3-CIP-2305 Parris Island 16in Steel Transmission Main Replacement Technical Specifications.pdf

PDF 7 MB Posted

Attached to
CIP-2305 Parris Island (PI) 16-inch Steel Water Transmission Main Replacement (Malecon Drive)
Solicitation number
2026-IFB-019
Issued by
Barnwell County, South Carolina

About this file

CIP-2305 Parris Island 16-Inch Steel Water Transmission Main Replacement Project

This comprehensive technical specification and contract document package is issued by the Beaufort-Jasper Water & Sewer Authority (BJWSA) in Okatie, South Carolina for the CIP-2305 Parris Island 16-inch Steel Water Transmission Main Replacement project on Malecon Drive. The project consists of two phases: Phase I involves installation of approximately 12,200 linear feet of 16-inch polyethylene liner (FFRP) or cured-in-place pipe (CIPP) inside an existing deteriorated 16-inch steel waterline; Phase II includes installation of approximately 1,625 linear feet of 16-inch fusible PVC pipe via horizontal directional drilling (HDD) on both sides of Archer Creek Bridge to replace existing suspended waterlines, plus 170 linear feet of 16-inch PVC installed by open cut. Bids are due by 2:00 PM on March 4, 2026, with bids remaining subject to acceptance for 60 days thereafter. A non-mandatory pre-bid conference is scheduled for February 12, 2026 at 1:30 PM, with site visits available afterward for restricted access areas. The contract will be awarded on a unit price basis with separate pricing required for Base Bid Options 1 (FFRP) and 2 (CIPP) and three alternates. Contract times are 150 calendar days for substantial completion and 180 calendar days for final completion, with liquidated damages of $250 per day for delays.

Bidders must provide bid security equal to 5 percent of their bid amount and submit a Qualifications Statement. The successful bidder will be required to furnish performance and payment bonds each equal to 100 percent of the contract price and maintain comprehensive insurance coverage including commercial general liability of $2,000,000 per occurrence and automobile liability of $1,000,000 combined single limit. Contractors must hold a current South Carolina contractor's license with WL classification. All mobilization and bonds/insurance costs are capped at a maximum of 5 percent of total contract amount, and the contractor is responsible for all costs associated with water provision, temporary facilities, erosion control, testing, traffic control, pavement restoration, and final cleanup. Funding sources and total project budget are not specified in the technical documents provided. The project involves complex rehabilitation and replacement of critical water transmission infrastructure requiring specialized installation methods, certified personnel, and full compliance with AWWA standards, NSF/ANSI 61 potable water requirements, and all applicable federal and state environmental and safety regulations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DOCUMENTS AND

TECHNICAL SPECIFICATIONS

CIP-2305 Parris Island (PI) 16-Inch Steel Water Transmission

Main Replacement (Malecon Drive)

Prepared for:

Beaufort-Jasper

Water & Sewer Authority

KCI Project No:

00030337_001

DECEMBER 2025

ISSUED FOR BIDS

THIS PAGE INTENTIONALLY LEFT BLANK

CIP-2305 Parris Island (PI)

16-Inch Steel Water Transmission Main Replacement

(Malecon Drive)

CONTRACT DOCUMENTS AND

Prepared for the Beaufort-Jasper

Water & Sewer Authority

Okatie, South Carolina

KCI Project No. 00030337_001

December 2025

KCI Project No. 00030337_001 Parris Island 16-Inch Steel Water Transmission Main Replacement

TOC-1 Beaufort-Jasper Water & Sewer Authority

Table of Contents

CONTRACT DOCUMENTS

SECTION TITLE

00020 Advertisement

C-200 Instructions to Bidders

C-410 Bid Form

C-430 Bid Bond

C-451 Qualifications Statement

00501 Contractor Affidavit

C-510 Notice of Award

C-520 Agreement

C-550 Notice to Proceed

C-610 Performance Bond

C-615 Payment Bond

C-620 Pay Application

C-625 Certificate of Substantial Completion

C-626 Notice of Acceptability of Work

C-700 Standard General Conditions

C-800 Supplementary Conditions

C-940 Work Change Directive

C-941 Change Order

C-942 Field Order

DIVISION 1 – GENERAL REQUIREMENTS

01000 General Requirements

01014 Scope And Sequence Of Work

01060 Regulatory Requirements

01061 Permits And Rights-Of-Way

01110 Control Of Work

01220 Project Meetings

01330 Shop Drawings

01400 Measurement And Payment

01500 Temporary Facilities

01562 Dust Control

01640 Product Handling

01740 Cleaning

TOC-2 Beaufort-Jasper Water & Sewer Authority

DIVISION 2 – SITE CONSTRUCTION

02600 Fusible Polyvinyl Chloride (PVC) Pipe for Installation by Horizontal

Directional Drilling (HDD) (Phase II Only)

