About this file

This appendix document from the Alabama Department of Transportation establishes the referenced standard specifications sections that govern the Oyster Bay Restoration Project, a highway and drainage infrastructure improvement initiative in Baldwin County, Alabama. The project scope includes installation of three precast concrete box culverts (8 feet by 4 feet) beneath Waterway West Boulevard in Gulf Shores, associated road and safety improvements, and cleaning and modifications of four existing drainage structures. All work must be completed within 180 working days following contract award. Proposals are due July 23, 2026. The specifications referenced in this appendix establish technical requirements across twenty-two standard specification sections covering clearing and grubbing, excavation and embankment, geosynthetics, soil and aggregate materials, asphalt pavements, concrete work, reinforced concrete culverts, guardrails, erosion control, and traffic management.

The project is federally funded through RESTORE Act grant awards and subject to OMB Uniform Guidance (2 CFR Part 200) and Treasury regulations (31 CFR 34). Contractors must register with SAM.gov with an active Unique Entity Identifier and maintain registration throughout the project period. Federal compliance requirements include non-discrimination and equal employment opportunity provisions, domestic procurement preferences, small business and minority business enterprise participation, and environmental compliance under NEPA, the Endangered Species Act, Clean Water Act, and Coastal Zone Management Act. All federal compliance requirements must flow down to subcontractors and vendors. Semi-annual Federal Financial Reports and performance reports are required, with records retained for a minimum of three years. The contract uses a unit pricing structure and incorporates detailed technical specifications, geotechnical reports, permits, and construction plans.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Appendix C: Referenced Sections of the Alabama Department of Transportation - Standard Specifications for Highway Construction 2018 Edition

Section 108.04(b)3. Contractor’s Stormwater Management Plan

Section 201 Clearing and Grubbing

Section 206 Removal of Miscellaneous Existing Drainage and Other Facilities

Section 210 Excavation and Embankment

Section 214 Structure Excavation and Backfill for Drainage and Minor Structures

Section 231 Stabilized Roadbed

Section 243 Geosynthetics for Slope and Soft Soil Reinforcement

Section 301 Soil, Soil Aggregate, and Aggregate, Base and Subbases

Section 401 Bituminous Surface Treatments

Section 405 Tack Coat

Section 410 Asphalt Pavements

Section 424 Superpave Bituminous Concrete Base, Binder, and Wearing Surface Layers

Section 502 Steel Reinforcement

Section 524 Reinforced Concrete Culverts

Section 534 Cleaning Existing Drainage Structures

Section 600 Mobilization

Section 620 Minor Structure Concrete

Section 630 Guardrail and Barrier Rail

Section 640 Minor Utility Adjustments

Section 665 Temporary Soil Erosion and Sediment Control

Section 701 Traffic Stripe

Section 740 Traffic Control Devices for Construction Work Zones