alluvium deposits overlying Austin Chalk, with soil strata consisting primarily of fat clay and lean clay with varying consistency and gravel content. Groundwater was encountered at depths ranging from 10 to 18 feet during drilling operations. Key recommendations include utilizing a shallow foundation system with select fill replacement to mitigate expansive soil-related movements, implementing specific site drainage and construction considerations, and conducting further geotechnical observation during construction. The report provides detailed guidance on foundation dimensions, bearing pressures, lateral resistance, and site preparation to ensure stable tank infrastructure, with emphasis on managing potential soil-related challenges typical to the central Texas geological region.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM 1

Addendum 5 City of Round Rock February 2024

2 Million Gallon Ground Storage Tank

ADDENDUM

ADDENDUM No. 1

Date __August 15__, __2025__

City of Round Rock, Williamson County

Project Name: 2 Million Gallon Reuse Ground Storage Tank

ID No.: CWST2

This Addendum forms a part of the Contract and corrects or modifies original Proposal

Documents, dated July 31st 2025. Acknowledge receipt of this addendum in space provided on the Proposal Form. Failure to do so may subject bidder to disqualification.

A. Questions and Clarifications:

Bonfire Question 1:

Are you going to post the Geotechnical report from the engineer? Kind of hard to determine elevations of excavation, groundwater encountered, etc, without it

Answer:

Geotechnical report now added to the project manual, as specification 01060 – Geotechnical

Report

B. Project Manual Revisions:

1. Addition of Geotechnical Report

• Insert attached geotechnical report into the project manual, as Specification 01060 –

Geotechnical Report.

This addendum consists of 35 pages.

Approved by OWNER

ADDENDUM 1

Addendum 5 City of Round Rock February 2024

2 Million Gallon Ground Storage Tank

Approved by ENGINEER/ARCHITECT

END OF SECTION

dlacour Stamp

2025-08-15T11:07:41-0500
Rebecca Vento

File details come from the government source that posted it. Updated .