02665 Fusible Polyvinyl Chloride (PVC) Pipe

02765 Close Fit Cured-In-Place (CIPP) Rehabilitation of Pressurized Potable

Water Mains (Phase I Only)

02770 Flexible Fabric Reinforced Pipe (FFRP) (Phase I Only)

BEAUFORT-JASPER WATER & SEWER AUTHORITY TECHNICAL

SPECIFICATIONS: Reference this information @ www.bjwsa.org (Referenced specification chapters are considered part of the Contract Documents)

CHAPTER 2 EARTHWORK

CHAPTER 3 GRASSING AND SITE RESTORATION

CHAPTER 4 ROADWAY REPAIR AND RESURFACING

CHAPTER 5 PIPELINE DRILLING, BORING AND JACKING (Division 2 Only)

CHAPTER 6 PIPELINE MATERIALS, VALVES, AND APPURTENANCES

CHAPTER 7 WATER SYSTEM STANDARDS

CHAPTER 13 APPROVED MANUFACTURERS

13.1 GENERAL

13.4 WATER

BEAUFORT-JASPER WATER & SEWER AUTHORITY DEVELOPMENT

POLICY AND PROCEDURE MANUAL: Reference this information at https://www.bjwsa.org/DocumentCenter/View/151/Development-Policy-and-Procedure-

Manual-PDF?bidld=

(Referenced sections are considered part of the Contract Documents)

CHAPTER 3 CONSTRUCTION PROCEDURES

(Section 3.4.2 – Worksite Safety)

CHAPTER 4 PROJECT CLOSEOUT PROCEDURES

(Section 4.3 Record Drawing Requirements)

(Section 4.4 Project Closeout Requirements)

END OF SECTION

www.bjwsa.org

SECTION 00020

Advertisement for Bids

Section 00020

ADVERTISEMENT

01000-1 Beaufort-Jasper Water & Sewer Authority

Beaufort-Jasper Water & Sewer Authority Okatie, South Carolina

CIP-2305 Parris Island (PI) 16-inch Steel Water Transmission Main Replacement (Malecon Drive)

INVITATION FOR BIDS

Bids for the construction of the CIP-2305 Parris Island (PI) 16-inch Steel Water Transmission Main Replacement (Malecon Drive) project will be received by Beaufort-Jasper Water & Sewer Authority, located at 6 Snake Road, Okatie, SC 29909, until 2:00 pm local time on March 4, 2026, at which time the Bids received will be publicly opened and read. Submit Bids Electronically at: BJWSA Procurement Portal Responses received after the deadline or at any other location or manner will not be accepted.

The project generally consists of two (2) Phases of Work:

Phase I

Installation of approximately 12,200 linear feet of 16-inch Polyethylene liner inside of an existing 16-inch steel waterline and other related required for complete installation.

Phase II

Installation of approximately 1,625 linear feet of 16-inch fusible PVC installed by horizontal directional drill (HDD) on both sides of Archer Creek Bridge to replace and existing 16-inch waterlines suspended from the Bridge and 170 linear feet of 16-inch PVC installed by open cut.

Bids will be received for a single prime Contract. Bids shall be on a unit price basis as indicated on the Bid Form.

Deadline for Good Faith Effort Written Notice Requirement is 8:00 am local time on February 17, 2026.

A non-mandatory pre-bid conference will be held by Beaufort-Jasper Water & Sewer Authority, located at 6 Snake Road, Okatie, SC 29909, starting at 1:30 PM local time on February 12th, 2026. At the conclusion of the meeting, anyone wishing to visit the site that lies beyond the MCRD gates will be escorted by BJWSA to view the restricted access portion of the work. Questions regarding the bid are to be submitted before 5:00 PM local time on February 19th, 2026. Questions must be submitted electronically at: BJWSA Procurement Portal.

Only those contract drawings, specifications, and bid documents obtained from https://bjwsa.bonfirehub.com are official. Bidders cannot rely on the accuracy of copies of the aforementioned documents, drawings, specifications, etc. obtained from any other source.

Bidders must deposit security with all bids. Security shall be in the form of a bid bond made payable to the Beaufort-Jasper Water & Sewer Authority (BJWSA) and shall be for an amount equal to not less than five percent (5%) of the amount of the bid. Provisions of the security shall be as described in the Information for Bidders.

Performance and Payment Bonds, each in the amount of 100% of the contract price will be required of the successful bidder.

No bid will be considered unless the bidder is legally qualified under the provisions of the South Carolina Contractor's Licensing Law (South Carolina Code of Laws as amended on April 1, 1999, Chapter 11, Sections 40-11-10 through 40-11-428). Contractors shall have a classification of WL.

https://url.us.m.mimecastprotect.com/s/00YjCxk71pTrxQ6nI8fAHyL8iu?domain=bjwsa.bonfirehub.com/ https://url.us.m.mimecastprotect.com/s/00YjCxk71pTrxQ6nI8fAHyL8iu?domain=bjwsa.bonfirehub.com/ https://url.us.m.mimecastprotect.com/s/00YjCxk71pTrxQ6nI8fAHyL8iu?domain=bjwsa.bonfirehub.com/ https://bjwsa.bonfirehub.com/

01000-2 Beaufort-Jasper Water & Sewer Authority

Owner reserves the right to waive any irregularities, or to reject any or all bids. Bids may be held by the Owner for a period not to exceed ninety (90) days from the date of the opening of bids.

+ + END OF ADVERTISEMENT FOR BIDS + +

01000-3 Beaufort-Jasper Water & Sewer Authority

SECTION C-200

Instructions to Bidders

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

TOC Page1 of 1

1.01 INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT

TABLE OF CONTENTS

Page

Article 1— Defined Terms

Article 2— Bidding Documents

Article 3— Qualifications of Bidders

Article 4— Pre-Bid Conference

Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

Article 6— Bidder’s Representations and Certifications

Article 7— Interpretations and Addenda

Article 8— Bid Security

Article 9— Contract Times

Article 10— Substitute and “Or Equal” Items

Article 11— Subcontractors, Suppliers, and Others

Article 12— Preparation of Bid

Article 13— Basis of Bid

Article 14— Submittal of Bid

Article 15— Modification and Withdrawal of Bid

Article 16— Opening of Bids

Article 17— Bids to Remain Subject to Acceptance

Article 18— Evaluation of Bids and Award of Contract

Article 19— Bonds and Insurance

Article 20— Signing of Agreement

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 2—DEFINED TERMS

2.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office—The office from which the Bidding Documents are to be issued, and which registers plan holders.

ARTICLE 3—BIDDING DOCUMENTS

3.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.

3.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.

3.03 Plan rooms (including construction information subscription services, and electronic and virtual plan rooms) may distribute the Bidding Documents, or make them available for examination.

Those prospective bidders that obtain an electronic (digital) copy of the Bidding Documents from a plan room are encouraged to register as plan holders from the Bidding Documents Website or Issuing Office. Owner is not responsible for omissions in Bidding Documents or other documents obtained from plan rooms, or for a Bidder’s failure to obtain Addenda from a plan room.

3.04 Electronic Documents

A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.

1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader Version 8.0 or later. It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.

B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.06.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.

ARTICLE 4—QUALIFICATIONS OF BIDDERS

4.01 Form EJCDC® C-451, Qualifications Statement (2018) demonstrating Bidder’s qualifications to perform the Work may be requested from the apparent responsive low bidder as deemed necessary by the Owner.

4.02 Failure to submit required qualification information within the time indicated by the Owner may disqualify Bidder from receiving an award of the Contract.

4.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

ARTICLE 5—PRE-BID CONFERENCE

5.01 A non-mandatory pre-bid conference will be held on Thursday, January 8th, 2026 at BJWSA’s main office followed by a non-mandatory site visit.

ARTICLE 6—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

6.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

6.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:

a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.

b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.

c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.

6.03 Other Site-related Documents

A. No other Site-related documents are available.

6.04 Site Visit and Testing by Bidders

A. Bidder may visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.

B. Bidders visiting the Site are required to arrange their own transportation to the Site.

C. Bidder must conduct the required Site visit during normal working hours.

D. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

E. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

6.05 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.

6.06 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 7—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

7.01 Express Representations and Certifications in Bid Form, Agreement

A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.

B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.

ARTICLE 8—INTERPRETATIONS AND ADDENDA

8.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.

8.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents through Bonfire.

8.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date for opening of Bids may not be answered.

8.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.

ARTICLE 9—BID SECURITY

9.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 5% percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.

9.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.

9.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

9.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.

ARTICLE 10—CONTRACT TIMES

10.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.

10.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

ARTICLE 11—SUBSTITUTE AND “OR EQUAL” ITEMS

11.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.

11.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 12—SUBCONTRACTORS, SUPPLIERS, AND OTHERS

12.01 A Bidder must be prepared to retain specific Subcontractors and Suppliers for the performance of the Work if required to do so by the Bidding Documents or in the Specifications. If a prospective Bidder objects to retaining any such Subcontractor or Supplier and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.

12.02 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work within five days after Bid opening:

A. Directional Drilling

B. Jack and Boring

C. Traffic Control

12.03 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder will submit a substitute, Bidder’s Bid price will be increased (or decreased) by

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.

12.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.

Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.

ARTICLE 13—PREPARATION OF BID

13.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

13.02 If Bidder has obtained the Bidding Documents as Electronic Documents, then Bidder shall prepare its Bid on a paper copy of the Bid Form printed from the Electronic Documents version of the Bidding Documents. The printed copy of the Bid Form must be clearly legible, printed on 8½ inch by 11-inch paper and as closely identical in appearance to the Electronic Document version of the Bid Form as may be practical. The Owner reserves the right to accept Bid Forms which nominally vary in appearance from the original paper version of the Bid Form, providing that all required information and submittals are included with the Bid.

13.03 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.

13.04 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.

13.05 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.

13.06 A Bid by an individual must show the Bidder’s name and official address.

13.07 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.

13.08 All names must be printed in ink below the signatures.

13.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

13.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.

13.11 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.

13.12 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.

ARTICLE 14—BASIS OF BID

14.01 Base Bid with Alternates

A. Bidders must submit a Bid on a lump sum basis for the base Bid and include a separate price for each alternate described in the Bidding Documents and as provided for in the Bid Form.

The price for each alternate will be the amount added to or deleted from the base Bid if Owner selects the alternate.

B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form.

14.02 Unit Price

A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

ARTICLE 15—SUBMITTAL OF BID

15.01 The Bidding Documents include one separate unbound copy of the Bid Form, and, if required, the Bid Bond Form. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the other documents required to be submitted under the terms of Article 2 of the Bid Form.

15.02 A Bid must be received no later than the date and time prescribed and at the place indicated in the Advertisement or invitation to bid.

15.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 16—MODIFICATION AND WITHDRAWAL OF BID

16.01 An unopened Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.

16.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 15.01 and submit a new Bid prior to the date and time for the opening of Bids.

16.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, the Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.

ARTICLE 17—OPENING OF BIDS

17.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 18—BIDS TO REMAIN SUBJECT TO ACCEPTANCE

18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 19—EVALUATION OF BIDS AND AWARD OF CONTRACT

19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.

19.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

19.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.

19.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.

19.05 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

B. At its sole discretion, Owner will award the Contract based on the selection of Base Bid of the lowest responsive bid between Option 1 or Option 2 and any combination of Alternates, depending on what is determined to be in the best interest of the project and the Owner. To be considered responsive, Bidders should ensure that all pricing and documentation for both the Base Bid Options and each of the Alternates are complete and accurate, as all Alternates may be selected for award. Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 20—BONDS AND INSURANCE

20.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.

20.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.

ARTICLE 21—SIGNING OF AGREEMENT

21.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.

SECTION C-410

Bid Form

EJCDC® C-410, Bid Form for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

BID FORM

Beaufort-Jasper Water & Sewer Authority CIP-2305 Parris Island (PI) 16-inch Steel Water

Transmission Main Replacement (Malecon Drive)

The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.

ARTICLE 1—OWNER AND BIDDER

1.01 This Bid is submitted to: Beaufort-Jasper Water & Sewer Authority

6 Snake Road, Okatie, SC 29909

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2—ATTACHMENTS TO THIS BID

2.01 The following documents are submitted with and made a condition of this Bid:

A. Required Bid security;

B. List of Proposed Subcontractors;

C. List of Proposed Suppliers;

D. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such authority within the time for acceptance of Bids; and, E. Contractor’s license number as evidence of Bidder’s State Contractor’s License or a covenant by Bidder to obtain said license within the time for acceptance of Bids.

ARTICLE 3—BASIS OF BID—LUMP SUM BID AND UNIT PRICES

3.01 Bidder will perform the following Work at the indicated unit prices:

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

PHASE I

Unit Price Bid Items – Base Bid Option 1: FFRP

No. Description Estimated Quantity

Unit Bid Unit Price Bid Amount

A GENERAL CONDITIONS

1 Mobilization 1 LS

2 Bonds and Insurance 1 LS

B WATER IMPROVEMENTS

16" Flexible Fabric-Reinforced Pipe

(FFRP)

12,202 LF

16" Stub Out Assembly and Butterfly Valves

2 EA

3 Connection To Existing Water Line 4 EA

4 Air Release Valve 2 EA

Fire Hydrant Assembly with 6” Gate Valve

1 EA

C COMMON WORK

1 Sediment and Erosion Control 1 LS

2 Pipe Cleaning and Inspection 12,202 LF

3 Testing (Pressure and BacT) 1 LS

4 Traffic Control 1 LS

5 Asphalt Pavement Replacement 136 SF

Total Base Bid Option 1: FFRP Amount $

$_____________________________________________________________________ DOLLARS

(Total in Words)

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Unit Price Bid Items – Base Bid Option 2: CIPP

No. Description Estimated Quantity

Unit Bid Unit Price Bid Amount

A GENERAL CONDITIONS

1 Mobilization 1 LS

2 Bonds and Insurance 1 LS

B WATER IMPROVEMENTS

1 16" Cured-in-place pipe (CIPP) 12,202 LF

16" Stub Out Assembly and Butterfly Valves

2 EA

3 Connection to Existing Water Line 4 EA

4 Air Release Valve 2 EA

Fire Hydrant Assembly with 6” Gate

2 Pipe Cleaning and Inspection 12,202 LF

3 Testing (Pressure and BacT) 1 LS

4 Traffic Control 1 LS

5 Asphalt Pavement Replacement 136 SF

Total Base Bid Option 2: CIPP Amount $

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Alternate 1 – Water Line Connection and Fire Hydrant

No. Description Estimated Quantity

Unit Bid Unit Price Bid Amount

A GENERAL CONDITIONS

1 Mobilization 1 LS

2 Bonds and Insurance 1 LS

B WATER IMPROVEMENTS

1 16" DIP Piping and Connection to Existing Lines

1 LS

Fire Hydrant Assembly with 6” Gate

3 16" Butterfly Valve 6 EA

4 Air Release Valve 1 EA

C COMMON WORK

2 Testing (Pressure and BacT) 1 LS

Total Alternate 1: Bid Water Line Connection and Fire Hydrant Amount $

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

PHASE II

Alternate 2: HDD North

No. Description Estimated Quantity

Unit Bid Unit Price Bid Amount

A GENERAL CONDITIONS

1 Mobilization 1 LS

2 Bonds and Insurance 1 LS

B WATER IMPROVEMENTS

1 16" HDD Fusible PVC 826 LF

2 16" PVC Restrained Pipe 31 LF

3 Concrete Collar / Transition and 16” DIP Fittings

2 LS

4 Connection To Existing Stub Out 2 EA

5 Remove 16” Steel Pipe from Bridge and Capped on Each Side

2 Testing (Pressure and BacT) 1 LS

3 Concrete Pavement Replacement 450 SF

4 Asphalt Pavement Replacement 675 SF

Total Alternate 2: HDD North Bid Amount $

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Alternate 3: HDD South

No. Description Estimated Quantity

Unit Bid Unit Price Bid Amount

A GENERAL CONDITIONS

1 Mobilization 1 LS

2 Bonds and Insurance 1 LS

B WATER IMPROVEMENTS

1 16" HDD Fusible PVC 799 LF

2 16" Fusible PVC 42 LF

3 16” PVC Restrained Pipe 111 LF

4 Concrete Collar / Transition and 16” DIP Fittings

2 LS

5 Connection to Existing Water line 2 EA

6 Air Release Valve 1 EA

Fire Hydrant Assembly with 6” Gate

8 Remove 16” Steel Pipe from Bridge and Capped on Each Side

2 Testing (Pressure and BacT) 1 LS

Total Alternate 3: HDD South Bid Amount $

At its sole discretion, Owner will award the Contract based on the selection of Base Bid of the lowest responsive bid between Option 1 or Option 2 and any combination of Alternates, depending on what is determined to be in the best interest of the project and the Owner. To be considered responsive, Bidders should ensure that all pricing and documentation for both the Base Bid Options and each of the

Alternates are complete and accurate, as all Alternates may be selected for award.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, ARTICLE 4—TIME OF COMPLETION

4.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

4.02 Bidder accepts the provisions of the Agreement as to liquidated damages.

ARTICLE 5—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF

ADDENDA

5.01 Bid Acceptance Period

A. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

5.02 Instructions to Bidders

A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.

5.03 Receipt of Addenda

A. Bidder hereby acknowledges receipt of the following Addenda:

Addendum Number Addendum Date

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Bidder’s Representations

A. In submitting this Bid, Bidder represents the following:

1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.

2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.

4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, with respect to the Technical Data in such reports and drawings.

5. Bidder has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

the Supplementary Conditions, with respect to Technical Data in such reports and drawings.

6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and

(c) Bidder’s (Contractor’s) safety precautions and programs.

7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.

8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

6.02 Bidder’s Certifications

A. The Bidder certifies the following:

1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.

2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.

3. Bidder has not solicited or induced any individual or entity to refrain from bidding.

4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 8.02.A:

a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.

b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.

d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

BIDDER hereby submits this Bid as set forth above:

Bidder:

(typed or printed name of organization)

By:

(individual’s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

(typed or printed)

If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.

Attest:

(individual’s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

Address for giving notices:

Bidder’s Contact:

Name:

(typed or printed)

Title:

(typed or printed)

Phone:

Email:

Address:

Bidder’s Contractor License No.: (if applicable)

END OF SECTION

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, SECTION C-430

Bid Bond

EJCDC® C-430, Bid Bond (Penal Sum Form).

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

BID BOND (PENAL SUM FORM)

Bidder Surety

Name: Name:

Address (principal place of business): Address (principal place of business):

Owner Bid

Beaufort-Jasper Water & Sewer Authority

Project (name and location):

Address (principal place of business): CIP-2305 Parris Island (PI) 16-Inch Steel Water Transmission Main Replacement (Malecon Drive) 6 Snake Road, Okatie, SC 29909

Bid Due Date:

Bond

Penal Sum:

Date of Bond:

Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth in this Bid Bond, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.

Bidder Surety

(Full formal name of Bidder) (Full formal name of Surety) (corporate seal)

By: By:

(Signature) (Signature) (Attach Power of Attorney)

Name: Name:

(Printed or typed) (Printed or typed)

Title: Title:

Attest: Attest:

(Signature) (Signature)

Name: Name:

(Printed or typed) (Printed or typed)

Title: Title:

Notes: (1) Note: Addresses are to be used for giving any required notice. (2) Provide execution by any additional parties, such as joint venturers, if necessary.

EJCDC® C-430, Bid Bond (Penal Sum Form).

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond.

Payment of the penal sum is the extent of Bidder’s and Surety’s liability. Recovery of such penal sum under the terms of this Bond will be Owner’s sole and exclusive remedy upon default of Bidder.

2. Default of Bidder occurs upon the failure of Bidder to deliver within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.

3. This obligation will be null and void if:

3.1. Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents, or

3.2. All Bids are rejected by Owner, or

3.3. Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph…